Module Name: Engineering Project Management

Module Title: 19MANE01I


Project Brief
An exploration company was awarded a new concession in the Eastern desert with commitment to perform
a 100-sq. km of seismic and drilling a new well within the 3 years of the exploration phase. The company
would like to use engineering project management to full fill its obligation on time. The main target is to
perform the seismic and drill the well. The seismic should include, seismic acquisition, processing and
interpretation, and then the drilling will start.

For both of the seismic and drilling you need to have permits from the following departments: -
• Ministry of Defense
• Ministry of Interior
• Ministry of Antiquities
• Ministry of Transportation
• Ministry of Communication
• Ministry of Electricity
• Environmental Authority
• Ministry of Irrigation
• EGAS and Ministry of Petroleum
Note: -
For each service or purchase you need to have a tender.

ACTIVITY, PREDECESSOR & DURATION:


1. Preliminary G&G study to detect the seismic area 61 days
2. Tender for 3D seismic
a. Invitation 8 days
b. Receive offer 15 days
c. Technical evaluation 15 days
d. Award 1 week
3. Permits 90 days
4. Seismic acquisition 6 months
5. Tender for Seismic processing
a. Invitation 7 days
b. Receive offer 15 days
c. Technical evaluation 15 days
d. Award 1 week
6. Seismic processing 6 months
7. Seismic interpretation 2 months
8. Define prospects 2 weeks
9. Rank prospect 2 weeks
10. Detect the first location to be drilled
a. Approval 1 week
b. Permits 90 days
i. Army permits 90 days
ii. Environmental permits 60 days
c. Tendering for rigs and service company 1 month
d. Tender for materials 1 month
Module Name: Engineering Project Management
Module Title: 19MANE01I
e. Purchasing the materials 3 months
11. Drilling well base of design 1 month
12. Cost estimate 2 weeks
13. Access road and Well site preparation 2 months
14. Rig move 2 weeks
15. Drilling well 46 days
a. Drill the 500 ft section 5 days
b. Run conductor casing 1 day
c. Mix the mud for the second section 1 day
d. Drill the second section 8 days
e. Run surface casing & cement 2 days
f. Rig up the BOP 1 day
g. Mix the mud for the third section 1 day
h. Drill the third section 10 days
i. Run intermediate casing & cementing 5 days
j. Mix the mud for the fourth section 1 day
k. Drill the fourth section 5 days
l. Run production casing & cementing 3 days
m. Run the production liner 1 day
n. Install the SSSV 0.5 day
o. Install packer 0.5 day
p. Perforate the promising interval 1 day
16. Test the well 2 weeks
17. Commercial announce 1 week

Project Requirements: -
 Write a brief introduction about the main idea of the project (1000 words)
 Set the calendar to match the petroleum industry
 Enter the tasks, durations, predecessors
 Adjust the Gantt chart
 Enter appropriate milestones and explain your choice
 Print the Gantt chart and project network showing the critical path (on A3 papers)
 Construct an AON diagram showing ES, EF, LS, LF, slack, duration, and the critical path.
(This should be done on a separate A3 paper by hand)

 Write 1 page minutes of meeting (individually).


The deadline for submitting the project is on Sunday 2nd of December 2019.