You are on page 1of 13

Construction of Civil & Steel Structural Works for 5th

Stream Alumina Plant at Damanjodi, Odisha.

Reference no: -
Thyssenkrupp UDEH NALCO/tkIS/ZT-BG/Mech-
India Private Ltd. JOB SAFETY ANALYSIS
Page 1|
Page

Job area is considered: Bauxite Grinding area. Establishment/Project: Dated:-


Project No: 1.0MTPA Alumina Refinery Revesion-0.0

Contractor: Zetwerk MBPL EPCM:tkUIPL Client: NALCO


Mr. Narayn Maiti (RCM) Mr. J K Pradhan (RCM) Mr. Sanjay Panda (DGM)

Person participating in Mr.Ashwin K. Dalai. Mr. K.N Suresh Mr. P.K.Dash (G.M-HSE)
Job Safety Analysis. (Manager-Exe) Mr. S.R Biswal

Mr. Dillip K. Panigrahy Mr. Legin Jose (HSE- Manager) Mr. Rakesh Kumar Behera
(Manager-HSE) Mr. Surya Kanta Patra (HSE) (D.M HSE)

JOB DESCRIPTION: - Height work (Erection/dismantling of scaffolding use of ladder) JSA & Working in night.

Requirement of Working Permit Requirement of adding Personal Protection Requirement of adding special equipment or
(Check the relevant box) Equipment. tool
(Additional list)
Restricted space  1. Safety Shoe 6. Rubber hand gloves 1.Saw cutting machine 06.Tool kit
Heating job  2. Safety Helmet 7. Goggles 2.Hammer 07.Light
Digging 3. Nose Mask 8. Ear plug 3.Safety Harness
Isolation / Energization 4. Reflective Jacket 4. Lifeline
Other job (Height)  5. Cotton/Rubber Hand Gloves 5.Ladder

JSA considering procedure Yes No Comment

Classification: Public
Construction of Civil & Steel Structural Works for 5th
Stream Alumina Plant at Damanjodi, Odisha.

Reference no: -
Thyssenkrupp UDEH NALCO/tkIS/ZT-BG/Mech-
India Private Ltd. JOB SAFETY ANALYSIS
Page 2|
Page
Is JSA establishment participated by job implementing group? 

Is JSA considered by Job implementing group before carrying out the 


job?
Is JSA sheet used/ consulted in work implementation?

Is the job carried out step by step? 
Do you propose to improve JSA sheet (give in detail) 
Is detail of any trouble showing 

ACTIVITIES HAZARD/ DANGER CONTROL MEASURE RESPONSIBLE


PERSON
Separate the job into the Describe all hazards identified Describe fully all equipment, facility, and/or procedure controls applicable
main tasks and record for each task based on for each hazard.
them in sequence. observations and experience.

 Experienced and License person should drive the vehicle. .

 Healthy and fit condition vehicles should be used for the job.

 Pre job description (PJD) to be done before starting the job.


 Physical injury
 Material should be loaded securely and fasten well.
 Fall of material from vehicle
Mobilization of  Ensure no overload or is allowed while transporting with vehicle.
 Slip and Trip of
Scaffolding material
 Operator should obey all traffic rule while driving 20KMPH/hr.
person/vehicle.
and Loading &
 Vehicle Topple  Banksman must be available with vehicle all time to giving surrounding
Unloading, shifting and
 Collision of Vehicle /Person clearance.
transportation
 Ergonomically hazard.  While reverse, forward and turning blow horn in vehicle.

Classification: Public
Construction of Civil & Steel Structural Works for 5th
Stream Alumina Plant at Damanjodi, Odisha.

Reference no: -
Thyssenkrupp UDEH NALCO/tkIS/ZT-BG/Mech-
India Private Ltd. JOB SAFETY ANALYSIS
Page 3|
Page
 Material should be stacked in manner in vehicle and site.

 Ensure the work area is neat and clean.

 Ensure the vehicle is parked or station in a safe place not on slope or


any traffic crowd area.
 While loading, unloading, and shifting keep barricading at work area.

 Follow proper material handling procedure during handling of


material.
 Ensure weight is on your thigh not on your back.

 While handling of material keep straight your body position.

 If it is not possible to handle manually, mechanical lifting devices shall


be used for handling of material.
 Requisite PPEs should provide to all workmen

 Work permits to be obtained.

 Physical inspect work area, prior to start work.

 Isolate all charged lines around work area. Which are fouling on the job.

 Follow good housekeeping practice.


