You are on page 1of 5

International Journal of Engineering and Advanced Technology (IJEAT)

ISSN: 2249 – 8958, Volume-8, Issue-2S2, January 2019

Estimation of Cash Flow from Value of Work


Done for Construction Projects in India
G Dhamodaran, K.R.Divakar Roy 

ABSTRACT--- Background/Objectives: To estimate the Cash the project completion on time. These decisions are being
Flow from Value of Work Done (VoWD) for a Construction taken based on the cash flow forecasts. Hence accurate cash
project in Indian environment flow projection is important.
Methods: Deducting mobilisation advance and retention
amounts from total Value of Work done completion.
II. PRESENT METHOD BEING FOLLOWED IN
Results/Findings: Can be implemented at construction
industryespecially for the process plant construction projects. THE INDUSTRY
Conclusion/Application: 'Cash flow estimation every month in Currently the traditional method getting some gestimate
part of construction progress calculation’ can be implemented in figures from the contractors and conveying the same with
construction industries which helps Client organization to some safety margin to Project Manager for funding
arrange required fund in advance
arrangement. Project Managers request the same with
Keywords: Value of Work Done (VoWD) - a quantitative
Management and Management is arranging the same with
project performance value which is calculated based on the
Earned Value Method (EVM) some financing agencies or from banks in the form for
loans. While approaching the financing institutes, the
I. INTRODUCTION projection given by the Project Manager is considered as the
basis and accordingly fund is released. Due to inaccurate
Cost management is one of the important aspects of
forecasting, either facing shortage of cash or left with
Effective project management like Scope management,
unused money4.
Time management, Change management, Risk management
It flows from the client to the contractor and on to the
and Communication management. Budgeting and
subcontractors and suppliers. It is beneficial for clients to
monitoring the budget and ensuring effective cost control
know the cash flow plan in advance, to arrange funding
system implementation are keeping a control on the project
sources accordingly, and ensure smooth functioning of the
with which cost overrun of the project can be controlled.1 At
project (Kenley, 2003). Similarly, accurate cash flow
the same time, monitoring cash flow is critical to ensure the
forecasting is essential for the survival of any contractor at
seamless execution of the project throughout the entire
all stages of the work.
construction period. The budgeted cost will be spent in
distributed manner and will not be of linear. Some system A. Classical methods
should be in place to ensure allocation of the required cost The procedure of the classical method can be seen in any
on time. Any delay in arrangement of fund will interrupt the text book of Project management. This is prepared by
construction work hence required amount should be tabulating periodic payments and receipts using the project
estimated and provided to management in advance to allow Gantt chart as basis5.
time for sourcing2.
Construction product transportation is a physical activity B. Mathematical methods
involved in the flow of things between the point of origin Many researches developed mathematical models based
and the point of consumption in order to meet requirements on various assumptions. Khosrowshahi has proposed a
of customers or corporations7. Money is important resource mathematical model for forecasting of project expenditure
like man, machine and material for any of the project which by identifying variables associated with the physical shapes
supports day to day operation of construction execution. of expenditure profiles for different types of projects. This is
Because of inadequate cash flow to support construction suitable only for contractual negotiations.
many of the projects failed or delayed. Delayed fund Park, Han & Russell have attempted to estimate cash
arrangement delays the project and on other hand early flows by categorization of different project activities on the
arrangement of fund Costs Company to pay huge financing basis of time lags involved between their physical
charges3. As cash is the resource arranged by management, occurrences of different stages6.
it is regarded as management resource. Cash flow Jarrah, Kulkarni &O‟Connor collected actual cash flow
management is based on controlling, updating, monitoring data in form of monthly account summary reports for
and forecasting the cash flow. During the project progress, various projects under Texas Department of Transportation.
many financial related decisions would be taken to ensure The sample consisted of different category of projects such
as construction and replacement of bridges, new non-
Revised Manuscript Received on December 22, 2018. freeways, road overlay and rehabilitation of existing roads,
G Dhamodaran, School of Mechanical Engineering, Department of
Mechanical Engineering, Academy of Maritime Education and Training
(Deemed to be University), Chennai.
Dr.K.R.Divakar Roy, Department of Mechanical Engineering,
Andhra University.

