You are on page 1of 9

Madhure Infra Engineering Pvt.

Ltd
Project :-Avalon City Dapodi

Job Safety Analysis

TASK : Concreting (transit mixer,concrete Pump) CONTRACTOR :MIEPL JOB No.:

SUPERVISOR : Devidas Sonkamble, Shivsharan Vhanmhane LOCATION : Work Site Date: 10/09/2022

JOB STEP HAZARDS Control Measure ACTION


Break the job into steps. List the hazard or type of harm List the necessary control measures to be followed to Person who will ensure
Listing work which may be hazardous. identified with each step eliminate the identified hazards this happens

Transit Mixer

Placing of Transit Mixer Vehicle Movement/Hit hazard Documents of the vehicle to be checked and
certified.

Valid licence for the driver. Devidas


Sonkamble
Head light, Tail light, Reverse horn to be
checked. Shivsharan
Vhanmhane
Proper access to be provided by clearing all
unwanted materials or traffic to enter the work
space.

Helper to be provided for controlling the traffic


by signal.

Vehicle to be placed with the help of the helper.

Daily check for the equipment and the check


list to be fulfilled.
Madhure Infra Engineering Pvt.Ltd
Project :-Avalon City Dapodi

Job Safety Analysis

Continuous supervision to be provided.

Concrete Pump

Electrocution Entry to be restricted near the concrete pump


other than the operator and the electrician.

Only authorised operator is allowed to operate.

Proper ear thing to be given and all the


connections to be provided through ELCB only.

Electrician have to use rubber hand gloves


(tested & trade mark) while working/testing on
charged equipments.

Identification boards to be displayed.

All the moving parts to be guarded and no


Moving parts/Trip hazard loose clothing allowed near the
machinery/conveyors.

Un authorised entry to be restricted.


Fire Hazard
CO2 fire extinguisher to be provided.
Dust Hazard
Nose Mask provided for those who engaged on
cement work.
Madhure Infra Engineering Pvt.Ltd
Project :-Avalon City Dapodi

Job Safety Analysis

Eye Hazard
Safety Goggles to be provided for all those who
are engaged on the work.

Cut injury/nail bite


Skilled and trained carpenters will be deployed.
Shuttering & De-shuttering work
PPE’s to be provided for all.(Safety Helmet with
Chin Strip, Safety goggles, Safety shoes,
Reflective vest, cotton hand gloves.)

Scrap will be shifted to the scrap yard after the


completion of work.

Proper House keeping will be provided for


wood scrap, nails etc. to avoid cut injury/ nail
bite.

Daily tool box talks to be followed & recorded.


Vehicle movement/Cut hazard
Documents of the vehicle to be checked and
Concreting work by Transit
certified.
mixer & by manual
Valid licence for the driver.

Head light, Tail light, Reverse horn to be


checked.
Madhure Infra Engineering Pvt.Ltd
Project :-Avalon City Dapodi

Job Safety Analysis

Proper access to be provided by clearing all


unwanted materials or traffic to enter the work
space.

Helper to be provided for controlling the traffic


by signal.

Vehicle to be placed with the help of the helper.

Daily check for the equipment and the check


list to be fulfilled.

Continuous supervision to be provided.

Trip hazard
Shifting of concrete to the pouring area should
be cleared out all unwanted materials and
proper access to be given to avoid trip hazard

Person Injury
Concrete to be poured on concrete tray and
those who are doing the filling work & those
who are standing on the concrete will be
provided with gumboots and rubber hand
gloves other than mandatory PPE’s.
Madhure Infra Engineering Pvt.Ltd
Project :-Avalon City Dapodi

Job Safety Analysis

Fall hazard
Proper scaffolding to be provided with bracing,
mid rail, guard rail & top rail to be provided.

Working at height Secured platform with proper access.

Scaffolding to be certified and safe to use to


board to be displayed.

Scaffolding to be done by a trained gang under


supervision.

Underneath area to be isolated and cleared


from all unwanted materials.

Full body harness with double lanyard to be


provided for those who are working more than
2 mtrs and to be hooked properly at the top.

The ramp or step staging with railing to be


permanently clamped with the structure to
avoid trip hazard.

. Documents of the equipment to be checked


and cleared.
Electric Shock
Madhure Infra Engineering Pvt.Ltd
Project :-Avalon City Dapodi

Job Safety Analysis

Electric panel of the equipment to be tested


and certified.

Proper earthing to be provided for the


equipment.

All the electric connections to be given through


ELCB’s and will avoid running of cables
through sharp edges, water or wet area or
running on the ground to avoid electric shock.
Fall Hazard Swing area of the tower crane to be isolated
from the movement of traffic.

Continuous supervision to be provided.

Working at height using tower


All the tools and tackles to be certified by a
crane.
competent person including man cage and
concrete bucket.

Authorised operator is allowed to operate the


tower crane.

Proper SWL to be followed. Do not over load


the man cage.

Only one man is allowed to control the signal


Madhure Infra Engineering Pvt.Ltd
Project :-Avalon City Dapodi

Job Safety Analysis

for the tower carne.

People using man cage have to use safety


harness (full body) and hook the harness on
Material Fall hazard the handle provided on the hook on the ceiling
of the tower crane and the entrance of the cage
to be closed before hoisting.

Special training to be given those who are


using the tower crane.

All the tools and tackles to be certified by a


competent person including man cage and
concrete bucket.

Authorised operator is allowed to operate the


tower crane.

Proper SWL to be followed. Do not over load


Hit Hazard
the man cage.

Only one man is allowed to control the signal


for the tower carne.

Tower crane swing area to be cleared from all


the obstructions.

Before extending the boom, area ahead should


be cleared from electrical cables.
Madhure Infra Engineering Pvt.Ltd
Project :-Avalon City Dapodi

Job Safety Analysis

Counter weight moving part area of tower


crane to be isolated using barricading.
Trip hazard
Always one person to be there to supervise
and to give signal for the tower crane.

Daily tool box talks to be followed and


recorded.

House keeping Work area should kept neat & clean after the
completion of work.

All the scraps to be to shifted to the specified


Inadequate illumination
scrap area.

Remove all the materials used for shuttering


from the work area and shifted to the yard as
soon as the de-shuttering work ends or
properly stacked at the work place for reuse.

Working at night
Proper illumination to be provided at the work
area as per required or depends on the work.

Job Safety analysis attendees : Mr.Devidas Sonkamble,Mr.Shivsharan Vhanmhane,Mr.Vijaykumar Lohiya,Mr.Ravikumar


Thokal
Madhure Infra Engineering Pvt.Ltd
Project :-Avalon City Dapodi

Job Safety Analysis

Written by Ravikumar Thokal


Revieved by Vijaykumar Thokal