Base preparation for  Slip / Trip fall of person  Ensure projected rods/debris to be removed. No manhole and
scaffolding erection.  Damage underground projected bars should be in work area.
utility.  Keep work area clean &neat, free from rubbish& debris.

Classification: Public
Construction of Civil & Steel Structural Works for 5th
Stream Alumina Plant at Damanjodi, Odisha.

Reference no: -
Thyssenkrupp UDEH NALCO/tkIS/ZT-BG/Mech-
India Private Ltd. JOB SAFETY ANALYSIS
Page 4|
Page
 Cut /bruise injury.  Be careful on slopes or wet/ muddy areas, well compacted base ground

 Earth worm of insect biting should ensure at scaffolding erection area.

 Ergonomic injury  Water logging must be avoided.


 Appropriate warning signs to be displayed.
 Unauthorized access to work area to be prohibited & hard barricade.
around the work area.
 Proper work supervision should be provided to the work area.
 PCI to be done at work area to avoid any earth worm/insect spreading.
 Follow good work posture during the manual material handling work.

 Job requisite PPEs should provide to all workmen.

 Obtain the Work permit for the job. .

 Competent and skilled workmen should engage in job.

 Ensure engaged workmen have vertigo qualified, competent, and fit for
the job.
 Scaffolding pipe and ladder should be used as per IS Standard. (3696-
 Physical injury. P1),4014 and 2750.

 Personnel fall from height.  Scaffold should erect as per job design (four times from the workload)
Erection and  Material falls from height.  Scaffolding Tag must be tied with scaffold after inspected by competent
dismantling of scaffold.  Slip/Trip hazards person before taking in use.

Classification: Public
Construction of Civil & Steel Structural Works for 5th
Stream Alumina Plant at Damanjodi, Odisha.

Reference no: -
Thyssenkrupp UDEH NALCO/tkIS/ZT-BG/Mech-
India Private Ltd. JOB SAFETY ANALYSIS
Page 5|
Page
 Scaffolding collapse.  The ladder should be fixed for safe access. 1:4 ratio or 70 degrees.

 Electrocution hazard  A 12 mm thickness Lifeline should be installed for FBH anchoring.

 A proper platform should be provided for working at height. Ensure


top rail, mid rail, toe guard and other required components as per IS
code.
 If required Safety net should be provided under working platform.

 The spanner should be tie up with rope or harness.

 Loose material should not be kept on the working platform.

 Scaffolding basement should be properly compaction.

 Erection of Scaffolding should be done aided by water level or sprite


level.
 Sign board should be provided at workplace.

 Material should be stack in safe manner.

 Housekeeping to be done before and after the job.

 Proper lighting should ensure at work area.

 During adverse weather avoid to carrying out work (Lightening,


thunderstorm, wind, rain and nigh etc.)
 Job to be done under supervision of engineer/Supervisor.

 Barricade shall be provided under scaffold erection or dismantling

Classification: Public
Construction of Civil & Steel Structural Works for 5th
Stream Alumina Plant at Damanjodi, Odisha.

Reference no: -
Thyssenkrupp UDEH NALCO/tkIS/ZT-BG/Mech-
India Private Ltd. JOB SAFETY ANALYSIS
Page 6|
Page
area.
 Ensure no electrical line is passed or attached with scaffold.

 Ensure proper support and landing platform is provided.

 Vibrator, electrical cable, and light fittings should not attach with the
scaffold. It should be separate from the scaffold.
 Don’t throw any material from height during erection and dismantling.

 Ensure no damaged, welded, bend and makeshift pipe is being used for
the job.
 Time to time inspection must ensure of scaffold healthiness by the help
of competent scaffolder.
 For material ascending and descending use rope and rope pulleys of
pulley must be sure.
 Material lifting should be barricaded.

 Ensure standard tools and apparatus is being used in job.

 Provide requisite PPEs to workmen.

 Ladder should place in right angel (70 degree) or 1:4 ratio. .


 Ensure ladder is placed in correct place not over the approach, slanting
area or uneven surface.
 Aluminum ladder should be used and tie it securely. Inspect the ladder
Classification: Public
Construction of Civil & Steel Structural Works for 5th
Stream Alumina Plant at Damanjodi, Odisha.