Published By:
Blue Eyes Intelligence Engineering
Retrieval Number: B10900182S219/19©BEIESP 433 & Sciences Publication
ESTIMATION OF CASH FLOW FROM VALUE OF WORK DONE FOR CONSTRUCTION PROJECTS IN
INDIA
landscape scenic enhancements, widening of freeways etc. warehouse, batching plant, fabrication shops, material
Projects were further classified in different cost ranges. storage yard, etc.
Based on the scatter chart of payments against time for
Retention
different projects in a given category, a fourth degree
polynomial regression analysis was used to obtain the cash Retention is the percent of money retained by the owner
flow curves that turned out to be characteristic „S‟ shaped from every invoice by deducting before making the payment
for most of the projects. to contractor against certified invoice. This is to ensure the
Although statistical significance could not be proved due performance of the work performed by the contractor to
to limited availability of data, a feasible approach for cash minimum period after completion of the work. The
flow prediction was established7. accumulated retention amount will be paid to the contractor
He has suggested a set of new measurements and after completing the guarantee period varies from 12 months
indicators based on contract prices and financial accounts to 24 months in Indian conditions.
for the proposed „contractor cash flow‟ model in line with Running account bills
the „earned value‟ measurements and indicators in view of
This is amount of money equivalent to the work
possible integration of both systems. Wages and benefits is
performed by the contractor which will be as per the
an important motivators of the employees working in civil
contractual provisions of the contract. Rate for the every
construction companies.8
activity will be defined in the contract along with the
There are many more research papers by various
quantity to be executed. Upon completion of certain quantity
researchers trying to get the accurate model and are either
from the Bill of Quantities, for every month contractor will
too ideal conditional projects or involve more calculations
raise the invoice against the certification. After receipt of the
which generally not being followed in many projects.
invoice this will be certified and will be paid in next month.
Currently there is no any standard model to estimate the
cash flow. B. Major Terminologies
If the employers fails to fulfil the salary structure
Contract
company the performance level will not improve as
expected by the higher authorities.9 Functioning of a well- Contract shall mean the agreement between Company and
established organization need the hard work of employees. Contractor as set out in Scope of Works document,
Recruitment and selection is a long-lasting one and a central Completion Schedule, Contract Price or Contract Value,
aspect of HR Management. There was lot of problems needs General and Special conditions all as may, from time to
to be handled by the HR department10 Labor welfare time, be supplemented or otherwise modified in accordance
facilities are an important tool to increase the productivity of with applicable provisions
the employees in any organization. Contract Value
Salary along will not motivate the employees, so in
Contract Value shall mean total Contract Price payable by
addition to the company must provide some welfare benefits
Company to the Contractor for rendering the service in
to their employees11.This paper investigates the impact of
accordance with the agreed price schedule.
Internal Locus of Control on personal variables and job
related factors. The primary research strategy employed was Contract Schedule or Schedule
the survey strategy12. Researcher is very much interested on Schedule shall mean the time schedule for performing
emission rates to know which mode of transport if more Contract services and will be changed from time to time if
eco-friendly and remove logistical problems. SICAL required.
Logistics has recently started a new project named Coastal
RORO service as a part of their green logistics13. C. Estimating the Cash Flow from VOWD
Mobilization advance
III. PROPOSED METHOD TO CALCULATE CASH
This is the amount to be given to the Contractor for his
FLOW FORECAST FROM VALUE OF WORK
mobilization expenses. Contractor is required to establish
To predict the cash flow requirements, the terminologies his office, warehouse, labor camp, fabrication shop, storage
and types of cash flows are to be understood to accurately yards, testing laboratories etc. To set up these infrastructure
estimate the cash flow. facilities, Contractor requires certain amount which is
A. Definitions generally in India it varies from 10 to 15 % and mostly it is
of 10% of the contract value.
Advanced payment This will be paid generally in the 1st month. Accordingly
This is amount of money paid to the contractor for Cash Out can be expressed as a step function as below.
mobilization purposes. Then, it is deducted from running CO=10% of Contract Value for the first month
bill of contract progress payment. Facilitating this COi=MA X CV if i=1 (1)
mobilization advance improves the contractor cash flow
during his initial period of contract and ensures them to Where,
mobilize completely. However this strategy to be used only COi=Cash Out for ith month
for projects which require expensive site preparatory
requirements like contractor office, contractor labor camp,

