PROJECT FOR PROPOSED CONSTRUCTION OF REPORTING OFFICE, STAFF HOUSING, WATER AND SANITATION STRUCTURES IN SARIF POLICE STATION

BANANEY INVESTMENTS CO. LTD


P.O BOX 68678 – 00622
NAIROBI
SITE WORKS PROGRAMME
ID Task Name Duration Start Finish 30 Oct '22 06 Nov '22 13 Nov '22 20 Nov '22 27 Nov '22 04 Dec '22 11 Dec '22 18 Dec '22 25 Dec '22 01 Jan '23 08 Jan '23 15 Jan '23 22 Jan '23 29 Jan '23 05 Feb '23 12 Feb '23 19 Feb '23 26 Feb '23 05 Mar '23 12 Mar '23 19 Mar '23 26 Mar '23 02 Apr '23
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
1 PROJECT FOR PROPOSED 110 days Tue 01/11/22 Mon 03/04/23
CONSTRUCTION OF
REPORTING OFFICE, STAFF
HOUSING, WATER AND
SANITATION STRUCTURES
IN SARIF POLICE STATION
2 ACCOMODATION BLOCK 110 days Tue 01/11/22 Mon 03/04/23
AND OFFICE
3 MOBILIZATION 8 days Tue 01/11/22 Thu 10/11/22
4 SUBSTRUCTURES 25 days Wed 09/11/22 Tue 13/12/22
5 SITE CLEARANCE 3 days Wed 09/11/22 Fri 11/11/22
6 SETTING OUT 3 days Mon 14/11/22 Wed 16/11/22
7 EXCAVATIONS 8 days Tue 15/11/22 Thu 24/11/22
8 FOUNDATION 4 days Mon 21/11/22 Thu 24/11/22
BLINDING
9 FOUNDATION 5 days Tue 22/11/22 Mon 28/11/22
CONCRETE
10 FOUNDATION 10 days Mon 28/11/22 Fri 09/12/22
WALLING
11 FDN COLUMNS 4 days Thu 01/12/22 Tue 06/12/22
12 BACKFILLING & 7 days Mon 05/12/22 Tue 13/12/22
HARDCORE
13 BLINDING 2 days Wed 07/12/22 Thu 08/12/22
14 FLOOR BEDS 4 days Thu 08/12/22 Tue 13/12/22
15 FRAME 13 days Wed 07/12/22 Fri 23/12/22
16 GROUND BEAM 5 days Wed 07/12/22 Tue 13/12/22
17 COLUMNS 5 days Mon 19/12/22 Fri 23/12/22
18 EXTERNAL WALLING 13 days Wed 14/12/22 Fri 30/12/22
19 INTERNAL WALLING 14 days Wed 14/12/22 Mon 02/01/23
20 ROOFING WORKS 22 days Tue 03/01/23 Wed 01/02/23
21 SLAB FORMWORK 10 days Tue 03/01/23 Mon 16/01/23
22 SLAB STEEL FIXING 10 days Mon 16/01/23 Fri 27/01/23
23 SLAB CONCRETE 3 days Mon 30/01/23 Wed 01/02/23
WORKS
24 EXTERNAL FINISHING 13 days Thu 02/02/23 Mon 20/02/23
25 EXTERNAL PLASTER 6 days Thu 02/02/23 Thu 09/02/23
26 EXTERNAL PAINTING 4 days Wed 15/02/23 Mon 20/02/23
27 INTERNAL FINISHING 8 days Thu 02/02/23 Mon 13/02/23
28 INTERNAL PLASTER 5 days Thu 02/02/23 Wed 08/02/23
29 INTERNAL PAINTING 3 days Thu 09/02/23 Mon 13/02/23
30 FLOOR FINISHING 5 days Tue 14/02/23 Mon 20/02/23
31 FLOOR SCREEDING 5 days Tue 14/02/23 Mon 20/02/23
32 CEILING FINISHING 45 days Mon 02/01/23 Fri 03/03/23
33 PLASTER 5 days Mon 02/01/23 Fri 06/01/23
34 PAINTWORKS 6 days Thu 23/02/23 Thu 02/03/23
35 CEILING PAINTING 3 days Tue 28/02/23 Thu 02/03/23
36 DOORS AND 5 days Mon 27/02/23 Fri 03/03/23
WINDOWS
37 SPECIALIZED WORKS 80 days Tue 13/12/22 Mon 03/04/23
38 FIXTURES AND 40 days Tue 07/02/23 Mon 03/04/23
FITTINGS
39 PLUMBING & 60 days Tue 20/12/22 Mon 13/03/23
MECHANICAL
40 WORKS
ELECTRICAL WORKS 70 days Tue 13/12/22 Mon 20/03/23
41 ELEVATED WATER 15 days Mon 06/03/23 Fri 24/03/23
TANK
42 FENCING WORKS 18 days Fri 03/03/23 Tue 28/03/23
43 PROJECT COMPLETION 0 days Mon 03/04/23 Mon 03/04/23 03/04
44 PROJECT INSPECTION 0 days Mon 03/04/23 Mon 03/04/23 03/04
45 SITE HANDOVER 1 day Tue 04/04/23 Tue 04/04/23

Project: Project1 Task Milestone Project Summary External Milestone Inactive Summary Duration-only Manual Summary Finish-only External Milestone Deadline
Date: Sat 17/09/22
Split Summary External Tasks Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Progress

Page 1