SRI DATAI-CHM JV SDN BHD

PACKAGE B1: PROPOSED CONSTRUCTION OF


Doc. No: QA/014(a)
HIGHWAY FROM SEBUYAU TO LINGGA,
Project Title: SAMARAHAN AND SRI AMAN DIVISION
Rev: 00
(CONTRACT NO: PWD/HO/B113/2020)
Ref No: SSTR/SCJV/PB01/MST/00032
METHOD STATEMENT SUBMISSION Rev. 00
Title: Method Statement for Work Sequence on High Strength Geotextile

Submitted by: Acknowledgement of Receipt:

Signature : Signature :
Name : Tong Tianzhi Name :
Date / Time : 12/04/2023 Date / Time :
Technical comments:

Status: -

Approved Signature :

Approved with Comment

Reject Commented by :

Date :
1. Opus Consultant (M) S/B
3. JKR CSTRU
CC: Attn: Ir. Christopher Liew/ Mr. Pedo Anak
Attn: Mr. Kennedy Kedo
Ewat
2. KTA HQ
4.
Attn: Mdm. Tang Su Fan
SRI DATAI-CHM JV SDN BHD

Ref No:
Method Statement for Work Sequence on High
SSTR/SCJV/PB01/MST/00032
Strength Geotextile
Rev.00

PROPOSED CONSTRUCTION AND COMPLETION OF


THE SARAWAK SECOND TRUNK ROAD

PACKAGE B1: PROPOSED CONSTRUCTION OF


HIGHWAY FROM SEBUYAU TO LINGGA, SAMARAHAN
AND SRI AMAN DIVISION

(CONTRACT NO: PWD/HO/B113/2020)

METHOD STATEMENT

FOR

WORK SEQUENCE ON HIGH STRENGTH GEOTEXTILE

Description of Prepared By Reviewed By Approved By


Rev No. Date
Amendments (QAQC Manager) (Chief Engineer) (Project Manager)

00 12/04/2023 1st Issue Tong Tianzhi Xie Bo Yuan Huiming

2
SRI DATAI-CHM JV SDN BHD

Ref No:
Method Statement for Work Sequence on High
SSTR/SCJV/PB01/MST/00032
Strength Geotextile
Rev.00

TABLE OF CONTENT

1.0 SCOPE OF WORK 4


1.1 Purpose 4
1.2 Scope 4
2.0 ABBREVIATION & DEFINITIONS 4
3.0 REFERENCES 5
3.1 Projects Documents & Construction Drawings 5
3.2 Standards 5
4.0 RESOURCES 6
4.1 Materials 6
4.2 Plant, Machinery & Equipment 6
4.3 Manpower 7
5.0 CONSTRUCTION 8
5.1 Installation of High Strength Geotextile DJL 40 / DJL 60 8
5.2 Temporary Access Road 9
5.3 Spread of Sand 12
5.4 Measuring Thickness of Sand (Reinforcement Layer 1 & 2) 13
6.0 SAFETY AND HEALTH 14
6.1 Job Safety and Health Analysis 14
6.2 Emergency Arrangement & Information to Personnel 14
7.0 ENVIRONMENTAL CONTROL 15
8.0 QUALITY ASSURANCE & QUALITY CONTROL PLAN 15
8.1 Inspection and Testing 15
9.0 APPENDICES 15
Appendix 1 Job Safety & Health Analysis
Appendix 2 Inspection Forms / Checklists
Appendix 3 Layout / Drawings

3
SRI DATAI-CHM JV SDN BHD

Ref No:
Method Statement for Work Sequence on High
SSTR/SCJV/PB01/MST/00032
Strength Geotextile
Rev.00

1.0 SCOPE OF WORK

Purpose

The purpose of this method statement is to define the specific tasks relating to the construction
procedures, materials, plant, equipment required, resources needed and precautions to perform the
work or construction sequence for laying of woven high strength geotextile and laying of sand.

Scope

This method statement will cover / apply for the works at location CH 0+060.232 to CH 28+550 as
shown in Special Embankment Construction Drawing and Road Foundation Treatment Schedule
attached in Appendix.

