ID Task Name Start Finish October November December January February March April May June July August

Oct Nov Dec Jan Feb Mar Apr May Jun Jul
1 1 General Fri 15/12/23 Fri 15/12/23 15/12
2 1.1 Signing Contract Fri 15/12/23 Fri 15/12/23 15/12
3 2 Material Procurement, Importing & Approvement Thu 21/12/23 Wed 21/02/24
4 2.1 Materials Supplying and Procurement from abroad Thu 21/12/23 Wed 21/02/24
5 2.2 Materials Supplying and Procurement from local marketing Thu 21/12/23 Wed 10/01/24
6 2.3 Preparation of Materials in the stock and samples for Thu 21/12/23 Wed 10/01/24
UNOPS approvement
7 2.4 Material Approval Thu 21/12/23 Wed 10/01/24
8 3 Preparation Work Thu 21/12/23 Thu 18/01/24
9 3.1 Site assessment, surveys for the roof slabs & Thu 21/12/23 Thu 18/01/24
relocating the existing water tanks and other obstacles
10 3.2 Submit the excutive HSE plan and update Project Thu 21/12/23 Wed 10/01/24
implementation plan.
11 3.3 Roof Mounting structures Stock Thu 21/12/23 Wed 10/01/24
12 3.4 Receiving the sites from the supervising engineers by Thu 21/12/23 Wed 10/01/24
the funders
13 3.5 Team division and task assignment for each team Thu 21/12/23 Wed 27/12/23
14 4 Material Supply to site Fri 05/01/24 Mon 27/05/24
15 4.1 CIVIL materials: Cement, CONCRETE etc. Fri 05/01/24 Thu 18/01/24
16 4.2 Mounting Structure & cable tray supply Fri 05/01/24 Thu 18/01/24
17 4.3 Inverters/ Chargers Supply Fri 05/01/24 Thu 18/01/24
18 4.4 Mppt control &monitring system supply Fri 05/01/24 Thu 18/01/24
19 4.5 DC Cable & AC Cable Supply Fri 05/01/24 Thu 18/01/24
20 4.6 AC Panels, MDBs & DC Boxes Supply Fri 05/01/24 Thu 18/01/24
21 4.7 PV Modules Supply (available Stock) Fri 05/01/24 Thu 18/01/24
22 4.8 Booster Pump unit set Thu 14/03/24 Tue 02/04/24
23 4.9 RMU, DISTRIBUTION TRANSFORMERS AND Wed 21/02/24 Fri 01/03/24
TERMINATION AND ALL ACCESSORIES
24 4.10 Earthing/Lightning Components Fri 05/01/24 Fri 19/01/24
25 4.11 Air conditioners and Ventiltation system components Fri supply
05/01/24 Fri 19/01/24
26 4.12 Fire alarm system components: Panels, Smoke & Fri 05/01/24 Fri 19/01/24
Heat Detectors MCPs, etc.
27 4.13 Site Installation Mon 15/01/24 Mon 27/05/24
28 4.13.1 CIVIL WORK Fri 19/01/24 Mon 19/02/24
29 4.13.1.1 CONCRETE WORKs & CONTROL ROOMS WORKS Fri 19/01/24 Mon 19/02/24
30 4.13.1.2 Relocation o, any other obstacles in facilities'Fri 19/01/24 Mon 19/02/24
31 4.13.1.3 Mounting Structure Installation Fri 19/01/24 Mon 19/02/24
32 4.13.1.4 Undergroung Cable Trench Fri 19/01/24 Mon 19/02/24
33 4.13.2 Electrical Work Mon 15/01/24 Mon 27/05/24
34 4.13.2.1 PV Installations Tue 20/02/24 Mon 01/04/24
35 4.13.2.2 DC combiner boxes Installation Tue 20/02/24 Wed 27/03/24
36 4.13.2.3 Charger Controls Installation & Accessories Mon 15/01/24 Tue 20/02/24
37 4.13.2.4 DC breaker boxes Installation, Busbar and Accessories
Mon 15/01/24 Tue 20/02/24
38 4.13.2.5 Inverters Installation and accessories Mon 15/01/24 Tue 20/02/24
39 4.13.2.6 Booster pumping units Mon 15/01/24 Wed 28/02/24
40 4.13.2.7 mechanical components and Booster Wed 03/04/24 Mon 27/05/24
pumping accessories
41 4.13.2.8 Cable laying and connection Mon 15/01/24 Wed 13/03/24
42 4.13.3 AC Installations Wed 31/01/24 Thu 25/04/24
43 4.13.3.1 RMU, DISTRIBUTION TRANSFORMERS AND Fri 01/03/24 Thu 28/03/24
TERMINATION AND ALL ACCESSORIES
44 4.13.3.2 MDBs ,PANELS, MTS &ATS Installation Wed 31/01/24 Tue 26/03/24
45 4.13.3.3 Earthing/Lightning protection Installation Fri 01/03/24 Thu 25/04/24
46 4.13.4 Other Components Mon 15/01/24 Mon 11/03/24
47 4.13.4.1 LEDs Lighting system installation and wiring. Mon 15/01/24 Tue 20/02/24
48 4.13.4.2 Ventilation and air conditioners installation. Sat 10/02/24 Mon 11/03/24
49 4.13.4.3 Installation and wiring of Conventional Fire alarm
Mon 22/01/24
system panel
Tueand
20/02/24
its detectors
50 5 Commissioning, Training & Handover Tue 28/05/24 Mon 17/06/24
51 5.1 Testing and Training for Users Tue 28/05/24 Mon 17/06/24
52 5.2 As-Built drawings, Commissioning & Handover. Tue 28/05/24 Mon 17/06/24

Task Summary Inactive Milestone Duration-only Start-only External Milestone Baseline Milestone Manual Progress
Project: Project1
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Baseline Summary
Date: Sat 02/12/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Baseline Progress

Page 1