Professional Documents
Culture Documents
&
Line Madhure, Hosadurga.
Environment, Health and Safety Plan
ABLE OF CONTENTS: -
1. Purpose……………………………………………………………………………………………3
2. Environment, Health and Safety Policy………………………………………………………..4
3. Safe working procedure in Transmission Line………………………………………………..5
4. SAFE WORKING PROCEDURE FOR EXCAVATION
& FOUNDATION WORK………………………………………………………………………..5
5 Safe Work procedure for tower erection work………………………………………………..7
6. Safety measures to be taken while carrying out
assembly/ erection works Near power lines………………………………………………….9
7. Safe Work Procedure for Conductor Stringing………………………………………………10
8. SAFETY MEASURES TO BE TAKEN WHILE
ENCOUNTERING POWERLINE CROSSINGS…………………………………………….13
9. Precautions for stringing in the vicinity of charged Overhead
Lines and in areas where induced voltage is anticipated…………………………………..14
10. CLEARANCE REQUIRED FOR POWER LINES……………………………………………15
11. Material storage and Handling…………………………………………………………………16
12. CRANES AND LIFTING EQUIPMENTS……………………………………………………...17
13. Safe Working Procedures for Blasting………………………………………………………..18
14. Safe working procedure of welding……………………………………………………………19
15. Safe operating procedures for Gas cutting Operation………………………………………20
16. Safe Operating Procedures for Electrical Installation……………………………………….21
17. Safe Operating Procedures at Store………………………………………………………….22
18. Safe Working Procedures for Substation……………………………………………………..23
19. ERECTION OF DISTRIBUTION TRANSFORMERS………………………………………..30
20. Safe Operating Procedure for Power Transformer Erection………………………………..36
21. SAFETY RULE FOR SUBSTATION…………………………………………………………..42
22. SUBSTATION WORK PRACTICE…………………………………………………………….43
23. List of Personal protective equipment (PPE)…………………………………………………47
24. Earthing Schemes for shutdown operations………………………………………………….53
25. Emergency Preparedness plan………………………………………………………………...66
26. Emergency Response Committee……………………………………………………………...67
2|Page
Mr. Vijay Kumar Mr. Md. Shoaib Mr. Gudepu
Nayak Ansari Srinivas
Environment, Health and Safety Plan
1. Purpose:
The purpose of this HSE Management Plan is to define the HSE requirements and
objectives of the project as well as the processes and procedures that will govern actions to
ensure that Health, Safety & Environment requirements and objectives are satisfied during
all phases of the construction of this project.
EHS Policy shall be communicated to all the employees & workmen through display
boards, Posters, Safety Meetings & Pep Talk & etc.
3|Page
Environment, Health and Safety Plan
4|Page
Environment, Health and Safety Plan
5|Page
Environment, Health and Safety Plan
• Check with authorities about underground facilities like water line, sewer line, electric
cables or telephone cables and obtain proper permit and take proper precautionary
measures against the same before commencing any excavation
• Tool Box Talk shall be conducted by site engineer/contractor -gang supervisor daily and
will include topics of relevant activity and about HSE in the format EPC/EHS/FMT/08
• No excavation work is to be carried out unless the work is effectively supervised and
planned.
• In case there is movement of men or cattle in the vicinity of the excavation, the area is
to be suitably barricaded and warning signs displayed before starting any excavation
activity.
• Excavated earth / material must be placed at least 1.5 meter away from the edge of
the excavation.
• Precautions must be taken to ensure that boulders etc. do not fall back inside
the pit.
• All plants and machinery should be placed at least 2 meter away from the edge of the
pit to avoid collapse of the pit due to vibration produced by the machines. Wheel
blocks must be provided to avoid any undesired movement.
• All JCB / excavator must have a valid registration and insurance certificates and
operators working at site must hold valid driving license.
• The JCB /loader will be inspected by site supervisor as per format EPC/EHS/CKL/30
• No vehicular movement must be permitted within 2 meter from the edge of the
excavation.
• Excavations deeper than 5 ft. will require proper shoring or sloping depending on soil
conditions to advert pit collapse during excavation and foundation casting
• Proper and strong ladders must be used for access and egress into and out of
excavations by the workmen.
• Ensure that electrical connections for dewatering pumps, if any, do not cause any
danger to the workmen.
• After heavy rainfall, the site in charge should inspect the condition of the excavation. In
case there is a possibility of pit collapse, all activity must be
stopped immediately. Work must start only after ensuring adequate precautions
against the danger.
• Appropriate PPE's must be worn by workers at all times. PPE's required for excavation
activity includes safety helmets, shoes. All workers involved with the concreting work
must wear gumboots and gloves too.
• Workmen working at ground level above the projecting reinforcement bars must
protect themselves by suitable means against fall on the same.
• Template supporting jacks are to be placed evenly and as far away from the edge of
the pit as practicable.
• Wooden platform or sand bags are to be placed below the jacks for proper distribution
of load.
1. Tool Box Talk shall be conducted by site engineer/contractor -gang supervisor daily and will include
topics of relevant activity and about HSE in the format EPC/EHS/FMT/08
2. No erection work is to be carried out unless the work is supervised by effective and BEL staffs
and supervisors at all times when the erection work is in progress.
3. Fitters with sufficient skill and experience for the job only are to be permitted to
Carry out erection work.
4. Before commencing any erection work, medical fitness of all fitters must be ensured.
5. Workmen having any injury or those under the influence of drugs (prescription / illegal) or alcohol
must not be allowed to work on the tower under any circumstances.
6. Before starting the tower work, ensure that foundation has been properly backfilled.
7. Sufficient area for free movement of men and material must be ensured.
8. The condition of vehicles must be checked periodically. All vehicles in use at the Site must be
in good condition. The breaking systems should be checked Periodically and defective parts
if any must be rectified / replaced immediately.
9. All mobile crane /trucks/vehicle must have a valid registration and insurance and operators /
drivers must be well experienced, sufficiently qualified and trained and must hold a valid driving
8|Page
Environment, Health and Safety Plan
license.
10.All mobile crane shall be inspected as per format no. EPC/EHS/CKL/37
11.All Tools and tackles are to be thoroughly checked as per the format EPC/EHS/CKL/22 for their
healthiness
12.All tools and tackle’s healthiness has to be checked daily prior before starting the work by site
supervisor
13.Before commencing any lifting operations, it is to be ensured that the lifting
appliances and gear viz. derricks, lifting hooks, belts, slings, wire rope, PP rope, ‘D’
shackles, pulleys etc. to be used for erection work, are of good quality, of adequate capacity for
the job and in good condition. Defective material must not be used under any circumstances and
must be removed from site and replaced immediately.
14.Test certificates of all lifting appliances deployed at the site must be checked prior to erection
works.
15. Appropriate PPE’s shall be worn by all workers at all times. PPE’s required for this activity includes
safety helmets, safety shoes and gloves (if required).
16.All supervisors at the erection site must also wear safety helmets and safety shoes.
17. Workers working on towers are to always use full body double lanyard safety harness. All
straps of the safety harness must be properly tightened. It must be ensured that one
lanyard of the safety harness is properly anchored to a strong tower support at all times
while working, ascending / descending or during horizontal movements on the tower.
18.The healthiness of full body harness checked as per format EPC/EHS/CKL/17
19. Not more than two workers must secure their fall arresters on a single rope.
20. All PPE’s must be CE / ISI marked.
21.Workers shall wear safety shoes at all the time at site. Fitters who work on tower will wear canvas
shoes and the remaining workers shall wear leather safety shoes at the ground.
21. Towers are to be erected in a sequential manner. Work on the upper section must not be allowed
to start until all the members/diagonals and bracings of the lower section have been fully erected
and all nut bolts are properly tightened.
22. Fixing of two or more main leg members at ground level and erecting the same must not be
9|Page
Environment, Health and Safety Plan
28. For manual lifting of sections / heavy members, the hauling rope is to be supported with a strong
anchorage point to prevent slippage. The end of the hauling rope is to be wrapped around this
anchorage point by sufficient member of turns.
29. Wire / PP ropes used for tying pulleys etc. to the tower members must be adequately
padded with folded gunny bags to prevent damage.
30. No tower erection works shall be carried out after sunset.
31. Tower erection works shall not be carried out during inclement weather viz. dust storms,
windy weather, rains or storms. If thunderstorm is approaching, the work should be stopped
immediately.
36. Ensure the horizontal life line usage for horizontal movement on tower.
37. Ensure tower erection shall be carried out with the help of power winch
machine only, tractors shall be avoided.
10 | P a g e
Environment, Health and Safety Plan
1. No stringing work is to be carried out unless the work is effectively & competently
supervised at all times when the work is in progress.
2. Tool Box Talk shall be conducted by site engineer/contractor -gang supervisor daily will include topics
of relevant activity and about HSE in the format EPC/EHS/FMT/08 prior before start work
3. Before commencing any stringing work, ensure that, all the towers of the stringing section have been
fully erected. Ensure all members / bracings have been fitted, tightened, punched and tack welding of nut-
bolts done and back filling of the towers have been completed. The site in charge/Gang supervisor should
fill the format no. EPC/EHS/CKL/26
4. Ensure that all the towers of the stringing section have been permanently earthed.
5. All members of the stringing gang should be sufficiently skilled and experienced and for the job,
medical fitness of all fitters must been ensured.
9. Appropriate PPE’s must be worn by all workers at all times. PPE's required for this
activity includes safety helmets, safety shoes and gloves, canvas shoes for fitters.
10.All supervisors / workmen at the stringing site must also always wear safety helmets and safety shoes.
11. All workers working at a height of above 2 meter must always use full body double lanyard safety
harness. All straps of the safety harness must be properly tightened and Healthiness of full body harness
inspected for the checklist of EPC/EHS/CKL/17.Ensure the usage of vertical rope life line grab fall
arrester while ascending and descending on the tower. Ensure the horizontal life line usage for
horizontal movement.
12. From two lanyards at least one lanyard must be anchored to a strong support at all times. In addition
fall arrestor is also to be ensured.
13. All vehicles in use at the site must be in good condition. The condition of vehicles including the
breaking systems shall be checked periodically. Defective parts shall be rectified / replaced immediately.
14. T&P's used for stringing work, must be of good quality, sufficient capacity for the job & have proper
test certificates. T&P's are to be thoroughly checked for their healthiness as per the format no.