Reference no: -
Thyssenkrupp UDEH NALCO/tkIS/ZT-BG/Mech-
India Private Ltd. JOB SAFETY ANALYSIS
Page 7|
Page
weekly basis.
 Trained person should perform the job.
 Fall Person / Material  Barricade the work area, display signage at the work area.
Working at height by  Slip/Trip Hazard  During the work supervisor should be at site for supervision.
Scaffolding/ladder.  Electrocution  Pre job description (PJD) should be done before starting the job.
 Collapse of scaffolding  Proper lighting should be provided at workplace.
 Personal injury  FBH should be provided with shock absorber if your job height is 5 mtrs
 Ergonomically injury or above.
 Follow all height work procedure during working at height.
 Ensure ladder only for ascending and descending not for work.
 At a time one person only allowed to up and down.
 Ensure workmen must follow 3-point contact during ascending and
descending.
 While ascending and descending ensure person must face towards ladder
not back.
 Job to be done under supervision of engineer/Supervisor.
 Housekeeping should be done at work area time to time.
 Ensure no electrical line is attached to the ladder.
 Paint should not be done for ladder and scaffold pipe.
 Ensure electrical apparatus like cable, vibrator, light fittings and
electrical board etc. not attached with the working scaffold. It should be in

Classification: Public
Construction of Civil & Steel Structural Works for 5th
Stream Alumina Plant at Damanjodi, Odisha.

Reference no: -
Thyssenkrupp UDEH NALCO/tkIS/ZT-BG/Mech-
India Private Ltd. JOB SAFETY ANALYSIS
Page 8|
Page
separate form the working scaffold.
 Ensure all power connection is given through RCCB/ELCB of 30mA
sensitivity.
 Standard electrical equipment, DB and switchboard should use in job.
 Provide requisite PPE’s to all workmen.
 Work area to be maintained neat and clean.
 Stack material properly.
 Make the access way clear.
 Follow proper material handling procedure while handling of material.
 Ensure no protruding parts are to be left out at site.
 Slip/Trip of person
 Sequence wise work to be done.
 Hand/Body injury
Housekeeping  Ensure no material is thrown from height elevation use rope for lowering
 Ergonomically injury
of material.
 Job to be done under supervision of engineer/Supervisor.
 Don’t dispose nay material on ground directly. Follow manufacturer
instruction/MSDS.
 Provide requisite PPEs to workmen.

Emergency response  The injured person should be given First aid immediately.
 Physical Injuries (Minor,
 First aid box shall be made available with required kits in adequate
Serious, LTI) Fatal etc.
quantity and Certified First Aider available at work location.

Classification: Public
Construction of Civil & Steel Structural Works for 5th
Stream Alumina Plant at Damanjodi, Odisha.

Reference no: -
Thyssenkrupp UDEH NALCO/tkIS/ZT-BG/Mech-
India Private Ltd. JOB SAFETY ANALYSIS
Page 9|
Page
 Emergency vehicle shall be made available for meeting emergency needs.
 All employees shall be explained about the provisions of first aid, assembly
point and contact numbers etc.
 Emergency exit pathway and assembly points need to be imparted to
workmen in our Toolbox talk.
 Mock drill to be done frequently regarding each emergency to awareness
among the workmen.
 Barricade the area to avoid Unauthorized person’s restriction.
 Discharge rod, electrical shock proof gum boot, electric shock proof hand
gloves and height rescue arrangement should made available at work area.
 Ensure emergency contact number display at work area.
 Emergency arrangement tools shall have made available at site to fight any
emergency such as trip pod, rope, rescue crew, first aider, ambulance, and
dispensary items etc.).
 Mandatory PPE must always be worn (Helmet, Safety goggles, Cut
resistant hand gloves, Full sleeves shirt & pant and High ankle safety
shoes). COVID related PPE (Masks, gloves).
Night activity in height  Cut bruise injury.  Ensure proper precautions for sharp edges.
and ground (Rebar  Slip/Trip fall of person  Ensure Protruding rebar has cushions and caps.
steel fabrication,  Collapse of scaffold  Ensure all safety precautions are in place as per job like height as per the
binding, fixing, Slip  Electrocution job procedures. With approach, lifeline, handrail, and scaffold etc.

Classification: Public
Construction of Civil & Steel Structural Works for 5th
Stream Alumina Plant at Damanjodi, Odisha.

Reference no: -
Thyssenkrupp UDEH NALCO/tkIS/ZT-BG/Mech-
India Private Ltd. JOB SAFETY ANALYSIS
Page 10 |
Page
form Shuttering /De-  Ergonomically injury  Toolbox talks shall be conducted for the workmen.
shuttering, Concrete  Eye injury  Ensure all manhole and floor openings have covered well with adequate
 Noise injury generation proper signage.
 Vibration  Ensure used height working platform and scaffold have certified and
 Skin dermatitis injury inspected by competent person with the tag.