Published By:
Blue Eyes Intelligence Engineering
Retrieval Number: B10900182S219/19©BEIESP 434 & Sciences Publication
International Journal of Engineering and Advanced Technology (IJEAT)
ISSN: 2249 – 8958, Volume-8, Issue-2S2, January 2019

CV=Contract Value man-hours are individual weightage for each of the activity.
MA=Mobilization Advance in % These productivity norms are majorly depends on
i=Month technologies involved, machineries employed etc. The
tabulated productivity norms are generally being followed in
Progressive payments
India.
Total Contract Value will be paid to the contractor with
respect their progress. After completing the work in every Table-1: Total Bill of Quantities and their weightages
month, Contractor periodically every month he raises S
Unit
Total Man-
Effort
Activity Scope UoM Man- Weightag
invoice based on the joint measurement sheet with field No
hour
hour
e
engineers. This invoice will be settled within some 1 Concreting 12000 CUM 75 900000 40%
stipulated time which will be generally 30 days in Indian 2 Structural Steel Fabrication 4000 MT 120 480000 22%
conditions. From this certified amount, the percent of 3 Structural Steel Erection 4000 MT 95 380000 17%
mobilization advance paid on 1st month will be deducted
4 Piping Fabrication 12000 ID 3.5 42000 2%
proportionate to be percent of Mobilization advance paid.
5 Piping Erection 35000 IM 4.5 157500 7%
COi=MA X CV if M=1 6 Equipment Erection 4500 Mt 50 225000 10%
= [∑ (Pij X CRj)]X (1-MA)if 1<M<n (2) 8 Electrical Cable Laying 1500 MTR 1 1500 0%

Where, 9 Instrumentation Cable Laying 3000 MTR 1 3000 0%

COi=Cash Out for ith month 10 Painting 14000 SQ.MTR 3 42000 2%


Pij=Activity wise Physical progress certification for ith 2231000 100.0%

month
CRj=Contract Rate for respective activity The weightages above are calculated based on the effort
MA=Mobilization Advance in percentage of Contract required to complete each of the activity. Each activity in
Value the Bill of Quantities are measured in different unit of
i=Month measurement (UOM) and it is necessary to convert them
n=Project Duration excluding Performance guarantee into one measurement entity. Only man-hour effort or the
period money to be spent can substitute this requirement.
Further, this Cash Out to be adjusted with retention These above calculated weightages are useful for progress
amount. calculation and for the each of the activity there will be
Retention Amount defined rates in Contract. These rates can be used to arrive
the cost weightage for the each activity to be carried out for
The portion of amount which is retained by client to the project which will be used for estimating the cash flow
ensure the performance of the facility which was built by the and other financial decisions.
contractor. Upon end of performance period, this entire
amount will be released to the Contractor. B. Cash Out estimation based on the progress with cost
Accordingly the Cash Out can be estimated as below weightage
COi =MA X CV if M=1 The cost weightage is depends on the quantum of each
= [∑ (Pij X CRj)]X (1-MA) X [1/ (1-R)] if 1<M<n activity and its respective contractual rate as effort based
= R XCV if M=m (3) weightage depending on quantum of the work and its
respective productivity norms. Accordingly, we can tabulate
Where, the above table to arrive to the cost weightage.
COi=Cash Out for ith month
Pij=Activity wise Physical progress certification for ith Table-2: Total Bill of Quantities and their weightages
month Cost
S
CRj=Contract Rate for respective activity No
Activity Scope UoM Unit Rate Contract Value Weightag
e
MA=Mobilization Advance
1 Concreting 12000 CUM 12000 144000000 38.92%
i=Month
2 Structural Steel Fabrication 4000 MT 20000 80000000 21.62%
n=Project Duration excluding Performance guarantee
period 3 Structural Steel Erection 4000 MT 15000 60000000 16.22%

