Professional Documents
Culture Documents
Management
Presenters
2
Project Schedules
3
Importance of Project Schedules
4
Individual Work Styles and Cultural
Differences Cause Schedule Conflicts
5
Project Time Management Processes
Activity definition: Identifying the specific activities that the project team members and
stakeholders must perform to produce the project deliverables.
Activity sequencing: Identifying and documenting the relationships between project
activities.
Activity resource estimating: Estimating how many resources a project team should use to
perform project activities.
Activity duration estimating: Estimating the number of work periods that are needed to
complete individual activities.
Schedule development: Analyzing activity sequences, activity resource estimates, and
activity duration estimates to create the project schedule.
Schedule control: Controlling and managing changes to the project schedule.
6
Activity Definition
7
Activity Lists and Attributes
8
Milestones
9
SMART Criteria
Specific
Measurable
Assignable
Realistic
Time-framed
10
Activity Sequencing
11
Three Types of Dependencies
12
Network Diagrams
13
Arrow Diagramming Method (ADM)
14
ADM
15
ADM
16
ADM
17
ADM
18
Precedence Diagramming Method (PDM)
19
Task Dependency Types
Activity Resource Estimating
21
22
Risk Register
23
Resource Calendar
24
Estimate Activity Resources Process
Activity Duration Estimating
Activity duration estimating is the process of taking information on project scope and
resources and then developing durations for input to schedules.
Estimating the number of work periods required to complete an activity will often require
consideration of elapsed time as well. For example, if “concrete curing” will require four
days of elapsed time, it may require from two to four work periods based on (a) which day of
the week it begins on and (b) whether weekend days are treated as work periods
26
Three-Point Estimates
27
Schedule Development
28
Gantt Charts
29
30
Critical Path Method (CPM)
31
32
Using the Critical Path to Shorten a Project
Schedule
Three main techniques for shortening schedules:
33
Critical Chain Scheduling
34
Buffers and Critical Chain
A Buffer is additional time to complete a task.
Critical Chain is the longest path in the network diagram that takes into
consideration task dependency and resource availability. It’s a modified
form of Critical Path Method where project activities use aggressive
time and have access to unlimited resources.
While Critical Path Method uses Float, Critical Chain uses buffers as
strategic points that eliminate uncertainty around projects.
35
There are four types of buffers:
Project Buffer - protects the project from missing its scheduled end date and
keeps the completion date unchanged. It is inserted at the end of the project
network diagram, between the last task and the completion date. It protects
project completion date, which might vary due to the changes in activity durations
in the critical chain. In other words, the size of the project buffer depends on the
activities in the critical chain.
Feeding Buffer - is inserted between the last task on a non-critical chain and the
critical chain. These buffers are typically added to a non-critical chain so that any
delays on a non-critical chain don’t affect the critical chain.
36
There are four types of buffers:
Resource Buffer - these are set on the Critical Chain to ensure appropriate
resources (people, equipment) are available throughout the project when needed.
These resources are commonly known as Critical Resources.
37
38
Program Evaluation and Review Technique
(PERT)
PERT is a network analysis technique used to estimate project duration when
there is a high degree of uncertainty about the individual activity duration
estimates.
39
40
Beta Distribution
PERT weighted average =
ABC Corp is planning on building a new CRM system. They've been storing your customer records on
paper for the past decade, causing many errors and delays for their customers. You are the project
manager for the project, and based on your past experiences, you believe the project will take 10 weeks
to complete. Optimistically, it could take as little as 6 weeks, and if some issues do occur, the worst case
scenario is that the project might take 20 weeks to complete. What is the duration estimate for this
project?
41
PERT Formula and Example
PERT weighted average =
42
Schedule Control
Perform reality checks on schedules.
Allow for contingencies.
Don’t plan for everyone to work at 100 percent capacity all the time.
Hold progress meetings with stakeholders and be clear and honest in
communicating schedule issues.
43
Schedule Control
Goals are to know the status of the schedule, influence factors that cause
schedule changes, determine that the schedule has changed, and manage
changes when they occur.
Tools and techniques include:
◦ Progress reports.
◦ A schedule change control system.
◦ Project management software, including schedule comparison charts, such
as the tracking Gantt chart.
◦ Variance analysis, such as analyzing float or slack.
◦ Performance management, such as earned value
44
Reality Checks on Scheduling
Review the draft schedule or estimated completion date in the project charter.
Prepare a more detailed schedule with the project team.
Make sure the schedule is realistic and followed.
Alert top management well in advance if there are schedule problems.
45
Working with People Issues
Strong leadership helps projects succeed more than good PERT charts do.
◦ Empowerment
◦ Incentives
◦ Discipline
◦ Negotiation
46
Summary
Project time management is often cited as the main source of conflict on
projects, and most IT projects exceed time estimates.
47