EPC/EHS/CKL/22, EPC/EHS/CKL/23
15. All lifting appliances must be of adequate capacity and in good condition. Test certificates of all lifting
appliances deployed at the site shall be checked prior to erection works.
16. The lifting gears deployed for the erection works viz. lifting hooks, belts, slings, wire ropes etc. should
be checked periodically and confirm its suitability to continue with work. Defective equipment is to
be removed from the site and replaced immediately. Test certificates of all lifting gears deployed
shall be checked prior to erection works.
17. All machines / equipment to be used shall be checked for any defect or repair well in advance. Any
18. Major tools like pulleys, shackles, pull-lifts, come along clamps, steel wire ropes etc. shall be
thoroughly checked for safe working condition prior to the commencement of work.
19. All the operators / drivers must be well experienced, sufficiently qualified and trained and
12 | P a g e
Environment, Health and Safety Plan
20. Local villagers must be informed of the planned stringing activity in the vicinity of the village, if any,
in advance. They must be informed about the hazards involved and the special need for the children
to be refrained from playfully infringing into the stringing area. The village head must preferably be
intimated in writing about the same.
21. Continuous public announcement preferably by megaphone must be made before and during the
stringing process to warn off the public from the area of operations.
22. At least one person must be placed as a look out in each of the span when stringing work is in
progress to ensure that no children hang on to the conductors during the stringing process. They
must be in possession of whistles & flags for controlling public and communicating with their team.
23. In addition a lookout must also be placed at a vantage position preferably at a height overlooking a
few spans.
24. Special patrolling checks should be maintained during the entire period and stretch of the stringing
work.
25. Reliable, efficient and uninterrupted communication arrangement like walkie-talkie must be
available amongst tensioner, puller, stringing supervisor and all the intermediate gang members.
27. Adequacy of anchor blocks provided for towers, puller and tensioner machine stay arrangements
28. For stringing on one side of the section proper guying and back staying is to be provided at all the
tension points.
29. Guying and back staying is to be done by steel wire rope only. Diameter of the wire rope should not
be less than 20 mm. anchoring for the backstays should be strong enough to withstand the intended
load.
30. Guying & back staying arrangement should have a provision for adjustment of tension of the guy
wires.
31. Angle of the guy rope with the horizontal plane should not be more than 300.
32. In case the guying and back staying arrangement is to be maintained for a long duration, then the
33. Guying and back staying is to be provided for one side stringing of D type towers also.
34. Guying and back staying arrangement should be checked periodically to ensure that the same does
not fail.
35. As far as practicable, jumpers are to be left disconnected until all the work of the line is completed.
36. Sequence of paying out should be from top to down for double circuit lines.
37. When pulleys etc. are tied to the tower member through wire / PP rope, the same should be
protected against damage by the sharp edges of tower members by providing a padding of folded
gunny bags etc.
38. Conductor drum stands shall be equipped with suitable brakes, to avoid over-run of conductors.
39. Conductors should not be left in such a position that they may cause danger to general public.
40. Random inspection of hardware fittings is to be done at site to check for any crack or other damage
before fixing them to the towers.
41. Because tension applied will be very high, it is essential to take extra precautions while stringing short
42. During final sagging after the load is transferred to the tower, sufficient time must be allowed for the
load to be stable. During this period all the workmen on the tower must wait on the tower main body and
not on the cross arm or conductor.
43. All final sag operations must be carried out using power winch machines only.
44. All the insulator strings should be thoroughly checked for any crack, kinks, availability and proper
placement of all spilt pins etc before lifting them on the tower.
45. Stringing / sagging works should not be carried out during inclement weather viz. dust storms, windy
weather, rains or storms. If thunderstorm is approaching, the work should be stopped immediately.
46. Stringing of conductors / sagging works shall be done only in daylight hours. No stringing and related
operations shall be carried out after sunset.
47. Proper signboards must be installed as required.
14 | P a g e
Environment, Health and Safety Plan
48. Adequately equipped first aid kit must be available at all working sites.
1. Network of the LT line in the vicinity is to be thoroughly checked and adequate precautionary
measures should be taken to prevent inadvertent charging of the LT line, which is to be crossed.
2. For crossing power lines, shutdown and PTW for the power line to be crossed must be taken from
concerned authorities before commencement of the work as per the format No. EPC/EHS/FMT/04
3. Scaffoldings shall be erected suitably with safety nets. It has to be checked by the format no.
EPC/EHS/CKL/08
4. Power lines required to be crossed and on which shutdown needs to be availed, should be shorted and
earthed at both side of the area of work immediately after taking the shutdown. The point(s) of isolation
of the power line must be properly protected by a suitable
5. Lock and key mechanism. I.e. LOTO system to be implemented. The point must also be manned till the
completion of the job both side of the working area must be protected by providing with temporary
earths (discharge rods).Proper quality of discharge rods are to be used.
6. All the connecting points of the discharge rods must have solid connections. Discharge rods should be
fixed properly so that both the connections at earth end and conductor end have solid contacts. Hanging
the hook of the discharge rod loosely on the conductor should not be allowed.
7. Discharge rods must remain connected to the LT line until all men and material are removed from the
LT line. No one should be allowed to touch the LT line after the discharge rods have been removed, even if
LT line is under shutdown.
8. Discharge rods to be used for construction activities should conform to the relevant IEC standards.
9. Tested and certified Electrical resistance hand gloves should be provided and used for doing such type
of work.
10. Shutdown permit system must be implemented strictly.
11. 11.Works shall be carried out under the permanent presence of Competent Person who
will also be responsible for obtaining shutdown permit.
1. Safe working distances shall be maintained while working near power lines.
15 | P a g e
Environment, Health and Safety Plan
2. Scaffoldings shall be installed to prevent damages to the existing power lines during
line crossing.
3. Discharge rods (portable earthling rods) shall be used when works are carried out
close to power lines.
9. Precautions for stringing in the vicinity of charged Overhead Lines and in areas where induced
voltage is anticipated.
ii. Conductor running blocks are to be earthed to the end these earths bonds must not be
removed unless the conductor is separately earthed.
iii. All the conductors at both ends of the section are to be earthed through running earths.
iv. In case scaffolds are to be used, those should be strong enough to carry the intended
load. It should be adequately earthed and provided with anti-climbing devices and
warning signs. Sufficient clearance must be maintained from existing charged lines.
v. Before breaking the continuity of the conductor at any point, it must be ensure that the
conductors at both ends of either side are properly earthed. Earth shall also be provided at both
side of the working point and shall remain in position until the conductor is reconnected.
vi. Earthing should be connected with the earth-wire before any earth bond is fitted.
vii. PP rope should be used for hauling / controlling spacering chair/cycle.
The clearance required to be maintained between 132 kV, 220 kV, 400 kV & 765 KV line from
66 kV, 33 kV & 11 kV are as follows:
16 | P a g e
Environment, Health and Safety Plan
Materials shall be stored in designated areas where they can be located in a well-organized manner,
protected from damage by weather conditions and from damage from vehicles used for transportation
and heavy plant.
17 | P a g e
Environment, Health and Safety Plan
a. Stacking
Materials shall be segregated as to kind, size and length and stacked such that they are safe against falling.
If the stacks/piles are high, they shall be stepped back at suitable intervals in height. Stacks/piles of
materials shall be arranged so as to allow a passageway of not less than 1 m width in between the
piles/stacks for inspection and removal. All passageways shall be kept clear of dry vegetation.
Materials shall be stacked on well drained, firm and unyielding surface. Material shall not be stacked so as
to impose any undue stresses on walls or other structures, Materials shall be stacked in such a manner as
not to constitute a hazard to passersby.
b. Manual Lifting
When the materials have to be handled manually each workman shall be instructed by his foreman or
supervisor in the proper method of lifting heavy objects. Workmen shall be provided with suitable
equipment for his personal Safety as necessary. Supervisors shall also take care to assign enough men to
each lifting job; the weight carried by each man shall be determined by the distance to be moved,
difficulty of movement presented, time required, etc.
Whenever any stack exceeds 1.5 m height, suitable and safe means of access shall be provided for the use
of workmen and such means of access shall not disturb the stability of the stack.
Posting Storage Areas: Appropriate signs shall be placed at all storage locations where special conditions
exist or where special precautions are necessary.
c. Cement Handling
18 | P a g e
Environment, Health and Safety Plan
Cement stacks shall not be higher than 10 bags. The bags shall be arranged in header and stretcher
fashion, that is, alternate layers lengthwise and crosswise, so as to tie the piles together to lessen the
danger of toppling over. Bags shall be removed uniformly from the top of the piles to avoid tipping of the
stack.
Ensure the following procedures for safe use of cranes and material handling, which include:
19 | P a g e
Environment, Health and Safety Plan
Control of cranes with overlapping operating areas, so as to avoid collisions of jibs or loads
Prevention and actions in the event of a crane boom contacting an overhead power line.
Authorized personnel possess valid driving license will only operate Cranes.
Mobile cranes will be fitted with reversing alarms. An attendant to guide the driver will accompany
mobile cranes. A signal man will maintain continuous visual contact with the driver to pass information
by hand signals. Cranes will not be left unattended when the engine is running.
The slewing pin must be fully fitted when the crane is traveling. The jib should be lowered and fully
retracted when in transit.
When use of a crane obstructs a roadway the Safety officer / client must be informed of the location
and duration of the obstruction.
In the event of an emergency (e.g., fire or flammable gas leak) the lift should stop, the equipment
should be made safe, and the engine should be stopped. The driver and attendant should then report
Safety officer. In high winds if the driver considers the wind too strong for Safety he should stop
operating and inform his supervisor.
• Valid license holder blaster from competent authority should be nominated to carry out blasting operations.
• Control blasting should be carried out to avoid the flying debris / rocks.
• Adequate muffling shall be done which includes, covering of pit with thick steel plate and
• Warning signs, caution boards shall be displayed, at trespassers areas around 200mtrs.
• Warning hooters should be used to give signals of blasting.
• Red flags are posted at the blasting zone.
• Workmen should be deployed carrying red & green flags to warn general public
• Do not use cell phones or any triggering device at blasting location.
20 | P a g e
Environment, Health and Safety Plan
• Skilled and trained & experienced welder having proficiency certificate shall only
perform welding operation.
• Check the condition of the cables. In case of any damage it should not be used
and get replaced it with new cable by authorized electrician.
• Lugs should be used for cable connection and the bare live part should be
properly insulated.
• Transformer should be fixed with ammeter and voltmeter.
• Welding machine should be grounded properly through lugs and body earth
should also be provided.
