WEEKLY REPORT -06 (07– 13 December 2020)

Vetted by Prepared by

Marno Anisa
Project Manager Site Engineer
Mar 12, 2021
Weekly Progress Report 06
Contents

1. Executive Summary
2. HSE Update
• Safety Manhour
• Equipment Report
• Update Initial Work (Temporer)
3. Site Progress
• Weather Report
• Manpower list
• Depth of Indicator Pile
• Site Progress Photos
• Overall Progress
• Plan Works
4. Documentation
5. RFA Drawing
6. RFA Material
• Prevention Covid – 19
• MEP Section

Mar 12, 2021


Extension Building PT. Clama Indonesia
2
Executive Summary

1. Contract Agreement
• Contract signed
• Start 2 November 2020 – Finish 30 June 2021 (8 Month)
• Production Building : Finish 30 April 2021 (6 Month)
• Running time : 42 Days (13 December 2020)
• Remaining time : 177 Days
2. Work Planning on-Site :
• Main Piling : 14 – 20 December 2020

Mar 12, 2021


Extension Building PT. Clama Indonesia
3
HSE Update Safety Manhour

No. ITEM Report

1 Accident / Incident / Near Miss 0

2 Cumulative no of Workplaced Accident 0


Reported
3 Cumulative no of Man-Days Lost to 0
Workplace Acciddents
4 Cummulative no of Man-Hours Worked 0

5 Accident Frequency Rate 0

6 Accident Severity Rate 0

Mar 12, 2021


Extension Building PT. Clama Indonesia
4
HSE Update Equipment Report

No. Equipment Name QTY Specification Date of Testing Expiry of Certificate Certificate No. STATUS

1 Prisma Polygon 1 Sokkia NA NA NA Good Condition

Mar 12, 2021


Extension Building PT. Clama Indonesia
5
HSE Update Initial Work (Temporary)

6 1 2 3 5

Legend :
1.Site Manager Room & GA Room (2 Level)
2. ISA Office & Engineering Room (2 Level)
3.Meeting Room
4.Security
5.Wearhouse & Project Manager Room (2 Level)
6.Toilet
7.Rebar stockyard

Mar 12, 2021


Extension Building PT. Clama Indonesia
6
Site Progress Weather Report

No. Day Date Work Hours 00.00 01.00 02.00 03.00 04.00 05.00 06.00 07.00 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 18.00 19.00 20.00 21.00 22.00 23.00

1 Monday 07/12/20 08.00 - 22.00


2 Tuesday 08/12/20 08.00 - 22.00
3 Wednesday 09/12/20 08.00 - 22.00
4 Thursday 10/12/20 08.00 - 22.00
5 Friday 11/12/20 08.00 - 22.00
6 Saturday 12/12/20 08.00 - 22.00
7 Sunday 13/12/20 08.00 - 22.00

    Sunny

    Cloudy

    Rainy

    Thunderstorm

Mar 12, 2021


Extension Building PT. Clama Indonesia
7
Site Progress Manpower List

No. Day Date Labour Outsourcing Operator Subcontractor

1 Monday 07 December 2020 3 0 3 4


2 Tuesday 08 December 2020 3 0 3 4
3 Wednesday 09 December 2020 3 0 3 4
4 Thursday 10 December 2020 3 0 3 4
5 Friday 11 December 2020 3 0 3 4
6 Saturday 12 December 2020 3 0 3 4
7 Sunday 13 December 2020 3 0 3 4

Mar 12, 2021


Extension Building PT. Clama Indonesia
8
Site Progres Depth of Indicator Pile

Depth (m) IP.1 IP.2 IP.3 IP.4 IP.5 IP.6 IP.7 IP.8 IP.9 IP.10 IP.11 IP.12 IP.13 IP.14

0.000
-0.500
-1.000
-2.00
-3.00
-4.00
-5.00
-6.000
-7.000
-8.000
-9.000
-10.00
-11.00 -10.500
-12.00 -12.000 -11.530 -11.980 -11.700 -11.540 -11.920
-13.00 13.000 -12.870 -12.700
-14.00
-15.00 -14.560 -14.610
-16.00 -15.850 -15.380

