Project : Prepared
RDMP – HVAC By Package 2 Reviewed By Approved By
Company : PT.PP SPV
Urban Chief/HSE Manager CM
Scope of Work/Pkg : HVAC Package 2
JSA No. : RDMP /
JSA / ............. / ...............
Position : Supervisor
Job Activity : Loading – unloading container
Area :
Date :
Name
Signature
Date
Status
Status
No Permit Registry No
Open 🗸 Close 🗸
Permit Registry No
Open 🗸 Close 🗸
No
NO Sequence of Basic Hazard Risk Consequence / Risk Recommendation action Result Risk*) PIC
Job Steps Bahaya Resiko severity Assessment* Tindakan Pengendalian Penanggung
Tahapan pekerjaan Akibat Jawab
JOB SAFETY ANALYSIS (JSA) AND RISK ASSESSMENT FORM
PR SV RR PR SV RR
1. Persiapan 1.1 Tidak 1.1 Komunikasi yang 1.1 Kesalahan prosesur 3 2 M 1.1 Pastikan semua pekerja 2 1 L Supervisor
Preparation Memahami gagal. kerja. ikut ToolBox Meeting
Materi Yang Miss Erroneous work sebelum Pekerjaan akan
Disampaikan communication. procedures. dilakukakan dan
Oleh Supervisor mengisi attendent list
saat ToolBox 1.2 Human Error. 1.2 Koordinasi kacau, bagi yang terlambat
Meeting Human error Erroneous tidak diijinkan mengisi
Not coordination attendent list.
Understanding 1.3 Pekerja tidak Make sure all workers
the Material memahami step 1.3 Kecelakaan kerja. join the Tools Box
pekerjaan. work accident Meeting before the
Presented by the
Workers do not
Supervisor on Work will be done
understand the
ToolBox Meeting work steps
1.2 Tool box meeting
1.2 Pekerja Tidak 1.4 Pekerjaan tidak dipimpin oleh
diawasi dengan supervisor.
Memahami
benar. Tool box meeting are
Tugas – lead by supervisor
Work not control
Tugasnya
properly
Workers do not 1.3 Pastikan semua peserta
understand their TBM memahami
duties. prosedur dan jalur
komunikasi saat terjadi
1.3 Pekerja tidak kondisi emergency .
ikut TBM. Ensure for all TBM
Workers do not attendance is know for
join TBM emergency procedure
and emergency
1.4 Ijin kerja tidak evacuation route
ada.
No Work Permit 1.4 Pastikan semua
memahami isi dari
JOB SAFETY ANALYSIS (JSA) AND RISK ASSESSMENT FORM
toolbox meeting.
Ensure all attendance is
know content of TBM
kerja (SIKA),
pernyataan metode
kerja, jsa, dan sertifikat
alat dan kompetensi
sudah ada, valid dan
disetujui
Ensure the work permit
(SIKA), work method,
JSA, and certificate is
valid and approved
2 Persiapan pekerjaan, 2.1 Alat belum 2.1 Alat rusak 2.1 Pekerjaan tidak 3 3 M 2.1 Periksa alat kerja 2 1 L Supervisor
pemeriksaan alat – diperiksa dan Tool or equipment bisa dikerjakan/ sebelum memulai
alat kerja broken or dilanjutkan pekerjaan.
diberi tanda
Prepare for work, Stop work or cant Tool and equipment
pemeriksaan disfunction
tool and equipment continue check before start
checking Tool and working.
equipment work
is not checked 2.2 Pastikan alat dalam
yet and give keadaan fit dan telah di
sign check periksa oleh tim
RDMP JO.
Ensure for tool and
equipment is on good
condition and already
checked by RDMP JO
inspection team.
3 Bongkar – muat 3.1 Gagal memahami 3.1 Terkena fasilitas 3.1 Kerusakan 4 4 H 3.1 Hanya operator yang 2 1 L Operator
container fasilitas eksisting eksisting property memiliki SIO MIGAS Crane (SIO
Loading - unloading Exposed to Property damage dan bersertifikat yang must be
Failed to
container existing facilities dapat mengoprasikan included)
understand 3.2 Ganti rugi alat berat.
existing facilities 3.2 Kebocoran pipa Compensation Only operator that
minyak, gas, uap, already have SIO
3.2 Terkena manuver & air. 3.3 Kebakaran/ledak MIGAS and certified
alat Leak of oil, gas, anFire and that can operate
Exposed with explosion equipment
steam or water
lifting equipment
pipe line
3.4 Luka Memar dan 3.2 Pastikan prosedur
3.3 Tumpahan sobek berkendara yang aman
minyak atau oli 3.3 Kebocoran gas
Bruises and torn terlaksana / peraturan
pada mesin beracun wounds lalu lintas dalam
Oil spill to Leak of poisonus kilang.
machine gas 3.5 Tertimpa, terjepit, Ensure the safety
terbentur driving and traffic
3.4 Peralatan angkat 3.4 Kebakaran mesin Struck down, regulations in refinery
angkut terbalik Auto ignition pinched, hit procedure is already
Lifting Gear done
collapse 3.5 Kerusakan alat 3.6 Kematian
Equipment broken Fatality 3.3 Komunikasi dengan
HSSE RDMP dan JO
3.6 Tertimpa dan saat akan mobilisasi
Comunicate with
terjatuh
JOB SAFETY ANALYSIS (JSA) AND RISK ASSESSMENT FORM
penampungan kedua
di bawah mesin yang
digunakan.
Doing machine
condition daily
checklist and provide
spill storage under the
machine
4 Pekerjaan selesai, 4.1 Bekerja dengan 4.2 Area kotor dan 4.3 Kebersihan yang 3 2 M 4.4 Pastikan area bersih Supervisor
Housekeeping peralatan berantakan buruk dan rapi sebelum
Finishing work,
angkat angkut Dirty and Bad meninggalkan area
houseeping
Working with crowded housekeeping pekerjaan
lifting gear Ensure the location is
neat and clean before
leaving work area
JOB SAFETY ANALYSIS (JSA) AND RISK ASSESSMENT FORM
8
9
10
11