Weekly Progress Report 06
Contents
1. Executive Summary
2. HSE Update
• Safety Manhour
• Equipment Report
• Update Initial Work (Temporer)
3. Site Progress
• Weather Report
• Manpower list
• Depth of Indicator Pile
• Site Progress Photos
• Overall Progress
• Plan Works
4. Documentation
5. RFA Drawing
6. RFA Material
• Prevention Covid – 19
• MEP Section
1. Contract Agreement
• Contract signed
• Start 2 November 2020 – Finish 30 June 2021 (8 Month)
• Production Building : Finish 30 April 2021 (6 Month)
• Running time : 42 Days (13 December 2020)
• Remaining time : 177 Days
2. Work Planning on-Site :
• Main Piling : 14 – 20 December 2020
No. Equipment Name QTY Specification Date of Testing Expiry of Certificate Certificate No. STATUS
6 1 2 3 5
Legend :
1.Site Manager Room & GA Room (2 Level)
2. ISA Office & Engineering Room (2 Level)
3.Meeting Room
4.Security
5.Wearhouse & Project Manager Room (2 Level)
6.Toilet
7.Rebar stockyard
No. Day Date Work Hours 00.00 01.00 02.00 03.00 04.00 05.00 06.00 07.00 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 18.00 19.00 20.00 21.00 22.00 23.00
Sunny
Cloudy
Rainy
Thunderstorm
Depth (m) IP.1 IP.2 IP.3 IP.4 IP.5 IP.6 IP.7 IP.8 IP.9 IP.10 IP.11 IP.12 IP.13 IP.14
0.000
-0.500
-1.000
-2.00
-3.00
-4.00
-5.00
-6.000
-7.000
-8.000
-9.000
-10.00
-11.00 -10.500
-12.00 -12.000 -11.530 -11.980 -11.700 -11.540 -11.920
-13.00 13.000 -12.870 -12.700
-14.00
-15.00 -14.560 -14.610
-16.00 -15.850 -15.380
IP-3
IP-1
IP-2
Depth > 12m
Mar 12, 2021
Extension Building PT. Clama Indonesia
10
Site Progress Overall Progress
IP-14 IP-13
IP-12
IP-10
IP-11
IP-9
IP-7 IP-8
IP-6
IP-4 IP-5
IP-3
IP-1
IP-2
Depth > 12m
Mar 12, 2021
Extension Building PT. Clama Indonesia
11
Site Progress Site Progress Photo (Prepation for 1st Piling)
IP-3
Welding plate
Disinfectan
Mar 12, 2021
Extension Building PT. Clama Indonesia
21
Documentation RFA – Material - MEP
REVISION STATUS
NO DOCUMENT ID TITLE BRAND SENT TO STATUS REVISION SUBMIT REPLY DATE NOTE
STATUS DATE TARGET ACTUAL
1 001/AM/R0/PI-CI-MEP/XI/2020 STP - 5M3 BIO TECH ISA B R0 26/11/2020 01/12/2020 05/12/2020
2 004/AM/R0/PI-CI-MEP/XI/2020 COMPRESSED AIR PIPE AIR NET ISA R0 26/11/2020 01/12/2020
3 005/AM/R0/PI-CI-MEP/XI/2020 PVC AW - CLEAN WATER RUCIKA ISA B R0 26/11/2020 01/12/2020 05/12/2020
4 002/AM/R0/PI-CI-MEP/XI/2020 STP - 1M3 BIO TECH ISA R0 30/11/2020 07/12/2020
5 008A/AM/R0/PI-CI-MEP/XII/2020 NYY 2 X (4 X 1C X 185mm) + NYA 95mm KABEL METAL ISA R0 04/12/2020 11/12/2020
6 008B/AM/R0/PI-CI-MEP/XII/2020 NYY 4 x 120mm + NYA 50mm KABEL METAL ISA R0 04/12/2020 11/12/2020
7 008C/AM/R0/PI-CI-MEP/XII/2020 NYY 4 x 16mm + NYA16 mm KABEL METAL ISA R0 04/12/2020 11/12/2020
8 008D/AM/R0/PI-CI-MEP/XII/2020 NYY 4 x 6mm + NYA 6mm KABEL METAL ISA R0 04/12/2020 11/12/2020
9 008E/AM/R0/PI-CI-MEP/XII/2020 NYFGBY 4 x 6mm + NYA 6mm KABEL METAL ISA R0 04/12/2020 11/12/2020
10 008F/AM/R0/PI-CI-MEP/XII/2020 NYFGBY 5 x 4mm KABEL METAL ISA R0 04/12/2020 11/12/2020
NO DOCUMENT ID SUBJECT SENT TO STATUS SUBMIT REPLY DATE NOTE
DATE TARGET ACTUAL
1 001/RFI-MEP/PI-CI/XII/2020 VRF AC CAPACITY ISA SENT 10/12/2020 18/12/2020
3)Weight 345 Kg