• Welding machine should be placed above the rigid platform.
• Welding machine and cables should not be used on the wet area and in wet conditions.
• Power supply should be routed through MCB only.
• Fire extinguisher (DCP) should be always kept near the hot work area.
• Firewatcher should be engaged while carrying out welding operation.
• Check the knob and holder. No work should be carried out if any defective is found. 12.Ensure
the electrode holder is adequately insulated.
13.Never change electrode with bare hands or wet gloves, when standing on wet floor. 14.Ensure
that connections between the cable and the holder are firm and secured.
15. Never dip hot electrode holder in water.
16. Ensure that the welder is insulated from both the work and the metal electrode and holder.
17. Take special care to keep welding cables away from power supply cables or high tension wires.
18. Never coil or loop welding cable around the body
19. Ensure that no combustible material are present near welding activity.
20.Regularly inspect insulation on electrode holder, cables and accessories. 21.Use
welder’s screen and other PPE like welding shield,
22. Leather hand gloves, leather safety shoes, apron, Nose mask, safety Helmet, Full body harnessed.
23. After work, disconnect machine and remove electrode from holder.
24. Ventilation and blowers shall be provided it welding activity is carried out in closed area, to allow
fresh air.
25. Ensure illumination level is maintained for welding operation.
21 | P a g e
Environment, Health and Safety Plan
26. Workmen shall climb the tower from main leg member with the help of fall arrester through step
bolt.
27. Retractable block shall be used while welding in all the areas of the tower to avoid fall.
1. Acetylene cylinders are in maroon colour and Oxygen cylinders are in black colours, both the cylinders
shall be kept in upright position.
2. Written work permit shall be obtained from concerned authority, if the work has to be carried out in
restricted area.
3. Ensure that Acetylene and Oxygen cylinders are equipped with flash back arrestors/Non return valve
(NRV).
4. Ensure that four numbers of flash back arrestors are provided, two at cylinders near pressure gauge
and two near cutting torch.
5. Do not attempt to tamper, repair cylinders, valves or regulators.
6. Store cylinders upright and secured with chain slings.
7. Keep cylinder fittings and hoses free from oil and grease.
8. Repair or replace defective hoses. Do not use tape.
9. Do not store cylinders near the source of heat, spark, fumes & electric wire.
19. Ensure that oxygen and acetylene cylinders are stores separately.
20. Do not use domestic LPG for cutting operation; use only industrial cutting
sets like; Bharat cutting gas.
21. Ensure that gas cutting hoses do not overlap with the power cables.
22. Do not try to cut closed drums or any closed vessel, if at all the operation
has to continue, first open the lid or cover, and allow gas to escape for few
minutes.
23. Ensure fire extinguishers and fire buckets shall be readily available to dose
the fire in emergency.
26. Ensure relevant PPE are used; like safety shoes, clear face shield, safety
helmet, leather hand gloves, safety goggles etc.
23 | P a g e
Environment, Health and Safety Plan
• Authorized persons will only be allowed to install & rectify the electrical
connections and faults.
• Care should be taken to avoid cable run over water logged floors.
• Proper tool box talks to be conducted those who will be handling electrical items
and tools.
• Proper signage will be posted for all electrical hazardous areas.
• All hand operated electrical tools/ equipment connections should be checked
visually before use by operator
17. Safe Operating Procedures at Store:
1. Safety posters should be prominently displayed in the stores to enhance the knowledge of employees.
2. Ensure that material especially tower parts, insulators and conductor drums etc. been properly stacked
to prevent injury to workers while handling them
3. All workmen should wear safety helmets and shoes in the stores while on material handling duties
4. Ensure the Tool Box Meeting been conducted and record of the same maintained
5. Ensure proper drinking water facility available at store
6. Ensure the work being properly supervised
7. Ensure all emergency phone numbers of, Hospital, and Police displayed and available with the store in
charge in the store
8. Ensure first aid box been available in the stores
9. Ensure a crane operator skilled and experienced and hold a valid license
10. Ensure that the cranes being used for lifting heavy loads (if any) properly tested and certified
11. Ensure all lifting appliances being used viz; Chain pulleys etc. checked for serviceability and
certification & tested.
12. Ensure ropes / slings being used for lifting of equipment been checked visually for its serviceability
13. Ensure the house keeping of the stores adequate
14. Ensure the lighting in the store area adequate
15. Ensure the store is adequately fenced
16. Ensure adequate actions been taken for mitigating snake / rodent menace like spraying carbolic acid.
17. Ensure the scrap segregated from the store material and separately stored
24 | P a g e
Environment, Health and Safety Plan
18. Ensure that the grass and wild vegetation been regularly cleared to avoid any fire and damage to the
men
19.Ensure portable fire extinguishers and fire buckets filled with fine grain dry sand and water been
available in the store for easily accessible.
20. Check that EL.C.B has been installed of 30 ma for electrical installation to avoid shock
21. Ensure any power line crossing inside the store. If yes, proper nonconductive barriers are erected
under it such that high material is not touched by live wires
While planning any excavation work, it is important to plan against the following:
It shall be ensured that necessary equipment needed such as trench sheets, props, baulks, etc. are
available on site before work starts.
Precautionary measures:
Before starting excavation, it is to be checked whether there is any underground utilities present
like electrical power cables, water pipe line or any other service line in consultation with the client
and consultant.
25 | P a g e
Environment, Health and Safety Plan
If the excavated pit is more than 5ft. depth, then appropriate preventive measure to be taken to
avoid earth collapse like slope or bench providing to the walls of the pit or sheet piling etc. as per
norms and design. The slope of excavation should not be steeper than the angle of repose of the
particular soil. When the slope is less than the angle of repose, which cannot be achieved because
of limited place or if it is uneconomical to provide such a slope then shoring should support the
earth.
LIST OF LIFTING EQUIPMENTS
Excavation area should be barricaded 1meter away from the edge of excavation
pit. Hard barricading arrangement to be ensured
No materials should be stacked at edge of the excavation pit. Materials stacking to be half of the
depth away from the edge of the pit.
There should not be any vehicle movement close to the edge of the excavation pit.
Proper access should be made for workers, either by providing ladders or cutting steps on the wall
of the pit or by any appropriate means. More access/ladders shall be provided at every 15m
distance if there are hazards due to underground facilities and in case of normal conditions
access/ladder should provide at every 30m distance, when the excavated pit is large.
Ramp with an angle not more than 150 shall be made if the excavated earth is to be moved by
vehicles.
Proper lighting is required for work at night. Reflectors & caution boards are to be fixed to caution
outsiders.
Electrical cable routing should be laid such that it does not cause tripping hazard.
Care should be taken that the persons working near by the excavation achiest may not be hit by
moving part of the machine.
The Dump Truck that shifts the excavated material shall move only after lowering the hull to
original position; after completion of dumping the material.
26 | P a g e
Environment, Health and Safety Plan
A. Dewatering:
Dewatering the excavated trench & pools of water in the building area by using Pump. The pump should
be given body Earthing if it is electrically driven.
Stack yard
C. Cutting / Bending
List of authorized operators shall be displayed on the machine, to avoid un – authorized operations.
Emergency stop button and Trip dog button shall be checked before every use.
Cutting machine shall have a guard over the cutting tool, to prevent the splash of the bit pieces.
In case of hydraulic cutting machines, oil seals and other necessary provisions shall be provided to
arrest the oil leakages and a continuous monitoring shall be made on it.
Bit pieces and the scraps shall be disposed of immediately after the work is completed.
Gloves shall be provided for all workmen working with reinforcement rods.
Loose dress shall not be permitted in proximity to the operations.
Worked bars shall be kept in a orderly manner to cause little interference to the passages and other
operations.
In case of “L” the bars shall be placed in single direction to avoid protruding sharp edges.
Shifting
Reinforcement rods shall be shifted to the site only when its required, to avoid unwanted
materials lying in the site.
If possible the reinforcement bars shall be transported as a final assemble to the site to reduce
the work at site.
27 | P a g e
Environment, Health and Safety Plan
Bars if shifted in bundles shall be tied off and the transported to avoid the wide spread of the
sharp edges.
All over hung projections shall be covered fully by tarpaulin / canvas materials & secured.
D. Rods Aligning & Tying
Before starting to work with the reinforcement, rods working platforms shall be provide to facilitate
the smooth working.
Binding wires and other tools used for tying reinforcement bars shall be secured with tools bag or
other kits, if work is being carried out in height.
Clear Goggles shall be provided for all the workmen working with reinforcement bars.
The towers shall support reinforcement members of less stability.
E. Shuttering
Weight of the shuttering board being shifted shall be calculated. For shifting, no. of workmen required
shall be selected based on the weight and shape of the shuttering material.
Shuttering material shall not contain any protruding nails or other sharp objects, if some sharp
protruding objects are found they shall be eliminated then shifting shall be carried out.
Proper arrangement for slinging the shuttering boards shall be provided in it.
Weight of each shuttering boards shall be clearly marked in each shuttering boxes.
Shuttering boards before fixing shall be secured with the reinforcement rods by binding wires or other
arrangements.
While casting the columns at the edge of the buildings, shuttering boards with working platform and
handrail provision shall be used.
As a second alternative, the scaffolding with handrails (refer standards of hand rail) shall be used.
While shifting materials in bundles, slings shall be inspected and then used.
Shifting materials and Ply woods from the ground level shall be done through approved methods
(refer from work methods).
Plywood shall be carried by approved methods, such as tower cranes, material handling platform
etc. and not through staircase.
Shuttering oils shall be selected so that, the surface becomes less slippery.
28 | P a g e
Environment, Health and Safety Plan
G. Scaffolds:
Each scaffold shall be inspected by supervisor before using it. The same procedure will be followed for
dismantling as well. Periodic inspection shall be done for scaffolds while in use.
Access scaffolding:
Exclusively used for scaffolding purposes up to 40 m height braced at every 6m with permanent
structure. This uses lighter frames compared to those in heavy-duty tower staging. This provides free
movement for workmen without any obstruction at all levels.
Heavy Duty Tower:
Scaffold structures shall be providing in a solid base avoiding pavements & manhole covers
etc. Verticality of the structure shall be properly maintained
Ties for scaffold structure shall be properly maintained
Tower shall be braced at every 6 m in height in both horizontal directions with permanent structures
H. Concreting.
Foundation
29 | P a g e
Environment, Health and Safety Plan
All precautions necessary to start and operate the electrical equipment’s as mentioned in the P&M
part shall be strictly adhered.
