ID Task Task Name Duration Start Finish Predecessors May 18, '24 May 25, '24 Jun 1, '24

Predecessors May 18, '24 May 25, '24 Jun 1, '24 Jun 8, '24 Jun 15, '24 Jun 22, '24 Jun 29, '24 Jul 6, '24 Jul 13, '24 Jul 20, '24 Jul 27, '24 Aug 3, '24 Aug 10, '24 Aug 17, '24 Aug 24, '24 Aug 31, '24 Sep 7, '24 Sep 14, '24 Sep 21, '24 Sep 28, '24 Oct 5, '24 Oct 12, '24 Oct 19, '24 Oct 26, '24 Nov 2, '24 Nov 9, '24
Mode S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
1 OFFICE PARK 5TH AND 6TH FLOOR 142 days Tue 5/21/24 Thu 11/7/24
2 REMOVAL OF EXISTING 30 days Tue 5/21/24 Sat 6/29/24
WATERPROOF @6TH FLOOR LEVEL
3 Mobilization of scaffolding material 3 days Tue 5/21/24 Thu 5/23/24
from triangular area to site location
and shifting same to the work
location by using crane
4 Erection of scaffolding at radar area 3 days Sat 5/25/24 Mon 5/27/24 3
,rectangular area and traingle
portion area for access of men and
material
5 Inspection of erected scaffolding 1 day Tue 5/28/24 Tue 5/28/24 4
and getting approval with inspector
6 Removal of aggregate from 6th 3 days Wed 5/29/24 Sat 6/1/24 5
floor radar area by using chute and
dropping at 5th floor-PART-1
7 Removal of aggregate from 6th 3 days Wed 5/29/24 Sat 6/1/24 5
floor rectangle area by using chute
and dropping at 5th floor-PART-2
8 Removal of aggregate from 6th 10 days Wed 5/29/24 Sun 6/9/24 5
floor triangle area by using chute
and dropping at 5th floor-PART-3
9 Removing of aggregate from the 12 days Sat 6/1/24 Thu 6/13/24 6FS-4 days
chute area to the crane location
point using wheel barrow
10 Removal of waterproof membrane 3 days Sun 6/2/24 Tue 6/4/24 6
from 6th floor radar area and
dropping at 5th floor-PART-1
11 Removal of waterproof membrane 3 days Sun 6/2/24 Tue 6/4/24 7
from 6th floor rectangle area and
dropping at 5th floor-PART-2
12 Removal of waterproofing 5 days Wed 6/5/24 Mon 6/10/24 8FS-4 days
membrane from 6th floor triangle
area and dropping at 5th
floor-PART-3
13 Shifting of aggregate and 20 days Sun 6/2/24 Sat 6/29/24 7
waterproof membrane from the
crane point to the ground floor
using concrte trash skip
14 WATERPROOFING 56 days Sat 6/1/24 Thu 8/8/24
15 Shifting of construction materials 113 days Sat 6/1/24 Tue 10/15/24
from MTD store to site location
16 Providing Haunch -PART-1 3 days Wed 6/5/24 Sat 6/8/24 10
17 Apply water proofing primer 3 days Sun 6/9/24 Tue 6/11/24 16
BITUMAT BITUPRIME of two coat in
radar area
18 Laying of water proofing sheets 3 days Tue 6/11/24 Thu 6/13/24 17FS-1 day
BITUMAT POLYFLAME
19 Filling water test for 48 hours and 5 days Wed 6/19/24 Mon 6/24/24 18
remove water after
inspection(PART-1)
20 Providing Haunch -PART-2 3 days Wed 6/5/24 Sat 6/8/24 11
21 Apply water proofing primer 3 days Sat 6/8/24 Mon 6/10/24 20FS-1 day
BITUMAT BITUPRIME of two coat in
rectangular area
22 Laying of water proofing sheets 3 days Tue 6/11/24 Thu 6/13/24 21
BITUMAT POLYFLAME
23 Filling water test for 48 hours and 5 days Wed 6/19/24 Mon 6/24/24 22
remove water after
inspection(PART-2)
24 Providing Haunch -PART-3 4 days Tue 6/11/24 Wed 6/19/24 12
25 Apply water proofing primer 6 days Wed 6/19/24 Tue 6/25/24 24FS-1 day
BITUMAT BITUPRIME of two coat in
triangle area
26 Laying of water proofing sheets 5 days Mon 6/24/24 Sat 6/29/24 25FS-2 days
BITUMAT POLYFLAME
27 Filling water test for 48 hours and 5 days Sun 6/30/24 Thu 7/4/24 26
remove water after
inspection(PART-3)
28 Laying of polystyrene board 15 days Tue 6/25/24 Thu 7/11/24 19
29 Bull mark for water slope to the 15 days Thu 6/27/24 Sun 7/14/24 28FS-13 days
existing drain
30 Laying of cement tiles 25 days Sun 6/30/24 Sun 7/28/24 29FS-13 days
400X400X40MM
31 Grouting of tile joints 24 days Sat 7/6/24 Thu 8/1/24 30FS-20 days
32 Apply water proofing top 2 coat 20 days Sat 7/13/24 Sun 8/4/24 31FS-18 days
paint JOTA ROOF over PRIMERED
cement tiles
33 Fixing of Aluminium wall trim with 18 days Sat 7/20/24 Thu 8/8/24 32FS-14 days
elastometric sealant
34 REMOVAL OF EXISTING 38 days Sun 6/30/24 Mon 8/12/24
WATERPROOF @5TH FLOOR LEVEL
35 removal of aggregate from 5th 20 days Sun 6/30/24 Mon 7/22/24
floor and dropping at crane
lifting point
36 removal of waterproof 20 days Thu 7/11/24 Sat 8/3/24 35FS-10 days
membrane from 5th floor and
dropping at crane lifting point
37 Shifting of aggregate and 25 days Wed 7/17/24 Wed 8/14/24 36FS-15 days
waterproof membrane from the
crane point to the ground floor
using concrte trash skip
38 WATERPROOFING 92 days Tue 7/23/24 Thu 11/7/24
39 Providing Haunch 10 days Tue 7/23/24 Sat 8/3/24 36FS-10 days
40 Apply water proofing primer 10 days Mon 7/29/24 Thu 8/8/24 39FS-5 days
BITUMAT BITUPRIME of two coat
41 Laying of water proofing sheets 10 days Tue 8/6/24 Sat 8/17/24 40FS-3 days
BITUMAT POLYFLAME
42 Filling water test for 48 hours and 5 days Sun 8/18/24 Thu 8/22/24 41
remove water after inspection
43 Laying of polystyrene board 10 days Sat 8/24/24 Tue 9/3/24 42
44 Bull mark for water slope to the 5 days Wed 9/4/24 Mon 9/9/24 43
existing drain
45 Laying of cement tiles 15 days Tue 9/10/24 Sat 9/28/24 44
400X400X40MM
46 Grouting of tile joints 10 days Sun 9/29/24 Wed 10/9/24 45
47 Apply water proofing top 2 coat 15 days Thu 10/10/24 Sun 10/27/24 46
paint JOTA ROOF over PRIMERED
cement tiles
48 Fixing of Aluminium wall trim with 10 days Mon 10/28/24 Thu 11/7/24 47
elastometric sealant

Project: OFFICE PARK 5TH AND Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Sat 3/30/24 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress