Professional Documents
Culture Documents
Network Analysis
Examples
A major event like a wedding
Any construction project (dam, road, railway, school,
etc.)
Designing a political campaign
Project Life Cycle
Conception: identify the need
Feasibility analysis or study: costs
benefits, and risks
Planning: who, how long, what to do?
Execution: doing the project
Termination: ending the project
Network Concept
Networks:
Networks illustrate the way in which the parts of the
project are organized.
They can be used to determine the time duration of the
projects.
The network techniques that are used for project
analysis are PERT and CPM.
PERT stands for Project Evaluation and Review
Technique, whereas CPM is an acronym for Critical
Path Analysis.
6.2. PERT and CPM and Diagram
Construction
Program Evaluation & Review Technique (PERT):
Developed to manage the project duration
© Wiley 2007
PERT & CPM Cont’d
one?
Which activities can directly start after finishing this
one?
Which activities can be done in parallel to this one?
2 0
Finish
Build work 7
3 house 6
1 1
1 2 4 3
1
Order
Design house &
materials 1
obtain financing
Select Select
paint carpet
5
Network Drawing
Exercise:
Draw a network for Construction of House by using Activity on
Arrow
Activity Description Immediate Duration in
Predecessor week
A Design a house ____ 3
B Lay foundation A 3
C Obtain Finance A 2
D Order materials B&C 1
E Paint select D 4
F Select Carpet E 1
G Start house construct D 1
H Finish Work G &F 1
Importance of Network
diagram
To answer:
What is the total time to complete the project?
What are the scheduled start and finish dates for
each specific activity?
Which activities are critical and must be completed
exactly as scheduled to keep the project on
schedule?
How long can noncritical activities be delayed
before they cause an increase in the project
completion time?
AON Diagrams
Order & relationships are shown as arrows
Any activity may either:
Succeed (follow) – task B succeeds task A
Precede (go before) – task A precedes task B
TASK A TASK B
AON Diagrams
Any activity may:
Be performed concurrently – Task C can be performed at
the same time as Task D
TASK C
TASK D TASK E
AON Diagrams –Rules
Direction
Arrows should always go forward
The flow of work is from left to right
TASK C
TASK C
TASK D TASK E
TASK D TASK E
AON Diagrams –Rules
Arrows should only go from one node to
another node.
TASK C
TASK C
TASK D TASK E
TASK D TASK E
AON Diagrams –Rules
Avoid overlapping arrows
TASK C
TASK C
TASK D TASK F
TASK D TASK E
TASK E
AON Diagrams –Rules
If overlapping can not be avoided, use
bridges
TASK C
TASK D TASK E
TASK D
AON Diagrams –Rules
There should be one starting node (Start
Project) and one finishing node (Project
Complete) for each activity.
TASK C TASK D
TASK Start TASK Finish
TASK D TASK E
AON Diagrams –Rules
In a CPM network, two or more activities
are not allowed to share the same starting
and ending nodes at the same time.
Lay
foundation
4
2
Order
materials
AON Diagrams –Rules
0
2
1
4
2
Order
materials
AON Diagrams –Rules
An AON diagram should not contain more
than 50 nodes.
Preparing AON:
Identify the order that tasks must be done
order.
6.4. Basic steps in Network diagram----
CPM &PERT
• For each task, estimate the lowest (optimistic), most likely, and
highest (pessimistic) durations, then use:
• estimated Average time = (low + high + 4*most likely)/6
• steps 1 to 4 are also known as the planning phase
Basic steps in Network diagram----
CPM &PERT Cont’d
What are the latest start and finish dates for each activity
Immediate Duration
Activity Description
Predecessor (weeks)
A Develop product specifications None 4
B Design manufacturing process A 6
C Source & purchase materials A 3
D Source & purchase tooling & equipment B 6
E Receive & install tooling & equipment D 14
F Receive materials C 5
G Pilot production run E&F 2
H Evaluate product design G 2
I Evaluate process performance G 3
J Write documentation report H&I 4
K Transition to manufacturing J 2
Step 2- Diagram the Network for
Cables By manufacturer
Step 3 (a)- Add Deterministic Time
Estimates and Connected Paths
Step 3 (a) (Con’t): Calculate
the Project Completion Times
Paths Path duration
ABDEGHJK 40
ABDEGIJK 41
ACFGHJK 22
ACFGIJK 23
The longest path (ABDEGIJK) limits the project’s
duration (project cannot finish in less time than
its longest path).
ABDEGIJK is the project’s critical path.
6.5. Some Network Definitions
Critical Path: –
o The series of activities all of which must finish
on time for the whole project to finish on time.
i=4).
LF 4 = Minimum ( LF6 – t46, LF5- t45)
= 7-6
= 1 Month (This means activity 5 can
be delayed 1 month without delaying the project.
Calculating Slack
Late Early Slack
Activity
Finish Finish (weeks)
A 4 4 0
B 10 10 0
C 25 7 18
D 16 16 0
E 30 30 0
F 30 12 18
G 32 32 0
H 35 34 1
I 35 35 0
J 39 39 0
K 41 41 0
6.9. Probabilistic Time Estimates
As an alternative to CPM, PERT ( Project Evaluation and Review
Technique) uses probabilistic activity time.
The three time estimates for each activity are the most likely time,
the optimistic time, and the pessimistic time.
Probabilistic Time Estimates Cont’d
2 A,B,D,E,G,I,J,K 4.96
3 A,C,F,G,H,J,K 2.24
4 A,C,F,G,I,J,K 2.38
Calculating the Probability of Completing
the Project in Less Than a Specified Time
When you know:
The expected completion time
Its variance
Example:
Suppose that the cable manufacturing company
Penalty clauses
70
Cost slope
Solution:
Step 1: Draw the network and determine the critical path.
C (2)
F (3)
A (4)
E (3)
G (2)
B (8)
D (10)
Crashing Network Exercise
Total project cost = normal cost + crash cost = 630+ (2x50) = Br 730
Crashing Network Exercise
Step 4: Since we have fully used the crash time for B, now
crash critical activity D by four weeks (NB we can’t crash
activity D by more than four weeks because the four weeks
crash on activity D has made activities E and F to be on critical
paths).
Two Critical paths: The first is A, B, D & G and new
730+(60*4=240) = Br 970
Crashing Network Exercise
Step 6: We can further crash activity A by two weeks but not activity F
(Activity F can be crashed for one more week, but if we crash it, the critical path
A, B, E, F and G will be lost. When activity A is crashed by two weeks, the
following will be the result of crashing :
Two Critical paths: The first is A, B, D and G; and the second is A, B, E, F
Total project cost = Cost of step 5 + crash cost (crash cost of A) = Birr1040
83
Example 2: Given the information below, find the maximum length of the
schedule and the minimum cost schedule when the indirect cost is Birr70 per
day.
84
2
4 13
C (2)
A (4) 4
F(3)
0 5
13 15
18 18
0 0 E (5)
B (8) 3 D (10)
8 8
85
Example Cont’d
86
Example Cont’d
580+100 = 680
Indirect Cost = 70X16 = 1120
87
Example Cont’d
Step 3: Since we have fully used the crash time for B, now crash
critical activity D by two days
Two Critical paths: the first is B and D; and the second
is B, E and F.
Project duration 14 days
680+(60*2=120) = 800
Indirect Cost = 70X14 = 980
88
Example Cont’d
is B, E and F.
Project duration is 12 days
89
Example Cont’d
second is B, E and F.
Project duration is 11 days
91
6.11.The advantages of network technique