Professional Documents
Culture Documents
Management Insider
Page 1 of 29
Contents
1. Project Management Methods ........................................................................................................................................................ 2
2. Earned Value Management Definition ............................................................................................................................................ 3
3. Why Use EVM? ................................................................................................................................................................................ 3
4. PERFORMING EVM ANALYSIS .......................................................................................................................................................... 4
4.1. Planned Value (PV) ......................................................................................................................................................4
4.2. Actual Cost (AC) ...........................................................................................................................................................6
4.3. Earned Value (EV) ........................................................................................................................................................8
5. Metrics and Performance Measurements ..................................................................................................................................... 11
6. Variances........................................................................................................................................................................................ 12
6.1. Schedule Variance (SV) ..............................................................................................................................................12
6.2. Cost Variance (CV) .....................................................................................................................................................14
6.3. Variances: Review ......................................................................................................................................................16
7. Performance Indices ...................................................................................................................................................................... 17
7.1. Schedule Performance Index (SPI).............................................................................................................................17
7.2. Cost Performance Index (CPI) ....................................................................................................................................18
8. Review of Variance and Performance Indices ............................................................................................................................... 20
9. Estimate at Completion (EAC)........................................................................................................................................................ 21
10. Budget at Completion (BAC) ...................................................................................................................................................... 24
11. Other Formulas to calculate Estimate at Completion (EAC)...................................................................................................... 25
12. Summery.................................................................................................................................................................................... 27
References .......................................................................................................................................................................29
For example, if a task has a planned duration of ten days with thirty hours of work
duration, after five days it would be deemed fifty percent Complete even though the work
duration put in might be only 10 hours, so to complete the balance work another twenty
hours needs to be put in which may require more than the balance five days since as per the
plan only three hours a day was planned for the task.
Earned Value Analysis (EVA) is a method that allows the project manager to measure
the amount of work actually performed on a project beyond the basic review of cost
and schedule reports.
By using Earned Value and implementing of Earned Value Management (EVM), the
following questions can be answered objectively:
Earned Value, which also known as Budgeted Cost of Work Performed (BCWP)
Actual Cost, which also known as Actual Cost of Work Performed (ACWP)
Planned Value, which also known as Budgeted Cost of Work Scheduled
(BCWS)
– Cost and Schedule baseline refers to the physical work scheduled and the
approved budget to accomplish the scheduled work.
– PV tells you what you plan to do, or how much work should have been done
and how much was it meant to cost?
Simply stated,
PV, also known as Budget Cost of Work Scheduled (BCWS) and consists of a 5 step
process as follows:
1. Define Scope: What you are tasked to do (Scope Statement)
2. Assign Scope: Breakdown scope into manageable parts (WBS)
3. Schedule Scope: Time-phased, logic driven with critical path (Project Schedule)
4. Budget Scope: develop cost (budget) for all approved scope (Performance Measurement
Baseline)
5. Baseline: Snap-shot in time, frozen. What performance measurement will be based on?
[EARNED VALUE MANAGEMENT] MANAGEMENT INSIDER
Cumulative
Current PV
is the approved budget for PV
activities scheduled to be is the sum of the approved
performed during a given budget for activities
period. This period could scheduled to be
represent days, weeks, performed to date.
months,etc.
Based on these figures, we can calculate the cumulative PV and the current PV.
– The Current PV is the budget for the current month, March, and equals $3,000.
– The Cumulative PV is the total for the elapsed months: January – March. The
cumulative PV is $9,000.
– Actual Cost (AC), also called actual expenditures, is the cost incurred for
executing work on a project.
– This figure tells you what you have spent, or what was the actual cost of work
actually performed?
– As with Planned Value, AC can be looked at in terms of current and
cumulative.
Cumulative
Current AC is the actual costs of AC
activities performed is the sum of the
during a given period. actual cost for
This period could activities performed to
represent days, weeks, date.
months,etc.
– The Current AC is the actual cost for the current month, March, and equals $3,500.
– The Cumulative AC is the total for the elapsed months: January – March. The
Cumulative AC is $9,500.
– To report the accomplishments of the project, you must apply Earned Value
(EV) to the figures and calculations in the project.
– In other words, EV tells you, in physical terms, what the project has
accomplished.
Simply stated,
Cumulative
Current EV
is the sum of the EV is the sum of the
budget for the budget for the
activities activities
accomplished in a accomplished to
given period. date.
– The Current EV is the sum of the budget for the activities accomplished in the current
month, March, and equals $1,000.
– The Cumulative EV is the sum of the budget for the activities accomplished to date:
January – March. The cumulative EV is therefore $4,400.
Review
At this point, you should have a solid understanding of the three key earned value
components. Let’s review them now.
Variance • Schedule Variance (SV) = Earned Value (EV) – Planned Value (PV)
Analysis • Cost Variance (CV) = Earned Value (EV) – Actual Cost (AC)
6. Variances
– SV is the difference between the earned value of work performed and the
work scheduled.
