Reference No: J2618 / WMS / LSC / HSC / Revision No: 00 Revision Date: DD/MM/YYYY
JALEX Prepared:
SUNWAY Checked:
CONSTRUCTION
SDN. BHD. Reviewed:
REMARKS / COMMENTS
WORK METHOD STATEMENT
Title: TILING WORKS
Ref: J2618 / WMS / LSC / HSC
TABLE OF CONTENTS
- Table of Contents 2
- Amendments 3
1.0 Introduction 4
9.0 Attachments 7
WORK METHOD STATEMENT
Title: TILING WORKS
Ref: J2618 / WMS / LSC / HSC
AMENDMENT RECORD
DISTRIBUTION LIST
1 Project Director
(Master) Sunway Construction Sdn. Bhd. Yap Kah Hoo
(Main Contractor)
Project Manager
2 Turner International Malaysia Midhat Khalil
(Project Management Consultant)
Landscape Architect
3 Praxcis Design Sdn. Bhd. Norhafizawati Dahaman
(Landscape Consultant)
Note:
a) Any copy of this Method Statement is only valid for reference after it has been completely
signed off by SunCon.
b) In order to facilitate the task of Quality Control at the project site, the forms and checklists
attached with the latest revision of this Method Statement can be freely copied and used.
Outdated / superseded forms and checklists must not be used.
c) If there are any errors, outdated or incorrect information, missing or illegible pages, and/or
any other concerns about this Method Statement and/or its attachments; or if a complete
replacement set is required, please inform SunCon’s QA Department immediately.
WORK METHOD STATEMENT
Title: TILING WORKS
Ref: J2618 / WMS / LSC / HSC
1.0 OBJECTIVE
The objective of this Work Method Statement is to outline the methodology for Tiling
Works in order to ensure consistent quality as per design intent/specification.
The scope of work mentioned in this method statement as specified in the Contract
Specification and Construction Drawings. The methodology is applicable for:
All workers employed in the project site must have valid CIDB Green Card.
Item Description
3.1.1
3.1.2
3.1.3
3.2 Manpower
Item Description
3.2.1
3.2.2
3.2.3
WORK METHOD STATEMENT
Title: TILING WORKS
Ref: J2618 / WMS / LSC / HSC
3.3 Material
Item Description
3.3.1
3.3.2
3.3.3
3.3.4
4.1 Consignments of materials should be stored at the designated area and placed such
a way that they will be used in order of delivery and to permit the inspection and
sampling of individual batch. The materials should be inspected when delivered to
site to check for any deterioration or damage.
4.2 To prevent possible deterioration of materials, the material bags shall not be left /
stored under direct sunlight or very hot areas. The storage requirement shall follow
the MSDS.
4.3 Hoisting and transporting of material shall be done with tower crane, mobile crane or
any other material hoist. The respective supervisor is to ensure the hoisting and
handling of material is carried out in a safe manner. Loading platform shall be
provided at designated areas at each floor for loading and unloading purposes.
5.1 Preparation
5.1.1
5.2 Methodology
5.2.1
5.3.1
WORK METHOD STATEMENT
Title: TILING WORKS
Ref: J2618 / WMS / LSC / HSC
6.1 All inspection and testing involved shall as outlined in the Inspection Checklist and
Inspection & Test Plan attached in Attachment 1 & 2.
7.1.8 Contractors related to works conducted shall be represented at the monthly ESH
Committee meeting.
Job Safety & Health Analysis (JSA) shall be carried out on the activity prior to work
commencement. All recommended control measures identified in the JSA shall be
implemented and the potential hazards and risks shall be briefed to all personnel prior
to work commencement. For detailed JSA, please refer to Attachment 3.
WORK METHOD STATEMENT
Title: TILING WORKS
Ref: J2618 / WMS / LSC / HSC
7.3.1 In the event of emergency such as fire explosion, evacuation, structure collapse, major
injury or fatality, it shall be reported immediately to any of the following person
available:
a) Project Manager
b) Safety Personnel
c) Supervisors
7.3.2 Designated assembly area and emergency evacuation route shall be established and
communicated to all parties.
9.0 ATTACHMENTS
Attachment Description
1 Submission of Method Statement for Prior work commencement Method statement comply with the technical Method statement ,
approval specification and construction drawings Checklist, ITP & Material
H P&C C - A
Data Sheet
2 Technical/ Material Submission Prior to placement of purchase As per contract document Relevant technical/ material
order submission H P&C C - A
3 Shop Drawing Submission Prior work commencement As per specification and approved drawings Shop Drawing
H P&C C - A
4 Approval as of Mock Up As per mock up schedule Work carried out as per work method WIR & Inspection Checklist
statement/ checklist H P&C C - A
5.3 Post Inspection After completion of works/ No significant defects or damages / no Defects List (if any)
Before handover of the work incomplete works N P&C C - A
H = Hold Point (work shall only proceed upon consultant's written approval) N = Notification Point (subsequent works can proceed without consultant's prior approval)
P = Preparation C = Check A = Approve T = Test I = Interprete R = Review W = Witness (not compulsory) ** = Randomly
Legend: Y: Yes N: No
Location : Date of Inspection:
ID Main
Item Description Consultant
Contractor Contractor
1 Work Preparation Y N Y N Y N
a)
2 Installation Works Y N Y N Y N
a)
3 Post Inspection Y N Y N Y N
a)
Y N Y N Y N
4 Others (please state): _________________________________
Name / Signature of
Designation: Date:
ID Contractor NSC
Representative
Name / Signature of
Designation: Date:
Main Contractor
SunCon’s
Representative
Name / Signature of
Designation: Date:
Consultant Consultant’s
Representative
#Status Of Inspection: √ = Acceptable, X = Not Acceptable, – = Not Applicable * Circle or delete one
ATTACHMENT 3
Job Safety Analysis
SUNWAY CONSTRUCTION SDN BHD
HAZARD IDENTIFICATION, RISK ASSESSMENT AND RISK CONTROL (HIRARC)
Project / Department : TNB HQ CAMPUS (J2618) / OPERATION HIRARC No. : TNBHQ-JSA-201- Risk Rating (Likelihood x Severity)
Location : Date : High : 15-25 (Not – Acceptable)
SWMS / Job Activity : Rev. No. : 00 Medium : 4-12 (Tolerable)
Page : Low : 1-3 (Acceptable)
Other Risk (R) & Opportunity (O)
R/O Description R/O Description Likelihood Severity
5 Almost Certain 5 Catastrophic
4 Frequent 4 Major
3 Occasional 3 Moderate
2 Remote 2 Minor
1 Rare 1 Negligible
HAZARD IDENTIFICATION Initial Risk Assessment Risk Control Final Risk Assessment
Recommended
Sequence of Current Control Risk Risk Risk Risk
Item Hazard Risk Consequences L S Control Measure / L S
Work Rating Level Rating Level
Opportunity