Professional Documents
Culture Documents
Particular Construction
and Commissioning
Specifications
Uniform Technical Guidelines
H.1.1 General
Trenching works are steep temporary cuttings that are backfilled once a utility such
as a pipeline has been laid.
x For excavations not exceeding 1.2m, shoring support may not be required if
the ground is found to be self-supporting. If external loads are likely to be
present, or if there is doubt as to the stability of the trench sides due to weak
ground and/or high ground water table, especially in rainy weather, the
trench sides should be supported even if the excavation depth is less than
1.2m.
x The typical shoring details given in Figure H.1 may be acceptable for
depths up to 4.5m. Guidance on the design of shoring works can also be
found in Construction Industry Research and Information Association,
London (CIRIA) Report 97 on prescriptive design and Utilities Technical
Liaison Committee (UTLC) (2003).
ii. Liable to affect any road, building, structure, slope steeper than 30û,
water main 75mm in diameter or greater, the affected area being
defined as within 45û line up from the base of the excavation to the
ground surface.
x It is also not desirable to have the whole length of a long trench opened up
at any one time, even with support. Excavations should be in sections of
shortest practical length, preferably not more than 100 meters long.
1
Uniform Technical Guidelines
x The design and construction of trenching and shoring works shall consider
the following failure mechanisms:
iii. Heaving at base of excavation due to shear failure of the soil causing
local subsidence inside the trench.
iv. The erosive action of ground water, washing sand and silt into the
trench and causing local subsidence.
ii. Control infiltration of rainwater and water runoff from an open trench
into nearby slopes.
x Up-stands used together with trench covers have been found to be effective
in dealing with surface runoff. Up-stands are provided on either side of the
trench and can be made of compacted earth fill bunds cemented together.
The height of the up-stand shall be determined by the designer but shall not
be less than 10 cm.
1
Uniform Technical Guidelines
x Pumping from small sumps shall be provided for all trenches located at
slope crest, on slopes or in flood prone areas and opened up in the rainy
season.
H.1.4 Shoring
x Where the ground conditions are poor and have little “free-standing” time,
the installation of sheeting, excavation and insertion of waling and struts
shall proceed in stages until the full excavation depth is achieved.
x When removal of struts are required in order to give access during lowering
of pipes, equipment or compaction of backfill, only the minimum practicable
number of struts should be removed. The ground shall be adequately
supported at all times while workers are in the trench.
11
Uniform Technical Guidelines
Water Beam
Strut 1000 max
1500 max
1000 max
Figure H.1: Typical sheet pile shoring detail with steel struts and water beams
Notes:
H.2.1 Inspection
11
Uniform Technical Guidelines
c. The inspection of the installation of any pipes in a building will focus on the
following:-
a. Plumbing System
vi. The completed system shall be inspected for leaks during the test.
The pipe installation is considered to have passed the hydrostatic
test if no visible leak and no drop in the pressure reading are
observed during the test.
i. If the water for testing the underground pipe is obtained from the
supply main, the supply main shall be disconnected or isolated
before commencement of the test.
iii. Water shall be filled slowly to allow air to be expelled from the
system.
12
Uniform Technical Guidelines
vLL. 3ULRUWRWKHSUHVVXUHDQGOHDNDJHWHVWWKHZHLJKWWKUXVWDQGDQFKRU
EORFNV PXVW EH ILUVW LQVWDOOHG LQ RUGHU WR HQVXUH QR SLSH PRYHPHQW
GXULQJWKHWHVW
viLL. 7KHVH WHVWV VKDOO EH FRQGXFWHG IRU WKH HQWLUH V\VWHP LQFOXGLQJ
LQVWDOODWLRQVWDSSLQJWHHVIHUUXOHFRPSRQHQWVDQGWKHFRQQHFWLQJSLSH
DIWHU LW KDV EHHQ LQVWDOOHG RU FRQQHFWHG WR WKH H[WHUQDO UHWLFXODWLRQ
SLSHV
L[. $OOOHDNVGHWHFWHGGXULQJSUHVVXUHDQGOHDNDJHWHVWVKDOOEHUHSDLUHG
DQGWKHVDLGVHFWLRQVKDOOEHUHWHVWHGDIWHUWKHUHSDLULVFRPSOHWHG
[. 'HWDLOUHVXOWVRISUHVVXUHDQGOHDNDJHWHVWVPXVWEHLQFOXGHGDVSDUW
RIWKHKDQGLQJRYHUGRFXPHQWVWRWKHRSHUDWRU
a. Flushing
b. Disinfection
11
Uniform Technical Guidelines
ii. For safety reasons, the systems, or any parts of the systems shall
not be used during the duration where disinfection is being carried
out.
iii. The procedure for disinfection of piping system within a building shall
be in accordance with Section 6.1.10.4 of BS 6700:2006.
iv. After flushing, water samples shall be taken from the selected fittings
and sent for biological analysis by an accredited laboratory. The
water quality shall conform to the guidelines published by the
Ministry of Health.
construct the works in such a way that the intent of the design is not
undermined.
x The Competent Person shall review and approve the Contractor’s proposed
method statement so as to maintain the integrity of existing structures or
service lines, etc. on the adjacent sites.
1