Professional Documents
Culture Documents
CASE DESCRIPTION
1) The Contractor is constructing a structural steel building
2) During excavation works (critical activity), a broken pump resulted in a 2-day delay
3) During erection of steel structure (critical activity), slow performance caused a 4-day delay
4) Slab execution is not a critical activity but it cannot be started until the roof is finished
5) Client delayed slab design by 11 days
WORKSHOP EXERCISES
As a specialist claims consultant, you have been asked to analyse the effect(s) the events had on the projec
lay
A Excavation 5 days
day delay
ished
B Foundation 7 days
D Roof 5 days
E Cladding 8 days
G Installations 5
4 days
& Concurrent.
H Finishes 4 days
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35
29 30 31 32 33 34 35
Legend
Float
ACTUAL
ACTIVITY ID DESCRIPTION DURATION Days 1 2 3 4 5 6 7 8 9 10 11 12 13 14
A Excavation 5 days
B Foundation 7 days
D Roof 5 days
E Cladding 8 days
F Slab 3 days
G Installations 4 days
H Finishes 4 days
H Finishes 4 days
Workshop Exercises
Raj
624667241.xls
MASTER WORKSHOP 16 - SOLUTION
Legend
Float
ACTUAL
ACTIVITY ID DESCRIPTION DURATION Days 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
A Excavation 7 days
B Foundation 7 days
D Roof 5 days
E Cladding 8 days
F Slab 3 days
H Finishes 4 days
DELAY ANALYSIS
Total -30,000.00 $
Raj
624667241.xls