Professional Documents
Culture Documents
Planning The project team uses expert judgment, analytical techniques, and meetings to
Schedule develop the schedule management plan, which includes:
Management Project schedule model development
Level of accuracy and units of measure
Control thresholds
Rules of performance measurement
Reporting formats
Process descriptions
1
ITM750 Week 4
Sequencing Activities
Dependencies Pertains to the sequencing of project activities or tasks. You must determine
(relationship) dependencies in order to use critical path analysis. Types of dependencies:
Mandatory (hard logic): inherent in the nature of the work being
performed on a project (ex. codes cannot be tested until they are written)
Discretionary (soft logic): defined by the project team—should be used
with care because they may limit later scheduling options
External: involve relationships between project and non-project activities
Network A schematic display of the logical relationships among project activities and their
Diagrams sequencing. Two main formats are the arrow and precedence diagramming
methods
2
ITM750 Week 4
3
ITM750 Week 4
for monitoring project progress for the time dimension of the project
Important tools and techniques include Gantt charts, critical path analysis,
and critical chain scheduling, and PERT analysis
Gantt Charts Provide a standard format for displaying project schedule information by listing
project activities and their corresponding start and finish dates in calendar form
Black diamond: a milestone
Thick black bars: summary tasks
Lighter horizontal bars: duration of tasks
Arrows: dependencies between tasks
Critical Path A networking diagramming technique used to predict total project duration
Method (CPM) Critical path: the series of activities that determine the earliest time by
which the project can be completed
Slack/float: amount of time an activity may be delayed without delaying a
succeeding activity or the project finish date
4
ITM750 Week 4
It is not the one with all the critical activities—only accounts for time
There can be more than one critical path if the lengths of two or more
paths are the same
Can change the project progresses
Critical Chain A method of scheduling that considers limited resources when creating a project
Scheduling schedule and includes buffers to protect the project completion date
5
ITM750 Week 4
Program A network analysis technique used to estimate project duration when there is a
6
ITM750 Week 4
Evaluation and high degree of uncertainty about the individual activity duration estimates
Review Uses probabilistic time estimates—duration estimates based on using
Technique optimistic, most likely, and pessimistic estimates of activity durations, or a
(PERT) three-point estimate
PERT weighted average = (optimistic time + 4X most likely time +
pessimistic time )/6
Agile and Time Core values of the Manifesto for Agile Software Development are:
Management o Customer collaboration over contract negotiation
o Responding to change
Product owner defines and prioritizes the work to be done within a sprint,
so collaboration and time management are designed into the process
Teams focus on producing a useful product in a specified timeframe with
strong customer input
Using Software Software for facilitating communications helps people exchange schedule-
to Assist in related information
Time Decision support models help analyze trade-offs that can be made
Management Project management software can help in various time management areas