R-Retention Amount in % of Contract Value 4 Piping Fabrication 12000 ID 1000 12000000 3.24%

m= 1st month after completion of performance guarantee 5 Piping Erection 35000 IM 500 17500000 4.73%

period 6 Equipment Erection 4500 Mt 12000 54000000 14.60%

8 Electrical Cable Laying 1500 MTR 200 300000 0.08%


IV. ESTIMATING CASH FLOW FOR A SAMPLE
Instrumentation Cable
PROJECT & RESULTS 9
Laying
3000 MTR 250 750000 0.20%

10 Painting 14000 SQ.MTR 100 1400000 0.38%


A. Cash Out estimation based on the progress with effort
369950000 100%
earned weightage
This can be seen from a small example and we can
forecast the Cash Out. The efforts required for each of the
activity are tabulated and the contribution to overall project

Published By:
Blue Eyes Intelligence Engineering
Retrieval Number: B10900182S219/19©BEIESP 435 & Sciences Publication
ESTIMATION OF CASH FLOW FROM VALUE OF WORK DONE FOR CONSTRUCTION PROJECTS IN
INDIA
The rates tabulated above are indicative and not as per D. Comparison between plan and actual values of effort
any real Contract. But the rates are approximately similar to based estimation and Contractual rate based
the rates given in Contracts issued in India. estimation
C. Comparison between plan and actual values of effort The actual cash flow will be only based on the cost and
based estimation and Contractual rate based not based on the effort based progress. Hence, the cash out
estimation to be estimated based on the cost weightages. To derive this
the progress calculations, the bill of quantities considered in
We consider one plan and actual scenario for the sample
the Contract needs to be used for estimating the progress.
data and we can compare the values. The table below shows
Plan and actual values of the bill of quantities. The planned Table-5:Plan and Actual values of progress with cost
quantities are planned while planning for the project and the weightages
actual quantities are estimated at end of every month or Percentage of Invoicing Planned and Actual
Contract Cost Plan /
week as agreed with the management. Forecasting of the S No Activity Scope UoM Unit Rate
Value Weigtage Actual
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14

