Professional Documents
Culture Documents
Lect#5
Scheduling
Project Time Management
Processes
Project Time Management
Project Time Management includes the processes required to
ensure timely completion of the project.
3. Activity Duration Estimating –Estimating the number of work periods that will be
needed to complete individual activities.
Purpose:
• To break down the work of the project into manageable components so that
time, resource and cost could easily be determined.
• Each task/activity should be broken down to the point where these estimates
are easily derived.
The Critical Path Method was developed by DuPont at about the same
time
PERT has been primarily used for research and development projects
CPM was designed for construction projects and has been generally
embraced by the construction industry
Use network to help plan, schedule, monitor and control the project
Network Techniques “PERT & CPM”
Activity - A specific task or set of tasks that are required by the project, use up
resources, and take time to complete.
Event - The result of completing one or more activities. An identifiable end state
occurring at a particular time. Events use no resources.
Network - The combination of all activities and events define the project and the
activity precedence relationships
Path - The series of connected activities (or intermediate events) between any two
events in a network
Critical - Activities, events, or paths which, if delayed, will delay the completion of
the project.
Network Techniques “PERT & CPM”
a
c
b
a
c
Dummy Activity
1 4
a c
3
b d
2 5
1 a c
3 4
b d
2 6 5
Incorrect Representation
(A)
(C) 3
1 2
(D)
(B) 4
Activity Immediate
Predecessors
A -
B -
Correct it?...
C A
D A, B
Correct Representation
C
A
1 2 3
Dummy Activity
B
5 4
D