– SV tells you the value of work performed verse the value of work
scheduled
– SV Compares what is done with what was supposed to be done?
Current Status PV EV AC
Piping $25,000 $24,000 $25,500
HVAC Duct $8,500 $8,500 $8,000
Raceways $3,200 $1,500 $2,200
Total $36,700 $34,000 $35,700
SV = EV – PV
SV = $34,000 – $36,700
SV = -$2,700 what does this tell you?
A Schedule Variance of -$2,700 tells you that the project is “Behind” schedule
Tells you what percentage schedule varies from what has been planned to date.
– CV is the difference between the earned value of work performed and the
actual cost.
– CV Compares actual project cost with budgeted project costs.
Current Status PV EV AC
Piping $25,000 $24,000 $25,500
HVAC Duct $8,500 $8,500 $8,000
Raceways $3,200 $1,500 $2,200
Total $36,700 $34,000 $35,700
CV = EV – AC
SV = $34,000 – $35,700
SV = -$1,700 what does this tell you?
A Cost Variance of -$1,700 tells you that the project is “overrun” or over budget
Tells you what percentage cost varies from what has been earned to date
You should have a solid understanding of the cost and schedule variance
calculations and what they mean. Let's review them now
Schedule Cost
Variance Variance
(SV) = EV – PV (CV) = EV – AC
Using these variance calculations on our previous project example information as follows:
Current
PV EV AC SV CV
Status
Piping $25,000 $24,000 $25,500 -$1,000 -$1,500
HVAC Duct $8,500 $8,500 $8,000 $0 $500
Raceways $3,200 $1,500 $2,200 -$1,700 -$700
Total $36,700 $34,000 $35,700 -$2,700 -$1,700
7. Performance Indices
Current Status PV EV AC
Piping $25,000 $24,000 $25,500
HVAC Duct $8,500 $8,500 $8,000
Raceways $3,200 $1,500 $2,200
Total $36,700 $34,000 $35,700
SPI= EV / PV
SPI= $34,000 / $36,700
SPI= 0.93 what does this tell you?
A Schedule Performance Index (SPI) of 0.93 tells you that you are behind schedule. It can be
defined in two ways:
Current Status PV EV AC
Piping $25,000 $24,000 $25,500
HVAC Duct $8,500 $8,500 $8,000
Raceways $3,200 $1,500 $2,200
Total $36,700 $34,000 $35,700
CPI= EV / AC
CPI= $34,000 / $35,700
CPI= 0.95 what does this tell you?
A Cost Performance Index (CPI) of 0.95 tells you that your actual costs are greater than what
was budgeted.
You are getting $0.95 worth of work for every $1.00 spent
Using all previous variance calculations on our previous project example information as
follows:
Current
PV EV AC SV CV SPI CPI
Status
Piping $25,000 $24,000 $25,500 -$1,000 -$1,500 0.96 0.94
HVAC Duct $8,500 $8,500 $8,000 $0 $500 1 1.06
Raceways $3,200 $1,500 $2,200 -$1,700 -$700 0.47 0.68
Total $36,700 $34,000 $35,700 -$2,700 -$1,700 0.93 0.95
From previous calculation on mentioned project, we came to a conclusion that, the project
is 7% behind schedule (SPI=0.93), also greater by 0.5% than budget cost (CPI=0.95) which
means the project is overrun its budget and behind schedule.
Schedule Cost
Schedule Variance (SV) = EV – PV Cost Variance (CV) = EV – AC
– If the result is POSITIVE means “On – If the result is POSITIVE means
Schedule” “Underrun”
– If the result is NEGATIVE means – If the result is NEGATIVE means
“Behind Schedule” “Overrun”
Schedule Variance (SV)% = SV/PV Cost Variance (CV)% = CV/EV
Tells you what percentage schedule Tells you what percentage cost varies
varies from what has been planned to from what has been earned to date.
date
Schedule Performance Index (SPI) = Cost Performance Index (CPI) = EV/AC
EV/PV
– If result is less than 1.0, cost is
– If result is less than 1.0, project is GREATER than budgeted
“BEHIND” schedule – If the result greater than 1.0, cost is
– If the result greater than 1.0, LESS than budgeted
project is “AHEAD of schedule
– The Estimate at Completion (EAC) is the actual cost to date plus an objective
estimate of costs for remaining authorized work.
– The objective in preparing an EAC is to provide an accurate projection of cost
at the completion of the project.
“The Estimate to Complete (ETC) is the cost of completing the authorized remaining work”
*There will be more formulas to calculate EAC later in the next pages.