quantities can be done at the end of every period. 1 Concreting 12000 CUM 12000 144000000 38.92%
Plan
Actual
500.00 1000.00 2000.00 2000.00 2000.00 2000.00 2000.00 500.00
300.00 800.00 1000.00 1500.00 1500.00 1500.00 2000.00 2000.00 1400.00
Structural Steel Plan 500.00 500.00 1000.00 1000.00 1000.00
2 4000 MT 20000 80000000 21.62%
Table-3: Plan and Actual values of progress with effort Fabrication
Structureal Steel
Actual
Plan
500.00 500.00 500.00 500.00 1000.00 1000.00
500.00 500.00 1000.00 1000.00 1000.00
3 4000 MT 15000 60000000 16.22%
weightages Erection Actual
Plan
500.00 500.00 500.00 500.00 1000.00 1000.00
3000.00 3000.00 3000.00 3000.00
4 Piping Fabrication 12000 ID 1000 12000000 3.24%
Actual 2000.00 2000.00 2000.00 2000.00 2000.00 2000.00
Total Percentage of Value of Work Planned and Value of Work Done Plan 5000.00 8000.00 8000.00 8000.00 6000.00
Unit Man- 5 Piping Erection 35000 IM 500 17500000 4.73%
S No Activity Scope UoM Man- Weigtage Remark Actual 5000.00 5000.00 5000.00 5000.00 5000.00 5000.00 5000.00
hour
hour M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 Plan 500.00 1000.00 1000.00 1000.00 1000.00
6 Equipment Erection 4500 Mt 12000 54000000 14.60%
Plan 500.00 1000.00 2000.00 2000.00 2000.00 2000.00 2000.00 500.00 Actual 800.00 800.00 800.00 800.00 800.00 500.00
1 Concreting 12000 CUM 75 900000 40%
Actual 300.00 800.00 1000.00 1500.00 1500.00 1500.00 2000.00 2000.00 1400.00 Plan 500.00 500.00 500.00
Electrical Cable
Structural Steel Plan 500.00 500.00 1000.00 1000.00 1000.00 8 1500 MTR 200 300000 0.08%
2 4000 MT 120 480000 22% Laying Actual 500.00 500.00 500.00
Fabrication Actual 500.00 500.00 500.00 500.00 1000.00 1000.00
Structureal Steel Plan 500.00 500.00 1000.00 1000.00 1000.00 Instrumentation Plan 1000.00 1000.00 1000.00
3 4000 MT 95 380000 17% 9 3000 MTR 250 750000 0.20%
Erection Actual 500.00 500.00 500.00 500.00 1000.00 1000.00 Cable Laying Actual 1000.00 1000.00 1000.00
Plan 3000.00 3000.00 3000.00 3000.00 Plan 2000.00 5000.00 5000.00 2000.00
4 Piping Fabrication 12000 ID 3.5 42000 2% 10 Painting 14000 SQ.MTR 100 1400000 0.38%
Actual 2000.00 2000.00 2000.00 2000.00 2000.00 2000.00 Actual 3000.00 4000.00 4000.00 3000.00
Plan 5000.00 8000.00 8000.00 8000.00 6000.00
5 Piping Erection 35000 IM 4.5 157500 7% 369950000
Actual 5000.00 5000.00 5000.00 5000.00 5000.00 5000.00 5000.00
Plan 500.00 1000.00 1000.00 1000.00 1000.00
6 Equipment Erection 4500 Mt 50 225000 10%
Actual 800.00 800.00 800.00 800.00 800.00 500.00

8
Electrical Cable
Laying
1500 MTR 1 1500 0%
Plan 500.00 500.00 500.00 We can recalculate the Cash Out values based on the cost
Actual 500.00 500.00 500.00

9
Instrumentation
Cable Laying
3000 MTR 1 3000 0%
Plan
Actual
1000.00 1000.00 1000.00
1000.00 1000.00 1000.00
weightages as below
Plan 2000.00 5000.00 5000.00 2000.00
10 Painting 14000 SQ.MTR 3 42000 2%
Actual 3000.00 4000.00 4000.00 3000.00
2231000 100.0% Tabe-6:Cash Flow out percentages based on effort based
weightage
The estimated Cash Out are as below. First two rows are
plan and actual values from progress values considering Plan/Actual
Plan
Considerations
Cash Flow with Mob Adv
M1
10.00%
M2
3.89%
M3 M4 M5
7.18% 13.26% 17.15% 18.98% 14.13%
M6 M7 M8
9.82%
M9
5.24%
M10
0.18%
M11
0.12%
M12
0.05%
M13
0.00%
M14
0.00%
mobilisation advances. Second two rows are values of Actual Cash Flow with Mob Adv 10.00% 3.31% 6.59% 7.66% 12.07% 14.50% 16.32% 12.92% 9.29% 6.31% 0.79% 0.16% 0.07% 0.00%
Plan PG Retention 0.43% 0.80% 1.47% 1.91% 2.11% 1.57% 1.09% 0.58% 0.02% 0.01% 0.01% 0.00% 0.00%
performance guarantee amount pro-rated to all balance Actual PG Retention 0.37% 0.73% 0.85% 1.34% 1.61% 1.81% 1.44% 1.03% 0.70% 0.09% 0.02% 0.01% 0.00%
Plan CF with Mob Adv& PG 10.00% 3.46% 6.38% 11.79% 15.25% 16.87% 12.56% 8.73% 4.66% 0.16% 0.11% 0.04% 0.00% 0.00%
months till project completion and this will be released after Actual CF with Mob Adv& PG 10.00% 2.94% 5.86% 6.81% 10.73% 12.89% 14.51% 11.48% 8.26% 5.61% 0.70% 0.14% 0.06% 0.00%

