Professional Documents
Culture Documents
7
CONSTRUCTION
PLANNING NETWORKS
Review of Lecture No. 6:
Construction Planning Techniques
Planning Techniques discussed:
Bar Charts (Gantt Charts)
S-Curve
Line of balance
Time chainage Charts
Critical Path Method (CPM)
Precedence Diagramming Method (PDM)
Program Evaluation and Review Technique (PERT)
Note: A more detailed treatment of these may be done
towards the end of the semester.
Coverage – Lecture No. 7
Introduction to Planning Networks;
Steps and Procedures of Preparing planning
networks;
AOA Networks;
AON Networks
Introduction
Critical Path Method (CPM) or Critical Path
Analysis or activity on the arrow diagram started to
be used after Bar charts failure in highlighting the
activity interdependencies.
An activity is a unit of work in the project schedule.
An activity is a scheduled phase in a project plan
with a distinct beginning and end. An activity usually
contains several tasks upon completion of which the
whole activity is completed. Several activities can be
combined to form a summary activity.
Sample Activity on the Arrow
Network
Activity A Acivity B
Activity on the Arrow
Steps in preparing are as mentioned above
1. Listing the activities
2. Producing a logical network of activities:
Activity represented by an arrow
Length of arrow is irrelevant unless the network is
drawn to a time scale.
Activity on the Arrow (contd..)
Questions to ask yourself in order to check that a
correct logic is maintained:
Which activities must be complete before this
activity starts?
Which activities cannot start until this activity is
complete?
Which activities have no logical relationship with
this activity and can therefore take place at the same
time?
Activity on the Arrow (contd..)
At times it might be necessary to introduce dummy
arrows, drawn as broken lines which do not
represent any activity but are simply a logical link.
Definition: A dummy activity is one that is used to
maintain the pre-defined precedence relationship
only during the construction of the project network,
is called a dummy activity
Activity on the Arrow (Contd..)
Identifying the activities :
The points where arrows start and finish are called
events. The numbering of these events provides a
method of identification.
Sample use of dummy activities
Finish
Start event event
Install Motor
i j
A B
1 2 3
B
2
D
B
5
C D
3 6
2
3 A3
A2
B3
A1 5 6
1 2
B1 4 B2
Overlapping Activities: the use of lead and lag times
Dig
Trench
1 3
Lead Lag
Backfill
5 6
Construction of a Network
Maintain a numbering system in which each
activity has a unique i-j humber;
To that it may be necessary to introduce a dummy-
for example in the Figure below Activities B, C and
D have the same i-j numbers i.e. 2-3, and in this
case it is necessary to introduce a dummy to ensure
that each activity has a unique i-j number.
Dummy activities 3-5 and 4-5 introduced each with
a duration of 0
Use of Dummies B
A C E
1 2 3 4
D
B 3 Dummy
A C E
1 2 5 6
D Dummy
4
Use of Dummies
Build Construc
Walls t Roof
Make Install
Window Window
Frames Frames
Use of Dummies
Build Construc
Walls t Roof
1 4
Make 3
Window Install
Frames Window
Frames
2
5
Use of Dummies – Dummy activity 3-4 introduced
Build Construc
Walls t Roof
1 3 5
Make Install
Window Window
Frames Frames
2 4 6
Summary of Guidelines for drawing
the arrow -network
Each activity is shown by a single arrow;
The network is not drawn to scale;
B 5
A C E
1 2 6 7
3 4
Common Errors in Network Programming:
Redundancy Error – dummy activity 2-4 is
unnecessary as it is not needed for network logic
B 3
C
A E
1 2 4 7
Time Analysis and the Critical Path
Key question for any project- How long will the
project take?
Once durations have been given to each activity, on
overall time can be calculated by using the forward
pass.
Time analysis and the Critical Path
Determination of Duration of Activity
The time required for each activity needs to be
estimated; the estimate of duration will be based
on knowledge of the work, experience, records and
work study. or
Activity Duration = Man days/crew or
Activity Duration = Quantity of work to be
done/output of resources
Calculation of earliest completion time – Forward
Pass
Method Statement
Estimation of duration and resources required.
Refer SC 401 by Dr. Mlinga
7 7
1 5
C- 2 4
2
D- 6
A- 1
B- 7 E- 5 F- 3
1 3 5 6
0 0 7 7 13 13 16 16
duration.
the latest time of the finish event LESS
Activity Independent
Duration Float
Start Finish
TEi Event TLi TEj event
TLj
D- 6
A- 1
B- 7 E- 5 F- 3
1 3 5 6
0 0 7 7 13 13 16 16