For more understanding, let’s use previous formula on the next project
Actuals ETC EAC
ID Activity Mar Apr May Jun Jul Total
2.1 WBS Electrical
2.1.1 Install Raceways $1,100 $1,100
2.1.2 Pulling Cables $2,300 $2,300
Install Wiring
$1,200 $700 $1,900
2.1.3 Devices
2.1.4 Install Fixtures $2,100 $2,100
2.2 WBS HVAC
2.2.1 Fabricate Duct $1,100 $1,100
2.2.2 Install Duct $400 $400
2.2.3 Smoke/light test $100 $100
2.2.4 Insulation works $200 $600 $800
2.2.5 Cladding Works $500 $500
2.3 WBS Firefighting
2.3.1 Install Pipes $3,100 $3,100
2.3.2 Network HT $500 $500
2.3.3 Install Sprinklers $1,600 $1,600
2.4 WBS Drainage
2.4.1 Install UPVC Pipes $800 $800
2.4.2 filling test $100 $100
2.4.3 Install Specialties $500 $800 $1,300
Total $8,900 $2,500 $2,100 $500 $3,700 $17,700
Now let’s look at the same example with some additional changes to the ETC
“As the project manager you are reviewing your ETC and you get a call from the Cladding
Contractor. He tells you that the original budget for the cladding ($500) is no longer correct
because the price of the cladding increased. The project manager asks for a new estimate
and the cladding contractor tells him that it will now cost $700”
“Additionally, your site engineers tell you that the current ETCs for insulation are good, thus
the current cost underrun ($100) and the cost overrun ($200) for installing wiring devices
that will be realized at the completion of each activity
With this information, let’s take a look at the new EAC.
Actuals ETC EAC
ID Activity Mar Apr May Jun Jul Total
2.1 WBS Electrical
2.1.1 Install Raceways $1,100 $1,100
2.1.2 Pulling Cables $2,300 $2,300
2.1.3 Install Wiring Devices $1,200 $900 $2,100
2.1.4 Install Fixtures $2,100 $2,100
2.2 WBS HVAC
2.2.1 Fabricate Duct $1,100 $1,100
2.2.2 Install Duct $400 $400
2.2.3 Smoke/light test $100 $100
2.2.4 Insulation works $200 $500 $700
2.2.5 Cladding Works $700 $700
2.3 WBS Firefighting
2.3.1 Install Pipes $3,100 $3,100
2.3.2 Network HT $500 $500
2.3.3 Install Sprinklers $1,600 $1,600
2.4 WBS Drainage
2.4.1 Install UPVC Pipes $800 $800
2.4.2 filling test $100 $100
2.4.3 Install Specialties $500 $800 $1,300
Now let's determine the VAC for our previous project as follows:
VAC = BAC – EAC
VAC = $17,700 - $18,000 = -$300
In other words, the project is now forecasted to overrun by $300.
This formula is used when the original estimation is met without any deviation. It
signifies that your project is going well.
You are maintaining the CPI and SPI as 1, and you should continue the project in
the same way. It is always good for a project manager if he or she is maintaining
the CPI and SPI as 1 or even more than 1.
This formula is used when the current deviation with the original estimation is
thought to be different in the future.
It is generally AC plus the remaining value of the work to perform.
This formula is used to calculate actual to date plus the remaining budget changed
based on the performance.
It is used when we believe the current ratio is typical as planned. In other words,
we have to meet the schedule earlier than originally determined, and we calculate
the EAC accordingly to meet that schedule.
12. Summery
Schedule Variance
Earned Value (EV) - Planned Value (PV)
(SV)
Schedule
Performance Index Earned Value (EV) / Planned Value (PV)
(SPI)
Cost Performance
Earned Value (EV) / Actual Cost (AC)
Index (CPI)
Estimate to
Estimate at completion (EAC) - Actual Cost (AC)
Complete (ETC)
Earned Value
Mgmnt (EVM) AC + ETC
BAC / CPI
Estimate at
Completion (EAC)
AC + (BAC - EV)
As a final conclusion after all, you have the ability now to relate all of the following
questions and also the ability to answer them back.
Question Objectively Calculation
How much work should be done? Planned Value (PV)
How much work was done? Earned Value (EV)
How much did the work cost? Actual Cost (AC)
What is the total job budgeted to cost? Budget at Completion (BAC)
What do we expect the total job to cost? Estimate at Completion (EAC)
References
Project Management Institute. (2004) A Guide to the Project Management Body of Knowledge
(PMBOK® Guide). (Third ed.) Newtown Square, PA: Project Management Institute
Project Management Institute. (2005) Practice standard for earned value management (PMI
Global Standard) (2005 ed.) Newtown Square, PA: Project Management Institute
Government Electronics and Information Association. (2002) Earned value management
systems Approved: May 19, 1998. Reaffirmed: August 28, 2002. ANSI/EIA-748-A-1998
United States Department of Energy (2005) Earned value management application guide,
version 1.6. January 1, 2005. Office of Engineering and Construction Management.
© 2006, Chance Reichel, PMP
originally published as a part of 2006 PMI Global Congress Proceedings – Seattle
Washington
About Us
PHONE +201004974771
Cairo - Egypt