2.0 ABBREVIATION & DEFINITIONS

Table 1 Abbreviation & definitions

Abbreviation Definition
S.O. Superintending Officer
S.O.R. Superintending Officer Representative
JKRS Jabatan Kerja Raya Sarawak
ITP Inspection and Test Plan
RFI Request for Inspection
NCR Non-Conformance Report
CH Chainage
REV Revision
EGL Existing Ground Level
NA Not Applicable

4
SRI DATAI-CHM JV SDN BHD

Ref No:
Method Statement for Work Sequence on High
SSTR/SCJV/PB01/MST/00032
Strength Geotextile
Rev.00

3.0 REFERENCES

3.1 Project Documents & Construction Drawings

Table 2 Project documents & construction drawings

No. Document Remarks

1 Approved Shop Drawings Submit Progressively


KPKR/J/LB/1118/7558/B1/GE/SCH/RFT-101 (Rev.00)
KPKR/J/LB/1118/7558/B1/GE/SCH/RFT-102 (Rev.00A)
2 Contract Drawings KPKR/J/LB/1118/7558/B1/AM/TR-110 (Rev.00) –
KPKR/J/LB/1118/7558/B1/AM/TR-129 (Rev.00)

3 Quality Assurance Plan (QAP) Revision 01 (Submitted)

4 HSE Plan Revision 00 (Submitted)

5 Environmental Management Plan (EMP) Revision 00 (Submitted)

3.2 Standards

Table 3 Standards

No. Document Remarks

JABATAN KERJA RAYA (JKR) STANDARD JKR / SPJ / 1988,


1 SPECIFICATION FOR ROAD WORKS
(INCLUDING BRIDGE STRUCTURES) JKR 20401-0017-89

JABATAN KERJA RAYA Circular no. DPW 01/2020 dated


2 SPECIFICATION OF PARTICULAR
APPLICATION 13th February 2020
Specification for Geotextile

5
SRI DATAI-CHM JV SDN BHD

Ref No:
Method Statement for Work Sequence on High
SSTR/SCJV/PB01/MST/00032
Strength Geotextile
Rev.00

4.0 RESOURCES

4.1 Materials

Detail of materials to be used in the work:


Table 4 Materials
No. Type of Material MSA Ref. No.

1 Dae Jung DJL 40 (400/50kN) 7558/B1/46.2-CV (0009)

2 Dae Jung DJL 60 (600/50kN) 7558/B1/46.2-CV (0009)

Sibu Rejang River


3 Sand SSTR-SCJV-PB01-MSA-00012 (Rev.01)
Muara Saribas
SSTR-SCJV-PB01-MSA-00029 (Rev.00)

4.2 Plant, Machinery & Equipment

Detail of plant, machinery and plant proposed to be used to perform work:


Table 5 Plant, Machinery and Equipment
No. Plant, Machinery, Equipment & Material Quantity Purpose
1 Lorry Crane 1 Transportation of material.

2 Dump Truck 20 Transportation of sand material.

3 Bulldozer 2 To level sand material.

4 RTK-GPS 2 To measure coordinate & horizontal


distance.
5 Measuring Tape 2 To measure distance.

6 Auto Level 2 To measure vertical distance.

7 Level Staff 2 To measure vertical distance.

6
SRI DATAI-CHM JV SDN BHD

Ref No:
Method Statement for Work Sequence on High
SSTR/SCJV/PB01/MST/00032
Strength Geotextile
Rev.00

4.3 Manpower

List of supervision and workforce to be involved in the work:


Table 6 Manpower
No. Description No. of Brief Roles and Responsibilities
Person
1 Construction Manager 1 Assist Project Manager, overseeing the project
site and progress monitoring.
2 Site Engineer 2 Implementing site work and recording site
diary.
3 Safety Officer 1 Advice, implementing and enforce safety
procedure at site.
4 Site Safety Supervisor 2 Implementing site safety procedure at site.

5 Site Supervisor 2 Supervising and coordinate work progress on


site.
6 QAQC Engineer 1 Maintain quality of product and comply to
technical specification by Authority and
contract requirement.
7 Surveyor 2 Setting out, survey of embankment boundary
and levels.
8 Machinery Operator 4 Operating and driving the machines.

