Professional Documents
Culture Documents
04
planning.
Always assure that you provide margin as required under law
If it is a big river, decide the depth of foundation in consultation with a geotechnical engineer as
well as a structural engineer, based on the scour depth of the river, type of riverbed soil and highest
flood level
Plan for best possible river and embankment protection
Make sure that the water does not rush from the waterbody. Maintain earth which act as bunds
Avoid excavation during monsoon, particularly in rivers where there are possibilities of flash flood
Don’t do work nor decide the depth of foundation without proper geotechnical investigation.
(i) Supervision: Inspection and Documentation
(I) Supervision
It is the statutory responsibility of the employer to provide constant and adequate supervision.
Under the employer’s guidance, the project manager/supervisor is the key person to ensure that the
work is carried out with due regard for quality, progress, estimate-cost and, above all, safety.
The project manager/supervisor should fully utilize the guidance of the safety officer. He should
keep up the skill level of the workers by identifying and fulfilling their training needs.
He should also keep them motivated by providing a work environment which satisfies their
human needs. He should remember, a participative and persuasive attitude is more faithful than a
punitive attitude for maintaining safety and discipline at site.
II) Inspection and Documentation:
Building Inspector
For daily supervision work, the
supervisor should maintain a daily report.
It should contain the particulars of all the
technical aspects of the excavation work,
the safety status of the site and the
actions taken to ensure safety.
A weekly inspection register of
excavation work is mandatory. This
record and documentation are important
to prove that you have taken all practical
steps to prevent accidents, in case there
are any legal requirements or
emergencies.
(j) Back Filling
Backfilling of Earth Soil
The excavated pit or area should be filled up to the ground level as soon as the
constructed structure permits back filling
Before back filling ensure that all underground utilities are properly
joined/supported and need no further protection
60 cm thick rubble/gravel packing should be provided behind retaining walls,
before back filling, to permit drainage of water through the weep holes in the
retaining wall
The back-filling material should be spread in layers, watered and consolidated,
to avoid settlement at a later date. The ground may, thereafter, be turfed or
paved
In case of large open excavation work like open cast mines, back filling should
not to be done. The whole periphery should be fenced as per ‘miner rules’
In collieries, after completing the mining operation, the tunnels should be
packed with sand
As per ‘IBC (international building code)’ the excavation outside the foundation
shall be backfilled with soil that is free of organic material, construction debris,
cobbles and boulders or a controlled low-strength material (CLSM). The
backfill shall be placed in lifts and compacted, in a manner that does not
damage the foundation or the waterproofing or damp proofing material
Thank You ...