Professional Documents
Culture Documents
Finish work
Start
Design house and
obtain financing
darla/smbs/vit Select7 carpet
Order and receive
Select paint
materials
Arrow Diagramming Method (ADM)
Also called activity-on-arrow (AOA) project network diagrams
Activities are represented by arrows
Nodes or circles are the starting and ending points of
activities
Can only show finish-to-start dependencies
Used for CPM and PERT estimating methods
Some rules
Only one start and one end
Nodes do not have durations
Sample Activity-on-Arrow (AOA)
Network Diagram for Project X
Process for Creating AOA Diagrams
1. Find all of the activities that start at node 1. Draw their finish
nodes and draw arrows between node 1 and those finish
nodes. Put the activity letter or name and duration estimate
on the associated arrow
2. Continuing drawing the network diagram, working from left to
right. Look for bursts and merges. Bursts occur when a single
node is followed by two or more activities. A merge occurs
when two or more nodes precede a single node
3. Continue drawing the project network diagram until all
activities are included on the diagram that have dependencies
4. As a rule of thumb, all arrowheads should face toward the
right, and no arrows should cross on an AOA network diagram
Cont…
Use of nodes and arrows
Arrows: An arrow leads from tail to head directionally. It Indicate ACTIVITY,
a time consuming effort that is required to perform a part of the work.
Nodes A node is represented by a circle
- Indicate EVENT, a point in time where one or more activities start and/or
finish.
• Activity
– A task or a certain amount of work required in the project
– Requires time to complete
– Represented by an arrow
• Dummy Activity
– Indicates only precedence relationships
– Does not require any time of effort
Cont…
Remarks
The network should be read from left to right
There is only one start and one end node
Nodes do not have duration
Tasks/activities should be named and should
have durations
Situations in network diagram
B
A A must finish before either B or C can start
C
A
C both A and B must finish before C can start
B
A
C both A and B must finish before either of
B C or D can start
D
A B
A must finish before B can start
Dummy
both A and C must finish before D can start
C
D
Sample PDM Network Diagram
Activity Duration Estimating
After defining activities and determining their
sequence, the next step in time management is
duration estimating
Duration includes the actual amount of time worked on
an activity plus elapsed time
Effort is the number of workdays or work hours
required to complete a task. Effort does not equal
duration
People doing the work should help create estimates,
and an expert should review them
Cont…
Time estimates for tasks have to take in to
account such factors as:
Efficiency of the project team members, Possible
interruptions, Size of the project team, Availability of
users, Complexity of the business function to be
analyzed and Experience of team members and so forth
D= OD + 4*ED + PD
6
incentives
discipline
negotiation