9 General Worker 6 Labour work on site.

10 Environmental Officer 1 Supervising environmental issue on site.

11 Chainman 4 Assisting surveyor to carry out survey work.

7
SRI DATAI-CHM JV SDN BHD

Ref No:
Method Statement for Work Sequence on High
SSTR/SCJV/PB01/MST/00032
Strength Geotextile
Rev.00

5.0 CONSTRUCTION

5.1 Installation of High Strength Geotextile DJL 40 / DJL 60

The purpose of this work sequence is to protect the high strength geotextile from damaged by the
construction equipment and deterioration due weathering. After PVD and PHD were completely install
and conduct inspection with SOR, lay and compact 200mm drainage sand layer and conduct field
density test. Once the field density test is pass, setting up high strength geotextile based on approved
shop drawing with the witness of SOR. Laying of high strength geotextile will start up to 50m-100m.
Inspection of geotextile shall be carried out to confirm the length of geotextile laying and seaming of
geotextile as per project specification. Method of installation and seaming refers to Method Statement
ref. no.: SSTR-SCJV-PB01-MST-00006 (Rev.00). As-built of high strength geotextile shall be taking
after full width of laying.

Figure 1 Platform before laying geotextile

8
SRI DATAI-CHM JV SDN BHD

Ref No:
Method Statement for Work Sequence on High
SSTR/SCJV/PB01/MST/00032
Strength Geotextile
Rev.00

Figure 2 Laying of high strength geotextile DJL 40 / DJL 60

5.2 Temporary Access Road

Temporary access road will be made with laying of sand from right-hand side counter berm, 1.5m
away from rod settlement gauge and the width is ≤ 8m to road embankment with proper compaction,
sand thickness is 500mm. Laying of sand will lay up to 50m-100m to serve as the temporary access
road. The width of the access road may subject to modification that is made according to treatment
type and site condition.

Table 1 Treatment type & counter berm width

Item Treatment Type Counter Berm Width Geotextile Type


1 P1a 5m DJL 40
2 P2a 9m DJL 40
3 P3a 10m DJL 40
4 P5a 10m DJL 40
5 P6a 14m DJL 60
6 P9a 14m DJL 40 (2 layers)
7 P10a 16m DJL 60 (2 layers)

9
SRI DATAI-CHM JV SDN BHD

Ref No:
Method Statement for Work Sequence on High
SSTR/SCJV/PB01/MST/00032
Strength Geotextile
Rev.00

Before laying of temporary access road, the plywood with the size of 4’ x 8’ will placed on the interface
of geotextile to protect the geotextile from passing through by heavy machineries.

Figure 3 Playwood placed on the interface of geotextile

Plywood also will place above the geotextile located at the left-hand side and temporary close with the
warning caution tape to avoid heavy machineries or car to go through.

Figure 4 Left hand-side temporary close using the warning caution tape

10
SRI DATAI-CHM JV SDN BHD

Ref No:
Method Statement for Work Sequence on High
SSTR/SCJV/PB01/MST/00032
Strength Geotextile
Rev.00

After fill up to 50m-100m at right hand side, it will serve as a temporary access road at site for the
traffic movement.

Figure 5 Right-hand side serve as temporary access road

11
SRI DATAI-CHM JV SDN BHD

Ref No:
Method Statement for Work Sequence on High
SSTR/SCJV/PB01/MST/00032
Strength Geotextile
Rev.00

5.3 Spread of Sand

Laying of sand will continuously at left hand side until reach full width.

Figure 6 Direction of sand filling

After lay first 300mm (first reinforcement layer) of full width compacted sandfill, enter 2 weeks rest
period. Proceed with the sandfill for another 200mm (second reinforcement layer) up until achieve the
thickness of 500mm as per drawing. Field density test shall carry out after the compaction for both
layers.

Wrapping back geotextile minimum 1500mm as per drawing. Then, 0.5m of capping layer will be
placed by using the excavation materials on the both sides of the embankment. Wait as per the waiting
period 1 specified in the road foundation treatment schedule.

The work sequence will be repeated up to every 50m-100m on site. The sand filling work up to 50m-
100m (full width) shall be completed in 14 days. The actual complete time may subject to change due
to the weather and site condition.

During the construction work, temporary signage such as advance warning sign or temporary barrier
shall be placed at proper position to effectively convey the message to workers at site.