 Poor Visibility due to sunset  Ensure all power supply has taken through RCCB/ELCB of 30mA
working hour sensitivity.
 A dedicated licensed electrician should stay available at site during all
 Intoxicating/alcoholic in working hours.
working hour drinks.  Follow good posture of work during work.
 Person working alone.  Ensure no person lifts more than his capacity. Follow BOCW act.
 Fatigue due to continuous  Ensure working crew and staff all should separate. No person should work
work both day and night.
 Dizziness and sleepiness  Clean water is kept available at working areas to clean any spillage.
 Lack of awareness and poor  Ensure use of ear plug/muff in noise prone area.
work supervision  Concrete handling person should use PVC gloves and gum boot and in
 Mosquito, insect biting and addition apron and goggles.
earth worm biting.  Any concrete spillage over a person’s body cleans it immediately.
 Firing or room heating avoid  Obtain proper work permit for the extended working hour (beyond 7 PM).
cool weather. Ensure separate working crew and supervisory team is deployed for night
working hour.

Classification: Public
Construction of Civil & Steel Structural Works for 5th
Stream Alumina Plant at Damanjodi, Odisha.

Reference no: -
Thyssenkrupp UDEH NALCO/tkIS/ZT-BG/Mech-
India Private Ltd. JOB SAFETY ANALYSIS
Page 11 |
Page
 Sufficient nos. Lights shall be fixed in daytime. Ensure all light fittings have
fixed well-mannered with insulation in an independent way.
 Area illumination (100 LUX) and job light lux (250 LUX) must check in
night work hour.
 Ensure Close monitoring/job supervision by supervisor at all the time
working hour. No lone work is allowed.
 The whole workplace and access and egress are illuminated at nighttime.
 Provide signage and barricade to the exposed area.
 High Visibility vest (Reflective Jacket) to be worn.
 Buddy system to be followed.
 All blind spots at workplace to be illuminated.
 Ensure that light fixture installed not at height of eye level of operator to
avoid glare work.
 Breaks to be provided in between shifts.
 Job rotation to be done time-to-time.
 Keep your sleeping pattern regular.
 Ensure employees are taking balanced food and regular meals.
 Ensure lighting in vehicle movement areas.
 Signal man/banks man equipped with lighting blinker for proper
signaling.
 Ensure alcohol test during Toolbox Talks in night working hours.

Classification: Public
Construction of Civil & Steel Structural Works for 5th
Stream Alumina Plant at Damanjodi, Odisha.

Reference no: -
Thyssenkrupp UDEH NALCO/tkIS/ZT-BG/Mech-
India Private Ltd. JOB SAFETY ANALYSIS
Page 12 |
Page
 Intoxicating drinks & drug free workplace shall be maintained.
 Updated emergency contact numbers shall be displayed.
 Dedicated vehicles shall be stationed at workstations.
 Ensure availability of emergency response team members at work area.
 Ensure proper illumination at work area such as store, resting shed and
urinals.
 Ensure no open flame is allowed at the work site.
 PCI is to be sprayed at work area to avoid any mosquito and earth work
spreading.
 Ensure no workmen is allowed to sleep at working site and height.
 No erection is allowed during night working hours.
 Ensure no work is allowed in adverse weather like rain, thunderstorm,
and heavy wind flow.
 Separate toolbox talk should conduct for the workmen.
 Ladies’ workers are not allowed to work at night.
 Hazardous job also not allowed in night.
 The injured person should be given First aid immediately.
 First aid box shall be made available with required kits in adequate
quantity and certified First-Aider available at work location.
 Emergency vehicles should be made available at site to fight any
emergency.

Classification: Public
Construction of Civil & Steel Structural Works for 5th
Stream Alumina Plant at Damanjodi, Odisha.

Reference no: -
Thyssenkrupp UDEH NALCO/tkIS/ZT-BG/Mech-
India Private Ltd. JOB SAFETY ANALYSIS
Page 13 |
Page
 Emergency exit pathway and assembly points need to be imparted to
workmen in our toolbox talk.
 Emergency arrangement tools shall have made available at site to fight any
emergency sch as trip pod, rope, rescue crew, first aider, ambulance, and
dispensary items etc.
 Use of Job specific PPEs

Prepared by Reviewed by Approved by


(Contractor: - Zetwerk.) (tkUIPL-Department Lead/HSE) (tkUIPL -Site/RCM Manager)
Name: Name: Name:

Designation: Designation: Designation:

Signature: Signature: Signature:

Date: Date: Date:

Classification: Public