completion of performance guarantee period. Third two Cum Plan


Cum Actual
Cash Flow Final Plan
Cash Flow Final Actual
0.10
0.10
0.13
0.13
0.20
0.19
0.32
0.26
0.47
0.36
0.64
0.49
0.76
0.64
0.85
0.75
0.90
0.83
0.90
0.89
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
rows are by making the adjustments of performance
guarantee from the previously mobilisation adjusted From these comparison, the weightages are nearly similar
derivative and every time whenever we forecast the quantities, the cash
out also can be easily estimated based on the equations
Table-4: Cash Flow out percentages based on effort
indicated above.
based weightage
These above results being represented graphically as
Plan/Actual Considerations M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 below for the Contract rate based plan and actual values of
Plan Cash Flow with Mob Adv 10.00% 3.93% 7.36% 13.23% 17.06% 18.62% 13.80% 9.58% 4.92% 0.65% 0.61% 0.24% 0.00% 0.00%
Actual Cash Flow with Mob Adv 10.00% 3.33% 6.76% 7.64% 11.68% 14.10% 16.02% 12.69% 8.87% 6.58% 1.45% 0.52% 0.36% 0.00% Value of Work Done (calculated based on rate) and the Cash
Plan PG Retention 0.44% 0.82% 1.47% 1.90% 2.07% 1.53% 1.06% 0.55% 0.07% 0.07% 0.03% 0.00% 0.00%
Actual PG Retention 0.37% 0.75% 0.85% 1.30% 1.57% 1.78% 1.41% 0.99% 0.73% 0.16% 0.06% 0.04% 0.00%
Flow.
Plan CF with Mob Adv& PG 10.00% 3.50% 6.54% 11.76% 15.17% 16.55% 12.26% 8.52% 4.37% 0.57% 0.54% 0.22% 0.00% 0.00%
Actual CF with Mob Adv& PG 10.00% 2.96% 6.01% 6.80% 10.38% 12.53% 14.24% 11.28% 7.89% 5.84% 1.29% 0.47% 0.32% 0.00%
Cum Plan Cash Flow Final Plan 0.10 0.13 0.20 0.32 0.47 0.64 0.76 0.84 0.89 0.89 0.90 0.90 0.90 0.90
Cum Actual Cash Flow Final Actual 0.10 0.13 0.19 0.26 0.36 0.49 0.63 0.74 0.82 0.88 0.89 0.90 0.90 0.90

These above results can be plotted in the following graph


which shows plan and actual values of the Value of Work
Done and the Cash Flow estimated. Planned and actual cash
flow are shown in step graphs and the planned& actual
values are shown in S-curve.

From these two graphs the estimated cash out can be


estimated. This estimation to be regularly calculated and to
be projected to the management depends on the forecast
which will help him in estimating.