Mar 12, 2021


Extension Building PT. Clama Indonesia
9
Site Progress Depth of Indicator Pile

IP-14 IP-13 No Depth Pressure Force


QTY of
Dolly
pile
Indicator (m) ( Mpa ) ( ton ) (m)
(m)
IP-12 1 13 17,28 88 6+6 1
2 14.56 17,28 88 6+6 2,56
IP-10 3 14,61 17,28 88 6+6 2,61
IP-11 4 15,85 17,28 88 6+6 3,85
5 15,38 17,28 88 6+6 3,38
6 12 17,28 88 6+6 0
IP-9 7 12,87 17,28 88 6+6 0,87
8 10,5 17,28 88 6+6 0
IP-7 IP-8 9 12,70 17,28 88 6+6 0,7
10 11,53 17,28 88 6+6 0
11 11,98 17,28 88 6+6 0
IP-6 12 11,70 17,28 88 6+6 0
13 11,54 17,28 88 6+6 0
14 11,92 18,07 92 6+6 0
IP-4 IP-5

IP-3
IP-1
IP-2
Depth > 12m
Mar 12, 2021
Extension Building PT. Clama Indonesia
10
Site Progress Overall Progress

IP-14 IP-13

IP-12

IP-10
IP-11

IP-9

IP-7 IP-8

IP-6

IP-4 IP-5

IP-3
IP-1
IP-2
Depth > 12m
Mar 12, 2021
Extension Building PT. Clama Indonesia
11
Site Progress Site Progress Photo (Prepation for 1st Piling)

Preperation for indicator piling

1st piling indicator


Mar 12, 2021
Extention Building PT. Clama Indonesia
12
Site Progress Site Progress Photo (Welding & Paint protection)

Welding plate for piling indicator

Paint protection for joint piling


Mar 12, 2021
Extention Building PT. Clama Indonesia
13
Site Progress Site Progress Photo (Checked existing roof)

Checked existing roof

Checked existing roof

Mar 12, 2021


Extention Building PT. Clama Indonesia
14
Site Progress Site Progress Photo (Indicator piling IP-3)

Piling for IP-3

IP-3

Welding plate

Mar 12, 2021


Extention Building PT. Clama Indonesia
15
Site Progress Site Progress Photo (Material piling on site)

Material piling on site by Optima Pondasi

Mar 12, 2021


Extention Building PT. Clama Indonesia
16
Site Progress Site Progress Photo

IP-13 IP-10 IP-8 IP-5 IP-1


IP-6

IP-12 IP-9 IP-3

IP-14 IP-11 IP-7 IP-4


IP-2
Note :
Taken on
11/12/2020
Mar 12, 2021
Extension Building PT. Clama Indonesia
17
Site Progress Plan Works

WEEK 06 : 07 - 12 De c e mber 2020


LAS T WEEK NEXT WEEK
07 - 12 December 2020 13 - 20 December 2020
NO ITEM NOTE
7 8 9 10 11 12 13 14 15 16 17 18 19 20
M T W T F S S M T W T F S S
1 Indicator P ile
2 Ma terial on s ite for main pile
3 Acces s temporery
4 P repation HS P D-240 T
5 Rebar fabrication for pile cap
6 P iling HS P D-240 T
7 P iling HS P D-120 T
8
9
10
11

