TIME PLAN & DURATION

Time duration to complete this job following work scopes that given by our company are within seven (7)) days not including
mobilization and demobilization.
PROJECT TITLE : DIESEL ENGINE FWD FIRE PUMP
PROJECT : FSO PUTERI DULANG
CLIENT : FPSO VENTURES SDN BHD

PROJECT WORKS SCHEDULE

WORK DAY DAY DURATION DELAY DAY


RESONS OF DELAYS
DECCRIPTION STARTED COMPLETED (DAY) (DAY)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

OVERHAUL DIESEL
ENGNE VOLVO
PENTA

Send Sparepart &


7 days depend on boat schedule
Tools via boat.

Dismantle Acessories
1 day
& External Part

Dismantle Internal
Part, Inspection &
2 days
Cleaning All Internal
parts.

Install New Internal


Parts 2 days
(supplied by TGS)

Install Accessories &


1 day
external Parts

Commissioning &
Testing, Witness by 1 day
client

7 days
LEGEND PLANNED