CASE DESCRIPTION
Gang of 5 men (three carpenters and two steel fixers) was executing section of slab which is elemen
Critical Path. On fifth day Client Instruction issued for changing rebar design and increasing qty. Th
required dismantling of all executed reinforcement (two days - days 5 & 6), waiting time for new rebars
(three days - Days 5, 6 & 7) and assembly new reinforcement (one day more due to increased qty). On tenth
formwork supplier delayed supply last 20% of slab formwork for one day.
WORKSHOP EXERCISES
As a specialist claims consultant, you have been asked to analyse the effect(s) the events had on the
N
on of slab which is element of
sign and increasing qty. This
), waiting time for new rebars
ue to increased qty). On tenth day
SES
ct(s) the events had on the project.
Legend
Float
ACTUAL
ACTIVITY I DESCRIPTION Days 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
DURATION
A Preparation 1 day