Mar 12, 2021


Extension Building PT. Clama Indonesia
18
Documentation RFA - Drawing
REVISION STATUS
No. CODE TITLE SENT TO STATUS Revise Submit Replay Date NOTE
status Date Target Actual
1 PC/PI-CI/001 Pilecap & Tie Beam Layout PI C R0 10-Des-20 15-Des-20
2 PC/PI-CI/002 Pilecap & Tie Beam Layout partial 1 PI B R0 10-Des-20 15-Des-20
3 PC/PI-CI/003 Pilecap & Tie Beam Layout partial 2 PI B R0 10-Des-20 15-Des-20
4 PC/PI-CI/004 Table Tie Beam PI A R0 10-Des-20
5 PC/PI-CI/005 Details & Section Tie Beam PI C R0 10-Des-20 15-Des-20
6 PC/PI-CI/006 Details & Section Tie Beam #1 PI B R0 10-Des-20 15-Des-20
7 PC/PI-CI/007 Details & Section Tie Beam #2 PI C R0 10-Des-20 15-Des-20
8 PC/PI-CI/008 Details & Section Tie Beam #3 PI B R0 10-Des-20 15-Des-20
9 PC/PI-CI/009 Details & Section Tie Beam #4 PI A R0 10-Des-20
10 PC/PI-CI/010 Details & Section Tie Beam #5 PI A R0 10-Des-20
11 PC/PI-CI/011 Details & Section Tie Beam #6 PI A R0 10-Des-20
12 PC/PI-CI/012 Details & Section Tie Beam #7 PI A R0 10-Des-20
13 FP/PI-CI/001 Floor Plan Layout PI A R0 10-Des-20
14 FP/PI-CI/002 Floor Plan Layout Partial 01 PI B R0 10-Des-20 18-Des-20
15 FP/PI-CI/003 Floor Plan Layout Partial 02 PI B R0 10-Des-20 18-Des-20
16 FP/PI-CI/004 Column Pedestal Layout PI A R0 10-Des-20
17 FP/PI-CI/005 Details & Sections #1 Floor Plan PI B R0 10-Des-20 18-Des-20
18 FP/PI-CI/006 Details & Sections #2 Floor Plan PI B R0 10-Des-20 18-Des-20
19 FP/PI-CI/007 Details & Sections #3 Floor Plan PI B R0 10-Des-20 18-Des-20
20 FP/PI-CI/008 Details & Sections #4 Floor Plan PI B R0 10-Des-20 18-Des-20
21 ED-01 Column Anchor & Base Plate Plan ISA R1 08-Des-20 15-Des-20
22 ED-01A Column Anchor & Base Plate Detail ISA R1 08-Des-20 15-Des-20
23 ED-01B Anchor & Base Plate Detail ISA R1 08-Des-20 15-Des-20
24 ED-02 Beam Layout EL. ± 4.220 ; ± 8.050 ISA R1 08-Des-20 15-Des-20
25 ED-03 Roof Framing Plan ISA R1 08-Des-20 15-Des-20
26 ED-04 Roof Purlin Plan ISA R1 08-Des-20 15-Des-20
27 ED-05 Portal Frame ISA R1 08-Des-20 15-Des-20
28 ED-06 Portal Frame (2) ISA R1 08-Des-20 15-Des-20
29 ED-07 Portal Frame (3) ISA R1 08-Des-20 15-Des-20
30 ED-08 Portal Frame (4) ISA R1 08-Des-20 15-Des-20
31 ED-09 Portal Frame (4) ISA R1 08-Des-20 15-Des-20
32 ED-10A Built up Profile ISA R1 08-Des-20 15-Des-20
33 ED-11 Detail Connections (1) ISA R1 08-Des-20 15-Des-20
34 ED-12 Detail Connections (2) ISA R1 08-Des-20 15-Des-20
35 ED-13 Detail Connections (3) ISA R1 08-Des-20 15-Des-20
36 ED-14 Detail Connections (4) ISA R1 08-Des-20 15-Des-20
37 ED-15 Detail Connections (5) ISA R1 08-Des-20 15-Des-20
38 ED-16 Detail Connections (6) ISA R1 08-Des-20 15-Des-20
39 ED-17 Section & Detail Canopy ISA R1 08-Des-20 15-Des-20

Mar 12, 2021


Extension Building PT. Clama Indonesia
19
Documentation RFA - Material

TENDER DOCUMENT APPROVAL PROCURMENT


No. MATERIAL DATE RESULT Delivery NOTE
MERK SPECIFICATION MERK SPECIFICATION PO On Site
Submit Approved A AC R Time
A. STRUCTURE
1 Piling Jaya Beton Mini pile 250x250 , Optima Mini pile 250x250 , 10-Des-20 11-Des-20 V 10-Des-20 11-Des-20 11-Des-20
Duasia Pu 88 ton Pu 90 ton
Saeti Concretindo K-500 K-500
Dayacipta L = 12 m (6+6)m L = 12 m (6+6)m
Wika Precast connection plat 6mm connection plat 6mm
Adhimix Precast double plat
PP Urban

Mar 12, 2021


Extension Building PT. Clama Indonesia
20
Prevention Covid - 19

Screening Body Washtafel


Temperature

Disinfectan
Mar 12, 2021
Extension Building PT. Clama Indonesia
21
Documentation RFA – Material - MEP
REVISION STATUS
NO DOCUMENT ID TITLE BRAND SENT TO STATUS REVISION SUBMIT REPLY DATE NOTE
STATUS DATE TARGET ACTUAL
                     