Access shall be provided at every 25 ft of lateral travel.
If ladders are being used, it shall make an inclination of 75 0 with the horizontal plane and the ladder
shall be projected 1 Mtrs from the edge of excavations.
In case of Ramps, it shall have a gradual slope of 150 with the horizontal.
Whenever concreting is being carried out with help of concrete pumps, the pipes should be adequately
supported at necessary spots.
Ball passing shall be done only under the supervision of the concerned engineer.
Concrete duct shall be placed in such a way to cause minimum interference to the other areas such as
passages, etc.
Column Casting
Shuttering boards shall have adequate provisions for hooking and slinging.
Necessary platform with handrail arrangements shall be made ready before column castings.
While casting columns on the edge of the floor adequate protection to prevent workmen working at
height should be ensured.
Scaffolds shall be placed towards the inner side and hand railing shall be provided.
All the precautions mentioned in the formwork manual shall be strictly followed.
Slab Casting.
Before starting the slab activities Safety net shall be tied at the lower slab level and handrail shall be
made at the level wt which slab is casted.
The Formwork engineer shall inspect towers supporting the formwork materials and Green Tag shall
be hung indicating the safe condition of the tower.
Safe Access shall be provided for the slab to be casted.
Preferably Tower staircase shall be erected as approach; Staircase shall be made with proper
approaches at heights handrails shall be provided along the approaches.
The Formwork scheme drawing designed with safety shall be followed strictly.
While using flex system, tripods shall in true vertical and removable folding tripods shall be provided
for every alternate tripod.
Tripods shall be erected on the leveled ground and wooden runners shall be provided while casting
ground floor.
Tor steel shall not be used in place of “G” clamp.
Handrails shall be provided while shuttering and de-shuttering activities.
30 | P a g e
Environment, Health and Safety Plan
Safety nets shall be provided to prevent fall of materials (as per the Method enclosed in the safety
plan).
I. DE-SHUTTERING
• The area shall be cordoned off.
• Signal man shall be deputed to stop the unauthorized entry.
• All workmen shall wear PPEs. Lifeline shall be provided wherever required.
• The material is lowered by rope. Throwing of material is strictly prohibited.
• Tools and tackles with test certificate are used.
• For bigger load, the tag line should be used for guiding the load.
J. WATER PROOFING
K. FLOORING ACTIVITY
1. Handling of granite stones shall be taught for the concerned gang the right method of handling
them.
2. Appropriate PPEs shall be given to them, especially Safety shoes & gloves.
3. While cutting the granite or tiles the workers doing the operation shall use dust mask.
4. Dust pollution should be under check by carrying out the cutting operation as wet process or in an
enclosed area.
31 | P a g e
Environment, Health and Safety Plan
The transportation of DTC and its accessories to be shifted from site store to work spot by truck,
tempo only in urban area.
Tractor-trailer should not used in city area for the above work.
All the heavy equipment, like DTC, Cable drums are to be tied properly. Should not be kept in free
condition while transporting.
No person /workmen should travel sitting on heavy equipment/ cable drums while transportation
of materials.
While traveling by tractor-trailer No person should sit on tractor engine except driver.
ERECTION
32 | P a g e
Environment, Health and Safety Plan
Maximum No of serious accidents in Electrical Installation works occur due to electrocution or due to
toppling of panels. In most of the cases, width of the panels will be very small (0.3 to 1 M) and height will
be 2 to 3 Meters. Hence center of gravity will be high and even if they are slightly tilted they will topple.
Hence great care should be taken while handling the panels.
1.Proper unloading arrangements are to be planned before receipt of panels. A few of them are listed
below:
7. If no other method is possible an inverted ramp is to be dug out near the place of installation.
Note: Using channels in a maimed plane for unloading panels is risky. Miter unloading, the following
precautions are to be observed; while loading the panels to its location.
1. Two channels or plates to be used below roller pipes. Channels should be as far apart as possible to
give wider base.
2. If the casing has any projections in the base suitable planks are to be provided to facilitate movement.
3. Pipe rollers should be of same diameter.
4. Pipe rollers should be of suitable length. If they are too long it will be difficult to handle. If they are
short, they may lead to panel tilting
8. Workers handling panels should be alert to avoid injuries to toes as 3chances of getting caught under
rollers is always there.
9. Workers should be always behind the panels while pushing. To avoid tilting side ways proper guy ropes
can be provided.
33 | P a g e
Environment, Health and Safety Plan
10. If a chain pulley block or ‘tirfor’ is used for pulling, rope should be tied to the panel at the lowest level
possible.
11. When panels are to be lifted more than 2’, it is always advisable to lift both ends alternately, to avoid
lifting too much on one end.
1. To the possible extent cables should be transported by trucks / trailers, except for short distances.
Loading into trucks can be done either by having ramp (Excavated slope) such that body of the truck
will be at ground level or by using cranes. Whenever cranes are used, slings should be of adequate
capacity. In many cases drums will be far away from the crane approach point. While deciding the
capacity of the crane, Safe working loads for the particular boom angle to be checked up. This is very
important to avoid accidents. After loading the drums into vehicle, proper wedges are to be provided
and to be tied properly to avoid rolling.
2. While rolling the drums care should be taken to roll in proper direction. Otherwise cable will get
loosened and cause problems while lying. Before rolling the drum soil condition is to be checked up.
Otherwise there is a possibility of sinking on one side and toppling. While rolling the drums in slopes,
wedges should be provided at regular intervals to avoid drum picking up uncontrollable speed.
Persons handling the drums should be always behind and on the sides of the drums and never in the
front. This precaution is very essential and non-observance while handling the drums at slopes can be
dangerous.
3. While laying the cables at height workers should have proper base. We should insist on using Safety
appliances like safety belts etc. Never use cast iron pipes as shaft. Jacks should have proper and wide
base to avoid tilting of jacks. Whenever the height of drum is more and packing is required, proper
sleepers should be used.
4. A person is to be at the other end, whenever megger test is done on cables. Proper cordoning is to be
done while high voltage test is carried out on cables.
5. While using single core cables, proper checks are to be made to avoid short between phases.
6. Most important, thing to ensure is that the gang leader should have basic knowledge of rigging work.
N. Cable Laying
34 | P a g e
Environment, Health and Safety Plan
7) Person should hold the cable drum with the help of guy rope not by Hands.
8) The person should hold the cable drum to the left side of the vehicle at distance 2m from
the material (not to the opposite side of the vehicle.)
9) Frequent inspection of tools and tackles should be done on weekly basis. If any Defect
found means it should be discarded immediately from the storage area.
10) The competent person before use should conduct load test of all Tools & Tackles.
11) Shifting the materials from yard to site through vehicle (Tractor), the vehicle driver should be
screened and should have a gate pass & valid license. Speed limit of the vehicle should be of
15Kmph in the site premises. Overload of vehicles should be avoided. Vehicle should be in
good condition and should be tested by competent person or by Safety Person.
Rolling & Removing the cable from the drum for Laying over the Tray
1. Above 2 m height, Worker should wear full body safety harness belt with double lanyard.
And the belt should be hooked in the permanent rigid structure.
2. Life Line Rope (PP Rope) should be used while working in a trestle, unsafe condition and in
the unprotected beam.
3. Ladder should be used for climbing purpose above 2 m height. And it should be rigid
in condition and secured at both the ends. And it should be kept at 750.
1. Ensure all men and materials, are removed and bus bar chambers are closed before Meggering.
2. Ensure proper earthling before Meggering / high potential test is carried out.
3. Check the bus bar configuration etc. in case a part of the panel is being energized. In some cases,
manufacturers extend the bus bars of one section to the other section, to save adopter panels. In
one occasion where number of tie cables were more space behind the P.T. Panel was used for
cable connection, without proper •warning on the back cover, which caused bus fault.
35 | P a g e
Environment, Health and Safety Plan
4. Ensure thorough checking before carrying out high potential test, area should be cordoned off and
suitable warning boards are to be provided.
5. Panel manufacturers normally provide barriers between bus bar chambers to avoid accidental
contact with live parts, when you open the doors. Ensure all the barriers are in place before
Testing/Commissioning.
6. Control circuit fuses are to be removed before meggering /High pot testing.
10. Grounding connections and wire should be adequately sized to withstand the fault-current.
11. It requires additional physical work, as well additional time to adequately ground the work area
or equipment.
12. Ensure that rusted hardware is not used for making connections.
13. Ensure that connections are tight and adequate contact area is provided.
36 | P a g e
Environment, Health and Safety Plan
Stacking Of Equipment:
1. Surface Area shall be levelled and ensure it shall not be uneven surface to avoid toppling.
2. Skilled and experienced workmen shall be deployed.
3. Lifting appliance shall be tested and certified and in sound condition.
4. Sophisticated equipment shall be covered to protect from environmental damage.
Shifting of equipment from stacking area to the location:
1. Ensure the skilled manpower are deployed.
2. Ensure the crane conditions are healthier and safe to use.
3. Crane is tested and certified by competent person
4. Tag line are attached while shifting the object from one place to other to avoid swinging.
5. Ensure the approach road or a proper access is provided and clear.
Erection of equipment on structure by Derrick method:
1. Ensure SWL of Derrick.
2. Ensure it is tested and certified.
3. Damaged tools and tackles shall not be used.
4. Ensure the equipment is shifted smoothly and slowly.
5. Ensure proper work methodology is followed.
6. Skilled and experienced manpower is deployed.
7. Ensure the structure to which derrick is fixed, that is strong enough to withstand the load.
8. Ensure the alignment of structure.
9. Ensure structure‘s nut and bolts are tightened and checked.
10.Ensure the structure is in plumb.
39 | P a g e
Environment, Health and Safety Plan
Column Erection:
1. Responsible person shall be posted to supervise the erection work.
2. Required tower members shall be shifted to the location for erection.
3. Start erecting first four main leg members along with diagonals and bracings.
4. Erect the good conditioned, tested and certified derrick pole.
5. Ensure three guy ropes of 20 mm PP rope are provided and tied to fix structure.
6. Ensure the verticality of Derrick pole.
7. After completing first four legs, start erecting second section with the help of Derrick. And
continue till the end.
8. Ensure safety devices like fall arrestors, full body harness with double lanyard, safety shoes,
safety helmets are used on the job.
