HOW TO CREATE

3 MONTHS
LOOK AHEAD PLAN
IN PRIMAVERA P6
Under Activities window, click on the
filter option
Create a new filter
by clicking +New
1
Name the filter as 3 months Lookahead

3
Enter High value as
Datadate+3months that filters
activities for next 3 months
Select Start - within the 2 (3 month lookahead)
range option and PS-
Earliest Project start option
from respective dropdowns
Click Add 4
Click ok 6

Select Activity status


– is not equal to –
completed
from respective 5
dropdowns
Select
and
click
Apply
Now activities planned for next 3 months shall
only be filtered and appear.