TOUAT GAZ project

JOB SAFETY ANALYSIS (JSA)


JSA DOC. No: HSE.JSA.019 JSA TEAM MEMBERS

DATE: 09/11/2017 1. Eng.saif ALI . project Manager

REVISION NO: HSE-00 2. Locif Abd elnour ENI engineer

AUTHORISATION: (Team Leader / Coordinator / Supervisor) 3. Ait rahman Tarik


4. Mohamed elkomy . HSE Manager.
Signed :______ _______________________________
Signed : (JSA Team Leader)

JOB LOCATION: (include equipment no.) All over CSSI Site.

JOB DESCRIPTION: Electrical cable,boards,acessories testing


WORK TEAM MEMBERS PERSONAL PROTECTIVE PLANT, EQUIPMENT & ISOLATION, TAGGING, Environmental Controls
EQUIPMENT REQUIREMENTS TOOLS BARRICADES, SIGNS & (Bunding, Waste
LICENSES Disposal, Discharge
Prevention, etc)
NAME (print) Helmet Generator LOTO if required Cssi Will follow the
MSDS instructions
Black Safety Glasses or clear Tower light Caution taps And project
enviromenet procedure
Gloves Hand tools Relevant safety signs
Safety shoes Cad weld Equipment certified
Dust musk if necessary Clear access

1 rev 00
Mandatory PPE
PERMITS
Confined Spaces Work
Excavation Gas
Isolation Hot Work

Others please specify:

JOB SAFETY ANALYSIS (JSA) WORK SHEET


JOB STEP (Activity) HAZARD/Risk Who REQUIRED HAZARD CONTROL FINAL
AT P S R P S R ASSESMENT
RISK
PTW  Major injury (If All 2 2 4  PTW should be issued before work 1 1 1 Acceptable
work start without start.
PTW).
JSA  Personal Injury All 2 2 4  JSA should be conducted prior 1 1 1 Acceptable
work start by area supervisor and
briefed for all the involved persons.
 Area/Construction supervisor
should be on site full time.
 JSA will be changed/ cancelled in
case of work steps/equipment or
people changed.
 Injury to workers All 2 2 4  Required PPE shall be worn at 1 1 1 Acceptable
due to non- all times while working at
availability of PPE. excavation.

 Lack of awareness All 2 2 4  All employees should be given 1 1 1 Acceptable


safety induction and trained for
particular work. Toolbox talk must
be conducted prior to start work.
All works are being done only by
appropriate work permit
2 rev 00
Mandatory PPE
Performing  Failure to keep All 2 2 4  All tools are to be checked before 1 1 1 Acceptable
electrical Testing persons clear of the starts of the work
live test equipment  Supervisor to ensure that defective
 Failure to discharge tools are replaced.
equipment under  PPE shall be worn all the times at
test the work area.
 Electric Shock  Ensure PPE (hard hats, safety
glass, safety shoes and hand
 Fire and explosive
gloves) are approved type.
due to flammable
materials  Good housekeeping.
 Supervisor to ensure area to be
kept out of debris, unnecessary
tools materials and equipment.
 all parts of the body should away
from the energized cable or
(MIGGER)
 Ensure that have proper access
and take care the job site condition
 . Make sure proper PPE always
provided.
 .joint inspection prior to the start
job
 Tools Should be color coded and
approved
 Prohibit of the entrance of the
personnel non involved in the
testing job
 Provide the necessary caution
tape
 Provide the necessary signage
(cable under test)
 Carry out Toolbox talk prior
3 rev 00
Mandatory PPE
starting the test

All 2 2 4  fire watch should available all the 1 1 1 Acceptable


time .
 Fire extinguisher should available.
test should conducted prior to start
the job

Cable testing All 2 2 4 1 1 1 Acceptable


 Striping cable with  Correct cable stripping
instrument should be used
knife Sharp edge  Wear hand protection gloves
 Use proper PPE
 Live cable Only trained authorized competent person
shall do the job
 Electrocution/
fatality

 Live equipment All 3 2 6  Competent supervisor in 2 1 2 Acceptable


 Electrical hazard place, and continuous
 Electrocution or  Correct equipment stripping
Equipment fatality instrument should be used
Operation power tools  Only trained authorized
(MIGGER) competent person shall do the
testing

 - the migger must protected


and working in safe condition

4 rev 00
Mandatory PPE
PREPARED BY: APPROVED BY: REVIEWED BY: APPROVED BY:
SUBCONTRACTOR CONST. SUBCONTRACTOR HSE. CONTRACTOR CONST CONTRACTOR HSE

LOUCIF ABD ELNOUR MOHAMED ELKOMY

5 rev 00