Beam Erection:
1. Horizontal legs both faces are assembled including bracing on the ground near to the column.
2. Ensure the lifting arrangement is adequate for lifting the horizontal assembled faces.
3. Ensure that the sheave pulleys, D shackles, wire rope 12 mm diameter are inspected and
checked before lifting.
4. After fixing one face, start lifting second face of beam in same way.
5. Start fixing bracings and diagonal on the column for both faces.
6. Ensure 20 mm PP rope or horizontal lifeline or 8mm wire rope is tied to vertical column to
avoid fall of person during fixing diagonals and bracings.
7. Lifeline shall not be removed until stringing and insulator hoisting is completed.
40 | P a g e
Environment, Health and Safety Plan
1. Trained experienced and knowledgeable person shall be deployed for battery work.
2. Battery shall be handled carefully.
3. Never touch both battery terminals with your bare hands at the same time.
4. Remove rings, watches and dangling jewelry when working with or near batteries. The metal
in the jewelry can cause a shock or burn if they contact the battery terminals.
5. Only use insulated/non-conducting tools to remove cell caps. Never lay tools or other metal parts
on top of a battery.
6. Consider covering battery terminals and connectors if possible with an insulating blanket
before overhead inspections or repairs.
41 | P a g e
Environment, Health and Safety Plan
7. Ensure charger is turned off before connecting or disconnecting a battery to prevent arcing.
8. Do not smoke in battery charging areas.
9. Prevent open flames, sparks or electric arcs in battery charging areas. 10.Do
not strike the sides of the battery with any spark producing item. 11.Keep tools
and other metallic objects away from uncovered batteries.
12. Ensure an ABC dry chemical fire extinguisher in charging areas readily available
13. Neutralize static buildup just before working on battery by contacting nearest grounded
surface.
14. Ensure battery area ventilation is operating prior to working on.
15. Use extreme caution when handling electrolyte and keep an acid neutralizing solution—
such as baking soda readily available.
16. Use non-metallic containers to handle liquid.
17. If the electrolyte is splashed into an eye, immediately force the eye open and flood it with clean,
cool water for at least 15 minutes. Get prompt medical attention.
18. If electrolyte is taken internally, drink large /quantities of water or milk. DO NOT induce
vomiting. Call a physician immediately
19. To prepare electrolyte of a desired specific gravity, always pour the concentrated acid slowly into
the water; DO NOT pour water into the acid. Always stir the water while adding small amounts of
acid. If noticeable heat develops, allow the solution to cool before continuing to add acid.
20. Use appropriate equipment to load/unload batteries from mobile equipment. 21.Store
the batteries in a cool and well-ventilated place.
22. Ensure trained personnel are deployed in loading equipment.
23. Ensure Material safety data sheet (MSDS) is readily available to take precaution, in case of acid
spills.
24. Always wear proper eye, face and hand protection, like chemical apron, face shield, goggles,
hand gloves, gumboot etc.
24. Safe Operating Procedure For underground cabling work
Manual Trench Excavation;
1. All applicable PPEs should be worn by all workmen at all time of work is carrying out excavation.
2. All workmen should be inducted well before engaged them in to job.
42 | P a g e
Environment, Health and Safety Plan
3. Before starting any excavation it is to be checked whether there is any underground utilities
present like electrical power cable, water pipe line, gas pipe line etc.
4. Excavated soil should be kept 1M away from the pit.
5. Excavation pit should be barricaded 1M away from the edge of the pit.
6. Proper lighting is required at night work.
7. Skilled, experienced Manpower shall be deployed.
8. Ensure the cable trench has been dig as per the specification and layout mentioned in work
order.
9. Ensure the trench does not damage the adjacent structure.
10. Barricade the open trench with hard barricades and warning notice shall be displayed to warn
the persons working nearby, to avoid fall.
11. Usage of damaged tools shall be avoided.
12.Good conditioned tools shall be used.
PCC and Brick Lining in trench:
1. Skilled mason shall be deployed.
2. Approach shall be made to shift material.
3. Materials like sand, bricks & cements shall be kept at specifies location.
4. Precautions shall be taken while shifting bricks to required location. Wheel barrow shall be in
good condition while shifting with it.
5. Damaged mortar pans shall be discarded to avoid hand injury.
6. All applicable PPEs shall be worn by the workmen engage for brick and PCC work.
RCC Wall and Raft Construction:
1. Responsible person shall be deployed for supervising the concreting, formwork and other
supports.
2. Skilled Bar benders shall be deployed for reinforcement work.
3. Reinforcement steel shall be stacked properly at one side, so that it should not be the obstacle
in approach road.
4. Housekeeping shall be done periodically.
5. Sharp bar bending hook shall be kept in safe way to avoid injury to himself and coworker.
6. Relevant PPEs shall be worn at all times during on the job.
7. Ensure scaffolding shall be provided to work on vertical columns and relevant to IS 2750:1964
and fulfil BOCW Acts and Rules made thereunder.
8. Proper working platform shall be provided and ensure that it was properly secured with
43 | P a g e
Environment, Health and Safety Plan
44 | P a g e
Environment, Health and Safety Plan
When testing and maintenance on substation equipment involving personal contact with conductors,
which are normally energized and have been de-energized, the following procedures shall be adhered
to:
1. Ground all applicable phase loads before test leads are connected.
3. Upon completion of tests, grounds shall he reinstalled and test leads removed, in that order.
4. Remove all temporary ground connections, before closing source side isolator; close CB after
isolator is closed.
2. The primary objective in substation work should be made clear, i.e., when it is required to work in
live conditions, and what precautions are required for live line work.
6. Use adequately insulated and tested tools & test leads/or probes.
7. Ensure adequate work section clearance.
8. Study the single line/schematic drawing and establish the No. of sources that can provide power to
a given point.
10. Where test lamp is used for checking, 2 nos. of serially connected lamp shall be used to ensure
protection against accidental contact between phases.
11. Do not use flexible wire as test lamp lead. Use adequately insulated rigid wires.
12. Ensure that testing instruments are set in adequate testing range.
A safe lockout and tagging procedure shall be established prior to work on/or near electrical
equipment or lines, and lines or equipment containing dangerous or hazardous material, which can
be energized, pressurized, activated, or released remotely or inadvertently.
45 | P a g e
Environment, Health and Safety Plan
A safe lockout and tagging procedures is an operating procedure by which a person, action
individually or as a member of a maintenance crew, may have a machine or part of a machine or
equipment removed from and held out of service until released by that person. A tag indicating
“Danger! Do not Operators” or the equivalent shall be placed at the power source of the
equipment being serviced.
A safe lockout and tagging procedure shall be strictly followed in securing electrical systems,
machinery, pressure systems, and rotating equipment.
Power shall be turned off, tagged, and locked in the open position at the master switch or at the
main breaker. Gears, agitators, or transmissions shall be mechanically locked out or disconnected.
Padlocks shall be used and the person working on the equipment shall be in possession of a key.
A safe lockout and tagging procedure shall be required on all systems and equipment if the
unauthorized removal or return to service could result in injury, damage, or loss.
Any required safe lockout and tagging procedures shall be included in an activity hazard plan.
Safety meetings shall be held to familiarize designated persons on the site with the procedure,
including person responsibilities, and the system for safe lockout and tagging procedures. This shall
include all signs, tags lockout, and other devices to be used.
A lockout device that only accommodates one padlock shall not be used as the lockout may involve
more than one system
Padlocks and other accessories to be used shall be materially strong enough so that only excessive
force or pressure can break them. Defective padlocks or accessories shall be immediately replaced.
No key shall fit more than one lock.
The person issued with a lock shall only be issued with one key. The spare key and the master key
shall be held in a secure place by the supervisor and kept well apart from the primary lock and key
storage box.
Locks shall be distinctly numbered and no repetition of numbers allowed. Locks can, also be colour
coded to identify the user’s department (i.e electrical, mechanical, etc.)
The most basic form of safe lockout and tagging is given below-
Removing the keys from vehicle ignition locks and placing warning signs instructing employees that
the vehicle is under repair.
Locking – off the power supply to equipment, such as carpentry machinery, to prevent
unauthorized use or to ensure complete safety when repairing the machine and power supply
point.
Locking the doors and posting warning signs on areas or locations, which present hazards to
unauthorized personnel.
46 | P a g e
Environment, Health and Safety Plan
After the switching operation has been performed, the switchmen shall, whenever possible,
lockout the controller and /or attach Hold Tags as the case may be. The purpose if Lockouts and
Hold Tags are to make sure that the Controller remains open while work is being done and protects
the personnel working on the portion of the system being protected by the controller.
Hold Tags shall not be removed from any device unless authorized.
Each disconnecting device shall be properly tagged with an approved Hold Tag.
When Hold Tags cannot be attached to a device, they shall be attached at a conspicuous point, as
close to the device as possible. In case of switchgear where Power Circuit Breakers are lowered or
rolled out, the control, which would raise or roll the breaker to its operating position, shall be
tagged.
After completion of the work, the craftsman will then sign in the hold tag and return it back to the
Supervising Operator who will then directly supervise the removal of tags. The craftsman signing the hold
tag shall be the same person who requested the hold tag. Unless responsibility transfers, both the
Supervising Operator and the Craftsman shall follow the procedure for removal of lockout clips, chain and
padlock.
1) Before shifting the materials from yard to site through vehicle, the vehicle driver should be screened
and should have a gate pass & valid license. Speed limit of the vehicle should be of 15Kmph in the
site premises. Overload of vehicles should be avoided. Vehicle should be in good condition and
should be tested by competent person or by Safety Person.
2) While Loading & unloading the materials from the vehicle, precautions should be taken when shifting
heavy or sharp edge materials. Loading and unloading person should wear cotton gloves while
shifting the materials.
3) All tools & tackles used by workers in the site should be certified from P&M Department or HSE
Department before starting and at regular intervals of work.
4) Every worker should screened by Safety Engineer and they should have a valid gate pass and they
should know the working procedure of their specific task. They should wear all PPE’S like safety
Helmet, Safety Shoe., etc and they should know the Safety code of practices.
5) While cutting the channel supports by Power Hacksaw Machine, the cutting person should wear Safety
Goggles and Safety Gloves.
6) While lifting the Materials from ground level to the required level through Chain Block Pulley or by
Rope, the area should be barricaded. Competent or Safety Person should check pulley on weekly
basis. And it should be tied with rigid permanent structures. PP Rope should be in good condition.
Proper supervision should be required in the area. Communication system (Walkie-Talkie) should
47 | P a g e
Environment, Health and Safety Plan
be used. Person in the elevated area should wear Safety belt, safety shoes & safety belt and person
should hang the belt hook in permanent rigid structures at a height above his height.