12
SRI DATAI-CHM JV SDN BHD

Ref No:
Method Statement for Work Sequence on High
SSTR/SCJV/PB01/MST/00032
Strength Geotextile
Rev.00

Any damage of geotextile during the construction will repair or rectify with our own cost and time.
Request for Inspection (RFI) will be issue out to SOR before any commencement works at site.

5.4 Measuring Thickness of Sand (Reinforcement Layer 1 & 2)

The flow chart of measure reinforcement sand thickness as per below:

13
SRI DATAI-CHM JV SDN BHD

Ref No:
Method Statement for Work Sequence on High
SSTR/SCJV/PB01/MST/00032
Strength Geotextile
Rev.00

6.0 SAFETY AND HEALTH

6.1 Job Safety and Health Analysis

Safety and health aspects shall be exercised before and when implementation of the works and shall
be in accordance to Safety and Health Management Plan and other relevant documents stated in section
3.1. All control measures required for the activity is listed in Appendix 2: Job Safety and Health
Analysis.
Table 6 Personal Protective Equipment (PPE)

PERSONAL PROTECTIVE EQUIPMENT REMARKS


Safety Helmet Must use while work on site
Safety Vest Must use while work on site
Safety Boots Must use while work on site
Safety Harness Use while working at high place
Goggle Must use when involve tools
Mask Must use while work on site
Gloves Must use when involve in hot work

6.2 Emergency Arrangements & Information to Personnel

1. Safety officer shall be informed of the works to be performed and HIRARC of the works to be
carried out is established and approved.
2. Relevant personnel on site shall be briefed of the emergency contact details, response and made
reference to procedures in accordance to Project Emergency Response and Preparedness Plan.
3. Pre-task briefing will be conducted by the safety personnel in charge based on the control measures
detailed in the Job Safety and Health Analysis, Appendix 2.
4. In the event of any emergencies, the work team representative is required to immediately contact
the designated safety personnel as per the Project Emergency Response and Preparedness plan.

14
SRI DATAI-CHM JV SDN BHD

Ref No:
Method Statement for Work Sequence on High
SSTR/SCJV/PB01/MST/00032
Strength Geotextile
Rev.00

7.0 ENVIRONMENTAL CONTROL

1. In general, construction activities will inevitably contribute to some soil dispersion as well as
sediment pollution and any increase the concentration of suspended solids in the receiving
waterways.
2. Complying with all the requirements and statutory requirements in order to preserve and take care
due care of the local existing environment.
3. The potential environmental impacts shall be identified by the project team for all the related
activities and control measures shall be developed concurrently based on the identified impacts.
4. Check dam shall be constructed across the temporary earth drainage ditch. Silt fence also shall be
constructed around the stock pile area and along the river on both sides within the ROW in this
project. Silt fence consists of non-woven geotextile and supported by wooden fence.
5. Silt trap that comprises rock in gabions shall be constructed in respective catchment area to collect
and store sediment before entering natural waterways.
6. For detail environmental work, please refer to method statement for erosion and sediment control,
document no.: SSTR/SCJV/PB01/MST/00015 (Rev.01).
7. Dust control measures shall apply to construction site where there is the potential for air pollution
from dust traveling through the air.
8. To control sand dust on site, a water tanker is driven on site spraying water over the affected area
preventing the sand dust. Water should be applied a couple of times a day, depending on the
atmospheric conditions. The quantity of water applied should be carefully managed to prevent
excess water that can cause erosion problems.
9. Set appropriate and site-specific speed limits for vehicles enter the site to minimize generating dust.
Install signpost at suitable location on site and site workers are aware of designated speed limits.

8.0 QUALITY ASSURANCE & QUALITY CONTROL PLAN

8.1 Inspection and Testing


1. Implementation of QAQC works shall be in accordance with contractor Quality Assurance Plan
(QAP REV01 with code 1 status) and relevant quality system procedures.
2. The inspection and test plan (ITP) shall be approved by consultant.
3. The ITP details for the work shall be referred in Appendix 3.

9.0 APPENDICES

Appendix 1: Job Safety & Health Analysis


Appendix 2: Inspection Forms and Checklist
Appendix 3: Layout/Drawing

15
SRI DATAI-CHM JV SDN BHD

Ref No:
Method Statement for Work Sequence on High
SSTR/SCJV/PB01/MST/00032
Strength Geotextile
Rev.00

APPENDIX 1
Job Safety & Health Analysis

16