Published By:
Blue Eyes Intelligence Engineering
Retrieval Number: B10900182S219/19©BEIESP 436 & Sciences Publication
International Journal of Engineering and Advanced Technology (IJEAT)
ISSN: 2249 – 8958, Volume-8, Issue-2S2, January 2019

V. CONCLUSION Journal of Mechanical Engineering and Technology,


Volume 18 Issue 7, pp 1095-1102. 2017.
As this reduces lot of man-hour efforts and time this
method can be encouraged for many of the construction
AUTHORS PROFILE
projects. Also this helps in forecasting accurate cash flow
G Dhamodaran received his Bachelor Engineering in
and supports management in arranging the cash required in Mechanical Engineering from Bharathiar University
advance. Change Orders arises out of change in scope are to Coimbatore and Master Engineering in Manufacturing
be added to the Contract Value after approval and the same Technology from PRIST University, Tanjavur since 1997
and 2011 respectively. He is currently a PhD Student in
procedure will be followed while dealing with these AMET University, Chennai. His research interest is in
approved Change Orders. Construction Project Progress Monitoring and Measurement.
Further the method explained above can be extended to
other pre-construction activities like, engineering, ordering, Dr KR Divakar Roy received his Bachelor Engineering
in Mechanical Engineering from Andhra University,
manufacturing, delivery etc. The entire estimation is not
Visakaphatnam and Master Engineering in Industrial
taking care of the taxation part and is to be added before Engineering from Andhra University, Visakaphatnam
projecting to the management. since 1974 and 1985 respectively. He received his PhD in
2009 from Andhra University for his research topic “Growth Strategies for
an integrated steel- A System Dynamics Approach. Published many
REFERENCES number of papers and attended various national and international
1 Banki, M. T., and Esmaeili, B., “The effects of variability conferences. Fellowship in Institute of Engineers (India).
of the mathematical equations and project categorizations
on forecasting S-curves at construction industry”,
International Journal of Civil Engineering, 7(4), 258-270,
2009.
2 Kenley, R., “Financing construction: cash flows and cash
farming” London : Spon Press, 2003.
3 Khosrowshahi, F., “Project cash flow forecasting: a
mathematical approach”, 17th Annual ARCOM
Conference, 5~7 September 2001, University of
Salford,Association of Researchers in Construction
Management, 2001
4 Park, Hyung K., Han Seung H.; Russel, Jeffrey S., “Cash
Flow Forecasting Model for General Contractors using
Moving Weights of Cost Categories”, Journal of
Management in Engineering, October page 164~172,
2005
5 Görög, Mihály, “A comprehensive model for planning
and controlling contractor cash-flow”, International
Journal of Project Management 27 481-492. 2009.
6 Ra‟ed Jarrah, Devdatta Kulkarni and James T. O‟Connor,
“Cash Flow Projections for Selected TxDoT Highway
Projects”, Journal Of Construction Engineering And
Management © ASCE / Page 235-241. 2007.
7 Srinivasan, R.,Poongavanam, S.,Divyaranjini, R,
“Construction product movement in NTC - A case study
analysis”, International Journal of Civil Engineering and
Technology, Volume 9, Issue 9, August 2018, Pp 942-
946. 2018.
8 Poongavanam, S., Viswanathan, R., “Civil construction
employees opinion on wage and benefits - A study”,
International Journal of Civil Engineering and
Technology, Volume 8, Issue 7, Pp 1014-1019. 2017.
9 Poongavanam, S., “Pharmaceutical employees
compensation plan– A case study on their satisfaction”,
Indian Journal of Public Health Research and
Development, Volume 9, Issue 8, Pp 1605-1608. 2018.
10 Poongavanam, S., “A study on HR department and MIS
system followed in pharma companies”, Indian Journal
of Public Health Research and Development, Volume 9,
Issue 8, , Pp 1584-1587. 2018.
11 Poongavanam, S., “ Employee welfare measures &
industrial hygiene in civil construction company - A
study”, International Journal of Civil Engineering and
Technology, Volume 8, Issue 7, Pp 69-77. 2017.
12 Poongavanam, S., “The influence of internal locus of
control on personal and job oriented factors”,
International Journal of Economic Research, Volume 14
Issue 3, Pp 273-279. 2017
13 Poongavanam, S., “A comparative analysis of cox
emissions by road and sea transport”, International

Published By:
Blue Eyes Intelligence Engineering
Retrieval Number: B10900182S219/19©BEIESP 437 & Sciences Publication

You might also like