8) All power tools should be tested before starting and at regular intervals of work audit should be routed
through ELCB with proper Earthing.
10) Ensure Isolator switch (Cut-Off Switch) in Welding Machine before commencement of work.
11) When welding work carried out using Ladders or scaffoldings, Ladder should be secured on both the
ends. Ladder should be extended 1 m from the working level of the worker. Wooden Ladder should
not be used. Scaffolding base should be firm base level. Scaffoldings should be fixed at regular
intervals (6 m ht) to the rigid permanent structures. Working platform should be rigid and should
be 600mm width tied at both the ends with binding wires. Above 2 m height, Safety Belt should be
used Area should be barricaded. Proper supervision should be required. Fire Extinguisher should be
kept handy at workplace.
12) Use GI Sheet / Wet Gunny bag below the welding spot while working at higher elevation to prevent
the welding spotters.
13) Scrap bin should be kept at the required area and scrap should be removed on daily basis from the
work area.
14) Work area should be kept free from obstacles and always keep the area in the safe working
environment.
12) Person doing continuity test in a live cable should get clearance (Work Permit) from the client side.
13) Person doing continuity test in a panel should wear 11kv Rubber Hand Gloves.
14) Proper Supervision should be ensured.
15) Placing caution Board of Men at work Board in the Panel while working on live cable
16) Qualified & Experienced Electricians should be engaged for Continuity Test.
48 | P a g e
Environment, Health and Safety Plan
1) Check for underground utilities and get clearance from the concerned authority
2) Barricading to be done in the excavated area.
Pole painting:
1) Using good capacity and proper ladders. Ladder should be kept at an angle 75 degree and
should be secured at both the ends.
2) Proper leveling of surface should be ensured
3) Using of Mobile Ladder, Ladder wheel should be in locked condition.
4) Person doing painting work should wear all PPE’S like Safety Shoe, Safety Helmet, and Nose
Mask & Safety Goggles.
49 | P a g e
Environment, Health and Safety Plan
Use of Personal Protective Equipment and safety devices relevant to site activities- Enclosed as
Head protection:
Every individual entering the construction work premises shall wear safety helmet.
Foot protection:
Suitable foot protection shall be worn by all personnel entering the site.
Fall Protection:
(a) All employees working above 2 m height shall use safety harness
(b) All employees using safety harness shall anchor its lanyard to a fixed
structure before starting the work at height.
(c) Fall arrest devices shall be used in conjunction with safety harness
wherever required.
Hearing protection:
Ear plug, ear muff shall be worn by workmen who are working near noisy area
50 | P a g e
Environment, Health and Safety Plan
Body protection:
Wherever required full body protection is to be taken.
Hand protection:
Appropriate hand gloves shall be used for material handling,
concreting, welding, grinding,
gas cutting electrical works etc.
Eye protection:
(a) Suitable goggles shall be used by all personnel deployed for welding, grinding,
chipping, concreting etc.
(b) Execution & Supervisory staff shall wear safety spectacles.
51 | P a g e
Environment, Health and Safety Plan
Job Specific PPE & other job specific safety gadgets must be used whenever required
Though, the PPEs are last line of defence but still it is a culture in our company and
safety helmet, safety shoe, reflective jacket & safety goggles are considered as uniform.
Sl.
Activity Suggested PPE
No.
52 | P a g e
Environment, Health and Safety Plan
53 | P a g e
Environment, Health and Safety Plan
05 Safety Harness (Belt) IS 3521E Karam & Full body double lanyard
N Udyogi harness (belt) only
or
361 permitted, half body safety
harness (belt) not permitted
for
any work.
54 | P a g e
Environment, Health and Safety Plan
1179 Any
supplier
10 Fall Arrestor CE-360 & Karam & For working above 04m.
EN 353 Udyogi
SHCEME: 1
55 | P a g e
Environment, Health and Safety Plan
WORK ON TOWERS WHICH DOES NOT INVOLVE THE DISCONNECTION OF ANY CONDUCTORS OR
JUMPERS.
WORK:
For work on the de-energized circuit which does not involve the disconnection or lowering of any
conductors to the ground. This scheme is to be followed during earthing for the following work: -
Changing suspension or tension insulators.
Any other work on a suspension or tension string.
Fixing/replacing of spacer of vibration damper adjacent to the suspension or
Tension string.
PROCEDURE:
Apply Local Earths on all phases and on all sub-conductors of the de-energized circuit, on
adjacent towers at the both end of the working zone Apply Additional Earths to all phases
and to all sub-conductors at the working tower of de-energized circuit.
i. As an extra safety measure, both sub-conductors of working phase(s) may be bridged with
an Additional Earth.
ii. Carry out the maintenance on strings and vibration dampers as per the normal procedure.
However, if a winch is used for replacement of insulators, the winch must be earthed by the
use of a Field Equipment Earth attached to an earth spike driven into the ground. All the
pulleys used should have good electrical connection with the tower. The pulleys should not
have any insulation i.e. rubber lining etc.
iii. On completion of work, remove all additional earths / local earths.
56 | P a g e
Environment, Health and Safety Plan
SCHEME 2
57 | P a g e
Environment, Health and Safety Plan
WORK:
For work on the de-energized circuit which does not involve the disconnection or lowering
of conductors between towers to the ground. This scheme is to be followed during earthing
for the following work on tension towers:-
Breaking or re-making jumper connections, including lowering and raising a jumper.
PROCEDURES:
i. Apply Local Earths on all phases and on all sub-conductors of the de energized
circuit, on adjacent towers at the both end of the working zone.
ii. If either one end of the jumper or both ends of the jumper are to be disconnected,
apply Additional Earths at the end of conductors at the both ends of the jumper in
working Tower, on line side of the dead end compression joint where the jumper
are to be disconnected.
iii. In addition, provide Additional Earths on the jumper to be disconnected for
replacement / repair of the jumper.
v. If the jumper is to be lowered to the ground, disconnect the Line End Clamp of the
Additional Earth provided to the jumper before lowering the jumper to the ground.
The disconnected Additional Earth shall be kept suitably at tower cross arm.
vi. Lower the jumper in such a way that Safety Clearance is maintained from all live
conductors.
vii. Before any person on the ground touches the jumper, it should be discharged by the
use of an Additional Earth fixed to an earth spike driven into the ground.
viii. Carry out the maintenance work on the jumper as per the normal procedure.
ix. Raise the jumper to the cross arm maintaining Safety Clearance to all live
conductors. Precautions shall be taken so that the jumper is not raised in the
horizontal position.
58 | P a g e
Environment, Health and Safety Plan
x. Connect the Additional Earth to the jumper before touching it for connecting it to
the dead end compression joints.
xi. Connect the jumper at both ends with dead end compression joints.
59 | P a g e
Environment, Health and Safety Plan
SCHEME 3
PROCEDURE:
1. Apply Local Earths on all phases and on all sub-conductors on towers at the both end of the
working zone. These towers should not be more that 10 spans apart. At tension towers(s) within
the working zone, apply additional Earths to the jumpers and to all sub-conductors.
60 | P a g e
Environment, Health and Safety Plan
2. Carry out the maintenance work as per the normal procedure. While working, following safety
precautions shall be taken.
3. The men on the conductor shall always maintain Safe Electrical Clearance from tower steel parts or
any other material at earth potential at those towers where conductor is not earthed.
4. If any tool or plant is required by the lineman on the conductors, these shall be lifted to the
working position by using a polypropylene/insulated rope/bag.
5. If access to any tower is required, all the conductors at that tower shall be earthed with Additional
Earths.
6. On completion of work, remove all additional earths/local earths.
7. If, before work commences, there is a risk of thunder/lightning stroke, no work shall be started.. If
during the course of work, there is a risk of thunder/lightening stroke, all work shall immediately
stop and all men shall return to the ground.
61 | P a g e
Environment, Health and Safety Plan
SCHEME 4
PAINTING OF TOWERS WHICH DOES NOT INVOLVE ANY DISCONNECTION AND ANY
ACCESS TO CONDUCTOR
WORK:
For work on the de-energized circuit which does not require any contact with insulators, associated fittings
or conductors. This scheme is to be followed during earthing for the following work :-
Painting up to vertical center line of tower towards the de-energized circuit.
PROCEDURE:
1. Apply Local Earths on all phases and on all sub-contractors at not more than 10 towers apart of the
de-energized circuit. At tension towers, the Local Earths shall be connected to the jumpers.
2. Incase Only one or two towers to be painted, only the working towers need to be earthed as per
62 | P a g e
Environment, Health and Safety Plan
normal procedure of earthing for suspension or tension towers, as the case may be .
3. Carry out the painting work on towers as per the normal procedure.
4. On completion of work, remove all additional earths/ local earths.
SCHEME-5
RAISING AND LOWERING PHASE CONDUTORS AT SUSPENSION TOWER.
FITTING REPAIR SLEEVES/JOINTS TO PHASE CONDUCTORS.
WORK:
For work on the de-energized circuit of a transmission line which involves raising and lowering Phase
conductors and the fitting of repair sleeves/ joints to be phase conductors. This scheme is to be followed
during earthing for the following work:-
PROCEDURE:
LOWERING AND RAISING CONDUCTORS
1. Local Earths shall be fixed on all phase on conductors and on all sub-conductors at the suspension
towers and at adjacent towers.
2. If a manual which is used, it shall be earthed to the tower using a Field Equipment Earth. All the
Pulleys used should have good electrical connection with the tower. The Pulleys should not have
any insulation that is rubber lining, etc.
3. Connect the rope with the conductor through pulley at suitable places in the tower and through
winch.
4. I f scaffolding is used in the span below conductor, the scaffolding shall be earthed by providing an
earth spike.
5. Before lowering the conductor, the Local Earth(s) shall be removed from that conductor and these
Local Earth(s) shall be kept suitably at the tower.
6. When the lowered conductor is at approximately four (04) meters from ground, additional earths
shall be applied from ground spike/ tower on to the lowered conductor(s).
7. When on the ground and the conductor has to be cut, Bridging Earth(s) shall be provided on both
sides of cutting point with ground spike on tower legs. Then as per working procedure, he
conductor shall be cut and joined. After joining the conductor, The Bridging Earth(s) shall be
removed.
8. The conductor(s) shall be raised up to 4 meters height from ground and additional earth(s) shall be
removed.
