Professional Documents
Culture Documents
Planning and
Management
.
Project Scope
Once the project is selected, its scope must be defined as it sets the
stage for developing the project plan, project scope (Scope refers to a
project’s boundaries, it determines what work will be completed during the
project lifecycle).
A 5 -
B 2 A
C 18 B
D 10 -
E 15 D
F 5 E,C
Simple Gantt chart in excel
A Gantt chart is a type of bar chart, devised by Henry Gantt in the 1910s, that
illustrates a project schedule.
PERT
Project Evaluation & Review Technique
4/4/2022 21
Task Dependencies in Projects- they are of four (4) types
P Predecessor must finish before Successor can start. [Land
must be purchased before building a record centre] –
S Finish to Start
22
Dependency determination integration Attributes
o Mandatory dependencies
o Discretionary dependencies
o External dependencies
o Internal dependencies
4/4/2022 23
o Mandatory dependencies– impossible to reverse sequence
due to the nature of the project work. A must do sequence.
o Discretionary dependencies – can delete dependency of the
project based on experience and the decisions are usually based
upon best practices, business knowledge on projects of similar
nature.
o External dependencies – dependent on some event external to
the project which the project team does not have control over
it..e.g suppliers
o Internal dependencies - relationship between two tasks or
activities within the project and are generally within the project
team.
4/4/2022 24
Brief description of the tools for estimating resources
1. Expert judgment means bringing in experts who have done this sort of work
before and getting their opinions on what resources are needed.
2. Alternative analysis means considering several different options for how you
assign resources. This includes varying the number of resources as well as the
kind of resources you use. Many times, there’s more than one way to accomplish
an activity and alternative analysis helps decide among the possibilities.
3. Published estimating data is something that project managers in a lot of
industries use to help them figure out how many resources they need. They rely
on articles, books, journals, and periodicals that collect, analyse, and publish data
from other people’s projects.
4. Project management software such as Microsoft Project will often have features
designed to help project managers estimate resource needs and constraints and
find the best combination of assignments for the project.
5. Bottom-up estimating means breaking down complex activities into pieces and
working out the resource assignments for each piece. It is a process of estimating
individual activity resource need or cost and then adding these up together to
come up with a total estimate
Estimating Activity Durations
Once you’re done with activity resource estimating, you’ve got everything you need to
figure out how long each activity will take.
1. Expert judgment will come from your project team members who are familiar
with the work that has to be done. If you don’t get their opinion, there’s a huge
risk that your estimates will be wrong.
2. Analogous estimating is when you look at similar activities from previous
projects and how long they took. This only works if the activities and resources
are similar.
3. Parametric estimating means plugging data about your project into a formula,
spreadsheet, database, or computer program that comes up with an estimate.
The software or formula that you use for parametric estimating is based on a
database of actual durations from past projects.
4. Three-point estimating is when you come up with three numbers: a realistic
estimate that’s most likely to occur, an optimistic one that represents the best-
case scenario, and a pessimistic one that represents the worst-case scenario.
The final estimate is the weighted average of the three.
5. Reserve analysis means adding extra time to the schedule (called a contingency
reserve or a buffer) to account for extra risk.
Activity Durations
The activity duration estimates are an estimate of how long each
activity in the activity list will take.
This is a quantitative measure usually expressed in hours, weeks,
days, or months.
Another thing to keep in mind when estimating the duration of
activities is determining the effort involved. Duration is the
amount of the time that an activity takes, while effort is the total
number of person-hours that are expended. If it takes two people
six hours to carve the ice sculpture for the centrepiece of a
wedding, the duration is six hours. But if two people worked on it
for the whole time, it took 12 person-hours of effort to create.
Resource Levelling
Resource levelling is used to examine unbalanced use of resources (usually
people or equipment) over time and for resolving over-allocations or
conflicts.
When performing project planning activities, the manager will attempt to
schedule certain tasks simultaneously. When more resources such as
machines or people are needed than are available, or perhaps a specific
person is needed in both tasks, the tasks will have to be rescheduled
sequentially to manage the constraint.
Resource levelling during project planning is the process of resolving these
conflicts.
It can also be used to balance the workload of primary resources over the
course of the project, usually at the expense of one of the traditional triple
constraints (time, cost, scope).
On resource levelling consider project slack time and critical path
Slack/float time can be defined as the amount of time any task can be delayed without
causing another task to be delayed or impacting the completion date of your project.
Critical path: Longest sequence of activities in a project plan which must be completed
on time for the project to complete on due date
Project budgeting
Reliable cost estimates are necessary for all projects. Without a cost estimate it
would be impossible to prepare a budget plan for the entire project.
Cost Budget
Control Account
Rolled up into
Project
ADD
Contingency Reserve
ADD
Management Reserve
33
Terms commonly used on project costing
1. Absorption costing - means that all of the manufacturing
costs are absorbed by the units produced.
2. Direct costs – costs that can be directly attributed to the project work.
3. Cost of sales - the cost of purchasing raw materials and manufacturing
finished products.
4. General and administration costs - The fixed cost incurred in the
operation of a business e.g office space rental, plant and equipment,
staffing, and expenses
5. Indirect costs – cost that must be incurred to operate the business as a
whole, so they cannot be attributed to a single product.
6. Labour burden – a percentage of wages paid to employees on non
working days (overtime)
7. Variance – the difference between actual cost and budgeted cost
8. Overhead costs - costs required to run a business, but which cannot be
directly attributed to any specific business activity (“What must I pay for
each month in order to keep my business open?“)
Project budgeting
Determine the physical resources Estimate the financial resources
Parametric estimating
Analogous estimating (top down estimating – not very
accurate – costing of the whole unit based on previous
data e.g cost of constructing a bridge, is normally used
on construction projects where cost are usually known)
Three-point estimating
Expert judgment
Reserve analysis (contingency)
Bottom-up cost estimating - Bottom up estimating is a
thorough estimation of the project by estimating each and every
work package in the WBS (for projects that have no published data
which the project team can rely on – innovation projects
Budget variance analysis
Item Planned Actual Variance Comment Flexed budget
budget budget
Total
Sample Budget estimation for a project
Consultation
Project Leader 10 75 750
with partners
Preparation of
Department
project 40 80 3200
Head
proposal
Contract
1000 1000
expertise
Total : 6950
Definition phase
Who Hours Fees Total
Consultation with
Project Leader 10 75 750
end users
Functional
10 65 650
Designer
Consultation with
Project Leader 20 75 1500
experts
Functional
30 65 1950
Designer
Internal Experts 30 100 3000
Contract
2500
expertise
Catering for
250
meetings
Project
25 75 250
management
Subtotal: 128450
Unexpected costs 10% 13495
Total: 141945