1 001/AM/R0/PI-CI-MEP/XI/2020 STP - 5M3 BIO TECH ISA B R0 26/11/2020 01/12/2020 05/12/2020  
2 004/AM/R0/PI-CI-MEP/XI/2020 COMPRESSED AIR PIPE AIR NET ISA   R0 26/11/2020 01/12/2020    
3 005/AM/R0/PI-CI-MEP/XI/2020 PVC AW - CLEAN WATER RUCIKA ISA B R0 26/11/2020 01/12/2020 05/12/2020  
4 002/AM/R0/PI-CI-MEP/XI/2020 STP - 1M3 BIO TECH ISA   R0 30/11/2020 07/12/2020    
5 008A/AM/R0/PI-CI-MEP/XII/2020 NYY 2 X (4 X 1C X 185mm) + NYA 95mm KABEL METAL ISA   R0 04/12/2020 11/12/2020    
6 008B/AM/R0/PI-CI-MEP/XII/2020 NYY 4 x 120mm + NYA 50mm KABEL METAL ISA   R0 04/12/2020 11/12/2020    
7 008C/AM/R0/PI-CI-MEP/XII/2020 NYY 4 x 16mm + NYA16 mm KABEL METAL ISA   R0 04/12/2020 11/12/2020    

8 008D/AM/R0/PI-CI-MEP/XII/2020 NYY 4 x 6mm + NYA 6mm KABEL METAL ISA   R0 04/12/2020 11/12/2020    

9 008E/AM/R0/PI-CI-MEP/XII/2020 NYFGBY 4 x 6mm + NYA 6mm KABEL METAL ISA   R0 04/12/2020 11/12/2020    
10 008F/AM/R0/PI-CI-MEP/XII/2020 NYFGBY 5 x 4mm KABEL METAL ISA   R0 04/12/2020 11/12/2020    

11 008G/AM/R0/PI-CI-MEP/XII/2020 NYFGBY 3 x 4mm KABEL METAL ISA   R0 04/12/2020 11/12/2020    

12 009A/AM/R0/PI-CI-MEP/XII/2020 NYM 3 X 2,5mm KABEL METAL ISA   R0 04/12/2020 11/12/2020    


13 009B/AM/R0/PI-CI-MEP/XII/2020 NYY 4 X 2,5mm + NYA 2,5mm KABEL METAL ISA   R0 04/12/2020 11/12/2020    
14 009C/AM/R0/PI-CI-MEP/XII/2020 NYY 4 x 4mm + NYA 4mm KABEL METAL ISA   R0 04/12/2020 11/12/2020    
HIGH IMPACT PVC CONDUIT &
15 011/AM/R0/PI-CI-MEP/XII/2020 LEGRAND ISA   R0 04/12/2020 11/12/2020    
ACCESSORIES
16 015/AM/R0/PI-CI-MEP/XII/2020 PVC AW - SEWAGE AND WASTE WATER RUCIKA ISA   R0 14/12/2020 21/12/2020    
17 016/AM/R0/PI-CI-MEP/XII/2020 PVC D - VENT AND DRAIN PIPE RUCIKA ISA   R0 14/12/2020 21/12/2020    
                     

A Approved - No adviser comments Proceed.


Approved - With comments, Revise and Resubmit. Incorporate and
B
Proceed.
C Not Approved - Major comment, Revise and Resubmit. Do not Proceed.

Mar 12, 2021


Extension Building PT. Clama Indonesia
22
Documentation RFI MONITORING - MEP

 
NO DOCUMENT ID SUBJECT SENT TO STATUS SUBMIT REPLY DATE NOTE
DATE TARGET ACTUAL
                 
1 001/RFI-MEP/PI-CI/XII/2020 VRF AC CAPACITY ISA SENT 10/12/2020 18/12/2020    
                 
                 
                 
                 
                 
                 
                 
                 

Mar 12, 2021


Extension Building PT. Clama Indonesia
23
MEP SECTION – THIS WEEK SCHEDULE

1)Continue The Approval Material Submission

2)Preparation For New STP Working

Mar 12, 2021


Extension Building PT. Clama Indonesia
24
MEP SECTION – ROOF FAN

Mar 12, 2021


Extension Building PT. Clama Indonesia
25
MEP SECTION – ROOF FAN

1)Need Additional Ducting

2)Need Rain Hood On The Roof

3)Weight 345 Kg

Mar 12, 2021


Extension Building PT. Clama Indonesia
26
Thank you

Mar 12, 2021


Extension Building PT. Clama Indonesia