9. Raise the conductor(s) up to the cross arm level and apply the Local Earths on the Conductors.
10.On completion of work, remove all additional earths/ Local earths.
64 | P a g e
Environment, Health and Safety Plan
SCHEME-6
For work on the de-energized circuit of transmission line which involves lowering and raising phase
conductors and the fixing of repair sleeves / joints to the phase conductors. This Scheme is to be followed
during earthling for the following work.
1. Repeat scheme 2 for disconnection of jumpers. During repeating scheme-2, care shall be taken
while connecting bridging earths that one end is connected to tower side yoke plate / maintenance
65 | P a g e
Environment, Health and Safety Plan
3. Lower the conductor on the ground up to 4 Mts. Height & provide additional earth with ground
spike.
3. In case any cutting of conductor is required, provide Additional Earths on both side of cutting
points with ground spikes before cutting the conductors.
66 | P a g e
Environment, Health and Safety Plan
SCHEME -7
WORK:
Replacement of vibration dampers, copper bond and tightening of B/N of clamp etc.
PROCEDURE:
1. No earthing procedure is required as no shut down is to be taken for climbing up the double circuit
towers.
2. For single circuit towers. Follow the earthing scheme 1 for Suspension tower and tension towers.
67 | P a g e
Environment, Health and Safety Plan
68 | P a g e
Environment, Health and Safety Plan
SCHEME 8
PROCEDURE:
1. Obtain the shutdown of affected circuit on double circuit line and shut down of circuit of single
circuit line.
2. Provide earthing as per scheme 1 on all towers which require to be climbed.
3. Provide Additional Earths on the earth wire ends (2 mtr. away from ends) with earth spikes before
starting the job for mid span joints.
4. During rigging, the pulley used at cross arm end shall be provided with additional earth on to the
cross- arm. This is required if fiber round sling in place of wire rope sling has been used for
connecting the pulley.
5. Carry out repair & maintenance work on earth wire.
6. Raise the earth wire up to 4 Mts. Height from ground and then remove additional earth from
spikes.
7. Raise the earth wire up to cross arm level.
8. Removal all additional earths / local earths on completion of works.
69 | P a g e
Environment, Health and Safety Plan
SCHEME 9
70 | P a g e
Environment, Health and Safety Plan
The Emergency Response Plan shall describe how and to whom the BAJAJ Electricals Limited shall respond
in case of an emergency situation.
Emergency Response Plan shall describe the emergency organization, the routes of communication and
the measures to be taken to reduce the consequences of any emergency situation.
At each location a suitable number of firefighting extinguisher shall be provided to control and fire
emergency.
The emergency situations covered by the emergency response plan shall include:
Accidents with personal injury requiring assistance from outside authorities: (Contacts in
Construction management, other authorities)
Extreme weather conditions (flooding, high wind): (Contacts in Construction management, other
authorities)
Other emergency situations like Collapse of pit, Collapse of Tower, Snake bite, Fire in camp / Store,
Flood, Storm,
71 | P a g e
Environment, Health and Safety Plan
FIRST-AIDER
Rushes to the location arrange for Emergency Vehicle with medical aid.
If the First-Aider finds that the injured can be attended in the First-Aid center he will bring the
injured to the First-Aid center for treatment.
If treatment in the First-Aid center is not advisable, he will send the injured to approved
hospital nearby
PROJECT MANAGER
Responsible for activating the emergency plan and assuming overall command immediately
arrange for on-spot meeting. Take on-spot decision on the procedure to be adopted Arrange
required facilities. Communicate to client, and other concerned officials at site.
In case of fatal or likely to be fatal accidents, inform local police, Clients and consultants,
Manager Projects, Safety Head.
Organize agencies to restore the situation and arrange necessary aids for the rescue team.
72 | P a g e
Environment, Health and Safety Plan
Responsible for activating the emergency plan and assuming overall command in absence of
Project Manager immediately arrange for on-spot meeting. Take on- spot decision on the
procedure to be adopted Arrange required facilities. Communicate to client, and other
concerned officials at site.
In case of fatal or likely to be fatal accidents, inform local police, Clients and consultants,
Project Manager, Safety officer.
Organize agencies to restore the situation and arrange necessary aids for the rescue team.
COMMERCIAL OFFICER:
Ensure first aid facilities. Ensure arrangements for medical evacuation Coordinate with external
agencies
Arrange the required medical aid, foods etc.
Inform the legal and statutory concern and follow other local requirements.
Inform the family of the injured / deceased person.
Immediately inform to the Safety committee and organize for First Aid treatment.
Assist in the rescue team to remove people from the location.
Report the accident to site management immediately.
Act as a Co-ordinator for Emergency Response Committee
Collect all relevant information, witness for investigation.
Investigate the accident along with Safety committee and suggested suitable remedial
measures.
Ensure implementation of the remedial measures.
Collect details of manpower. Ensure the availability of first aid facilities and emergency vehicle. Carry
out head count at assembly point.
Place to be identified as Emergency Control Room (ECR) will be preferable adjacent to first aid
facility Shall be equipped with,
A Site layout showing assembly points and exit routes
Road maps leading to the site
List of telephone number of key personnel & other external agencies
List of Safety equipment.
List & location of firefighting equipment.
Emergency hand lamps
Hand operated alarm / siren/whistle ( as per site condition)
Log book & stationery
Declaration of Emergency:
Assembly point:
a. To be identified & clearly marked with signboards.
b. Signboards to be placed to indicate the direction to the assembly point from different work
areas
74 | P a g e
Environment, Health and Safety Plan
Head Count
Shall be taken by the Safety officer/safety supervisor at assembly point. It also includes accounting
for suppliers and customers
Emergency siren/whistle shall be put in site to alert site staff in case of emergency
The whistle/alarm shall be distinctive and recognized by all and may be
demonstrated during safety induction of new employees.
Following List shall be readily available at Emergency control room and site notice board and site
work location
A) HOSPITALS
B Distric Administration
Chitradurga – 577501.
POLICE STATION
D FIRE STATION
E CLIENT Personel
Ramesh Chitradurga 9448365263
76 | P a g e
Environment, Health and Safety Plan
Hard Stretcher
High Power search/torch light
Hand tools
Awareness Training
Awareness will be given at the time of safety induction prior to engaging employees at site.
Awareness Training for emergency response shall address,
Toxic chemicals,
Radioactive sources.
Mock drills
Fire Drill
Shall be carried out Every 3 months Schedule the fire drill program (date & time) and
77 | P a g e
Environment, Health and Safety Plan
78 | P a g e
Environment, Health and Safety Plan
HEAD-
SAFETY
Manager
Projects
Site Site
First Aider Commercial officer.
The objective of Safety Inspections is to verify that Safety provisions and practices conform to worksite
rules and regulations.
BAJAJ Electricals Limited shall establish and maintain documented procedures for Safety inspections to
ensure that unsafe conditions and practices at the worksite are identified and corrective measures are
implemented promptly and effectively.
Types of inspections:
79 | P a g e
Environment, Health and Safety Plan
Safety officer/Manager
Persons who are conversant with safe work practices, in-house rules and regulations and statutory
requirements carry out the Safety inspections.
Inspection Methodology
General regular safety inspection
Unsafe Condition and / or Unsafe Act which may lead to accidents, especially part of a plant or a
machinery or an equipment as well as the activities being undertaken during the execution of a job
Potential occupational health hazards and factors affecting hygiene at the workplace
Potential hazards causing harm to environment
Suggest suitable remedial action and facilitate implementation of corrective and preventive measures.
The general Safety Inspection will be carried out every day and it shall commensurate the dynamic &
rapid changes of the work site conditions.
The results of the inspection shall be recorded in the checklists and reported to the Project Manager in
the General Safety Inspection Report.
The major Inspection of Plant & Machinery and Equipment Including Vehicles will be carried out
fortnightly by Safety & Site In-charges as per inspection checklist.
The checklists that shall be used for this inspection shall include:
The results of the inspection shall be recorded in the checklists and reported to the site Manager in the
Plant & Machinery and Equipment Safety Inspection Report to rectify.
Workmen facility Inspection & store Safety Inspection will be carried out fortnightly.
The results of the inspection shall be recorded and reported to the Project Manager in
Workmen facility Inspection Report(EPC/EHS/CKL/02)
Store Inspection Report(EPC/EHS/CKL/27)
Follow up systems
The findings of the various inspections will be continuously followed up for implementation of corrective &
preventive actions. Follow up system includes;
Site Safety Supervisor notes down the UA/UC every day and informs the concerned engineer who will
rectify the UA/UC notified to him.
At the end of the week the Safety officer consolidates the findings and reports to the Project
81 | P a g e
Environment, Health and Safety Plan
Manager
The no. of UA/UC identified by him
The no. of UA/UC mitigated and balance no. of UA/UC
The Safety officer/HO also analyses the UA /UC trend and discusses them during the Site Safety
committee meeting.
The actions needed to eliminate the cause of non-conformities are discussed during the Site Safety
committee meetings
Control measures are applied to ensure that corrective and preventive actions as decided are taken and
that they are effective. The results are noted down as the number of points mitigated.
Project manager reviews the UA/UC report of site. The report shall minimum indicate the,
No of UA/UC observed
No of UA/UC mitigated
Safety Officer
EPC/EHS/CKL/29 02-07-2021, Rev-00
Hydra Details:
Model Engine No
Test certificate Yes No Validity: Chasis No
Hook 1 Hook 2 Hook 3 Extended boom
SWL
S
Check Items Observation Remarks
N
1 Load Chart available
2 Pollution Under Control (PUC) Certificate
82 | P a g e
Environment, Health and Safety Plan
S
Check Items Observation Remarks
N
3 Safety devices
a) Over load Limit switch
Limit switch & buzzer
Plate
b) Over hoist limit switch
Limit switch & buzzer
Over hoist plate/ Angle plate
c) Unloader valve
d) Inflator valve
e) Counter balance valve
83 | P a g e
Environment, Health and Safety Plan
S
Check Items Observation Remarks
N
3.(d)
f) Safety latches - Hook 1, Hook 2 & Hook 3
4 Cabin:
a) Battery
b) Clutch, Brake & Accelerator pedal
c) Stop cable
d) Indicators
e) Fire extinguisher
Cabin
4 Fire Extinguisher
Battery condition
5 Lifting assembly
a) Hook block
Hook and pulley
Wire rope sling connecting clips
c)
(bull dog clamps)
84 | P a g e
Environment, Health and Safety Plan
S
Check Items Observation Remarks
N
Correct method of securing dead end of wire
d)
rope sling?
