Professional Documents
Culture Documents
ENGINEERING
PROJECT
MANAGEMENT
Normal Activity
Normal
cost
Normal
time
Crash time Activity time
Reducing Project Completion Time
• Crashing a project needs to balance
▫ Shorten a project duration
▫ Cost to shorten the project duration
• Crashing a project requires you to know
▫ Crash time of each activity
▫ Crash cost of each activity
Crash cost/duration = (crash cost-normal
cost)/(crash time – normal time)
Project Crashing
Activity Precedence Duration Cost £ Slope
days (normal, (£/day)
(normal, crashed)
crashed)
a - 3, 2 40, 80 40/-1
= -40
b a 2, 1 20, 80 -60
c a 2, 1 20, 50 -30
d c 2, 1 30, 60 -30
e b 3, 1 10, 80 -35
Project Crashing Example
3
b e
1
a
2 4 6
8 days
c
£120
d
5
3
b e
Crash e
a
1 2 4 6
c 7 days
d £155
5
0 1 2 3 4 5 6 7 8 days
Project Crashing Example
3
b e Crash e, a
a 6 days
1 2 c 4 6
d £195
5
3
b e
Crash e, a, d, e
a
1 2 c 4 6 5 days
d £260
5
0 1 2 3 4 5 6 7 8 days
Project Crashing Example
3
b e Crash e, a, d, e, b, c
a 4 days
1 2 4 6
c £350
d
5
0 1 2 3 4 5 6 7 8 days
CLASS ACTIVITY
Activity Precedence Normal Normal Crash Crash Cost
Time Cost Time Cost Slope
(Tn) (Cn) (Tc) (Cc)
(days) ($1K) (days) ($1K)
A - 4 $210 3 $280
B - 9 $400 6 $640
C A 6 $500 4 $600
D A 9 $540 7 $600
E B,C 4 $500 1 $1100
F B,C 5 $150 4 $240
G E 3 $150 3 $150
H F,D 7 $600 6 $750
Questions to Answer
1. Verify that the normal completion time is 22 days
and that the direct cost is $3,050.
2. What is the least costly way to reduce the project
completion time to 21 days? What is the project
cost?
3. What is the least costly way to reduce the
completion time to 20 days? What is the project
cost?
4. Now, What is the earliest the project can be
completed and what is the least costly way of doing
this? What is the project cost?
Discussion