(
a
) Hook block Hook latch Slings/ sheave Sling tightening
85 | P a g e
Environment, Health and Safety Plan
S
Check Items Observation Remarks
N
Boom extension Mainframe safety
86 | P a g e
Environment, Health and Safety Plan
S
Check Items Observation Remarks
N
EPC/EHS/CKL/28,02-07-2021, Rev-00
87 | P a g e
Environment, Health and Safety Plan
grounding?
8 Does the machine have a functional non-
manipulated spring loaded trigger switch for
ON/OFF mode?
9 Is the power cord connected with standard 3-core
sheathed cable and appropriate industrial plug top?
10 Does the power cord possess a trip hazard during
operations or to the operator/other persons?
11 Is the power cable damaged and wrecked (cuts,
joints poor insulation etc.)
12 Whether authorized person (trained and
experienced) is operating the machine after
obtaining necessary safety training? Name :
13 Is the operator equipped with all necessary PPEs,
prior to cutting works?
Do the authorized maintenance persons use
14 appropriate and safety measures during repairing
works?
Is the circular-saw fitted with its all necessary body
15 parts )
(Retracting lower blade guard/motor housing/Lever
for retracting lower blade guard/main show and
holder)
89 | P a g e
Environment, Health and Safety Plan
Safety Check List During Tower /Pole Erection Work 02-07-2021, Rev-00
EPC/EHS/CKL/25
Name of line/location where Client: Location No.:
applicable::
Name of person filling check list Date:
Contractor:
Frequency of check : Before every tower erection / set no. of poles erection
Sl Description Observation Remarks
NO.
1 Check whether supervisor/ gang leader has issued Yes/ No
instructions to workers before start of work on
that day.
2 Check whether supervisor/ gang leader has Yes/ No
provided safety guidelines (Tool box talk)
/instructions to workers before start of work
on that day.
a) All workers are using PPEs at site i.e. safety Yes/ No
shoes, helmets, gum boots, hand gloves,
safety harness with double lanyards etc. as per
job requirement Yes/ No
b) BEL officials are using PPEs at site
C) All workers working at height have locked their Yes/ No
safety belts
d) Ensured workers are using Mobile Fall Arrestor Yes/No
while ascending / descending from tower.
3 a) Check all lifting tools and tackles being used at Derrick=
site have been tested for safe working load Pulleys (open & Closed)=
and having valid test certificates.(copy of test Ropes/ Slings (wire rope)=
certificate be checked by Site In charge before P P Rope=
start of line work. D Shackles and Hooks=
b) Visual inspection of all T&P to be used at site Any other
have been identified with identification no.
and found to be in healthy condition.
4 All nuts bolts of stub are fitted and are tightened. Yes/ No
5All nuts bolts and step bolts fitted in tower have been Yes/ No
reasonably tightened before undertaking job of
upper section of tower.
6 Proper guying arrangement is made. Yes/ No
90 | P a g e
Environment, Health and Safety Plan
4Check that all nuts bolts and step bolts have been Confirmation from contractor: Yes/
tightened and punched properly before start of No
job. Sample checking by BEL: Yes/ No
5Check that all members are fitted in towers before Confirmation from contractor: Yes/
91 | P a g e
Environment, Health and Safety Plan
7 Check R clips in insulator caps are fixed properly Confirmation from contractor: Yes/
and necessary security pins (split pins) are also No
fixed. Ground Sample checking by BEL:
Yes/ No
8Back stay arrangements is made properly (if Yes/ No
required)
9 Ensure that rollers have Poly-Propylene coating. Confirmation from contractor: Yes/
No
Sample checking by BEL on rollers
lying at ground: Yes/ No
10 Winch, pulleys, TSE machines are properly Yes/ No
earthed.
93 | P a g e
Environment, Health and Safety Plan
94 | P a g e
Environment, Health and Safety Plan
Inspected by:
Name and signature with date
Name of site:.........................................................................................................
95 | P a g e
Environment, Health and Safety Plan
BAJAJ ELECTRICALS LIMITED. 02-07-2021, Rev-00
SAFETY DEPARTMENT.
CHECKLIST FOR EPC/EHS/CKL/08
96 | P a g e
Environment, Health and Safety Plan
SCAFFOLDING
Name of Site : Inspected by :
Sub-Contractors Name : Date :
Sl. Points Observation Measures
No.
1 Is site having a practice of providing suitable
and sufficient scaffolds so that the work could
safely be done at a height
2 Is site engaging suitable / properly trained /
experienced workmen for constructing /
dismantling / shifting scaffolding works
3 Are scaffold platforms designed/constructed
with a safety factor of minimum four?
4 Is there a safe means of access to the working
platform
5 Are scaffold structures having a solid base
avoiding pavements & manhole covers etc
6 Is the scaffolding structure free from
excavation pit/proper distance is maintained
7 Is verticality of the structure properly
maintained
8 Are ties for scaffold structure properly
maintained (vertical as well as horizontal
position)
9 Is there a provision of toe boards/guardrails
and are they secured
10 Whether planks used for working platforms are
wooden/metallic
11 If wooden plank, whether thickness is
maintained as per standard or not, viz.
a. For 1.5 M span - 1.5” thick
b. For 2.6 M span - 2.0” thick
12 Is there a system of inspecting the scaffolds by
a competent person at least once a week and
also after every prolonged interruption in the
work
13 Is there a system of inspecting materials of
scaffolds on each occasion before erection?
14 Is there a system of inspecting scaffolds at
every spell of bad weather/heavy wind
condition
15 Is overhanging of the working platform
restricted to less than 50mm/four times the
thickness of the board
16 Is awareness of workmen on the importance of
97 | P a g e
Environment, Health and Safety Plan
98 | P a g e
Environment, Health and Safety Plan
The objective of Safety training is to equip employees at all levels with the knowledge, skills and attitudes,
which will enable them to perform their duties in a safe and efficient manner.
Safety training including refresher training to supervisors, workers and Safety personnel. Proper training
records shall also be documented and maintained.
• Training shall be provided to all personnel In order to provide them with comprehensive training of
the rules and regulations, statutory requirements, procedures and instructions relevant to their
particular duties.
• Training shall also be provided for personnel at all levels of organization when necessary.
• Health and Safety forms an integral part of all training and employees will attend specific Health
and Safety courses, which include:
• Health and Safety training records will be retained for each member of staff in their personal files
and in a database managed by the Safety Managers.
99 | P a g e
Environment, Health and Safety Plan
All management personnel shall undergo internal Safety training, which shall include:
EHS/Safety Policy
Safety Organization
The Safety Team shall conduct the following in- house/on the job Safety training programs for on topics;
• EHS/ Safety Policy
• Safety Management System
• Safety Organization
• Statutory requirements on Safety
• Duties and responsibilities with respect to Safety
• Principles of Accident Prevention
• Electrical Safety
• Fire prevention & control
• Plant & Machinery
• Gas Cutting & welding
100 | P a g e
Environment, Health and Safety Plan
• Material Handling
• Height work
• Conductor stringing Activity
• Tower Erection activity
Safety Induction training:
All workmen, supervisors and visitors shall undergo the Safety induction. This would be a pre-
requisite workmen & supervisors/ visitors at the site.
Inputs for general requirements of Safety in the project shall be obtained from the Engineer/ client
and incorporated in the induction training.
Shall provide supplemental training within the assigned areas as may be required for skills training
or other Contractor training activities.
101 | P a g e
Environment, Health and Safety Plan
h) Others
102 | P a g e
Environment, Health and Safety Plan
d) Evacuation Plans
e) Accident / Injury Reporting
Procedures
f) Hospital / Clinic / First Aid
Facility
g) Others
103 | P a g e
Environment, Health and Safety Plan
c) Others d. Motivation
The trade specific internal training shall be provided to workmen and documented. To control the Hazard
in following activities / operations, the suitable number of site employees shall be trained and authorized
to perform these activities / operations. For all such site employees, authorization cards shall issue. Only
such employs are authorized to perform the respective activity,
Fire Fighting
Electrical power Tools and Equipment
Scaffolds /Access Platforms
Material handling
Work on Public and Third Party Property
Display Screen Equipment Operation
104 | P a g e
Environment, Health and Safety Plan
While designing & imparting training for workmen, differing levels of responsibility, ability, language skills
and literacy shall be taken in to account.
First aid is an immediate and temporary care given to the victim of an accident or in case of sudden illness
until the services of the doctor can be obtained. It is thus important for the first aiders to know what to do
and what not to do. Improper and careless movement of the victim should be avoided since it increases
severity.
Fire Drill:
Fire drill shall be conducted periodically to appraise the different section of work force about the fire
hazards at project site/store yard and familiarize them in basic firefighting techniques.
The HSE team identifies the location and target participants of the Fire Drill one week in advance and a
circular shall be issued for the same.
• Classification of fire
• Fire Hazards in their area of work
105 | P a g e
Environment, Health and Safety Plan
Depending upon the suitability a live demonstration shall also be conducted using simulated fires at the
designated places.
The details of the Fire Drill conducted with the name of the participants attended shall be recorded in the
Fire Drill Register by Safety team.
Training Records
BEL shall ensure that all Safety-training records are documented and maintained in the form of a training
register. Only authorized the person can operates or work on the jobs. The records shall be maintained
their respective trade trainings. The register shall contain the following details:
106 | P a g e
Environment, Health and Safety Plan
Premedical health checkups shall be done for new workmen before engaging to the work and periodical, it
shall be followed and records shall be maintained.
During the execution of the project all the statutory requirements as listed below shall be followed.
1. Electrical License.
2. Building & other construction worker’s (Regulation of Employment and Condition of Service Act 1996
and Rules 1998) and welfare Cess Act 1996 with rules.
107 | P a g e
Environment, Health and Safety Plan
5. License under the contract Labor (Regulation & Abolition) Act 1970 and Rules.
6. The Environment Protection Act 1986 & Rules.
7. The Contract Labor Act 1970.
8. Central Electricity Authority (Safety requirements for Construction, Operation and Maintenance of
Electricals plants & Electric Lines) regulations 2011
9. Pre-Employment Medical Examination as per BOCW Act.
10. IS Certification (9001:2015)
11. The Electricity Rules 1956 (Amended 2000)
108 | P a g e
Environment, Health and Safety Plan
109 | P a g e
Environment, Health and Safety Plan
110 | P a g e