WP-MS-120
Project Quality Plan
Rev. Code : 0 Page 1 of 8

: Section: Work Procedures Effectivity : July 2021

: Subject: WP-MS-120 Method Statement for Masonry Works

METHOD STATEMENT FOR


MASONRY WORKS

By MDC Buildplus

AVIDA TOWERS MAKATI SOUTHPOINT

Document Review

Name Title Signature Date

Prepared by: Amadeo Marco Urbano MDCBP QAQC Engineer 9/16/2021


9/17/2021
Reviewed: Recil Faye Oribello MDC TSD Supervisor
9/20/2021
Reviewed: Marciano Lunag MDC Safety Superintendent
9/20/2021
Reviewed: Mary Ann Mina MDC Senior QAQC Engineer

Checked By: 9/16/2021 Approved By: 9/16/2021

Jerome Cortez Gareth John Galang


Project Superintendent Project-in-Charge
DocuSign Envelope ID: 82449129-1F9E-481F-8FEC-7B4C92003993

WP-MS-120
Project Quality Plan
Rev. Code : 0 Page 2 of 8

: Section: Work Procedures Effectivity : July 2021

: Subject: WP-MS-120 Method Statement for Masonry Works

Table of Contents

1 SCOPE OF WORK………………………………………………………………………….3
2 REFERENCE DOCUMENTS ...................................................................................... 3
3 WORK METHODOLOGY ............................................................................................ 3
4 MAJOR PLANT AND EQUIPEMENT ......................................................................... 7
5 SAFETY PRECAUTIONS ........................................................................................... 8
6 ENVIRONMENTAL PROTECTION MEASURES ....................................................... 9
7 QUALITY ASSURANCE / CONTROL ........................................................................ 9
7.1 TESTS ........................................................................................................................... 9
7.2 MEASURING AND TESTING EQUIPMENT TO BE CALIBRATED .............................................. 9
7.3 INSPECTIONS ................................................................................................................. 9
7.4 PARTIES REQUIRING ACCREDITATION ............................................................................. 9
8 RESPONSIBILITIES ................................................................................................. 10
9 APPENDICES ............................................................................................................. 8

Checked By: 9/16/2021 Approved By: 9/16/2021

Jerome Cortez Gareth John Galang


Project Superintendent Project-in-Charge
DocuSign Envelope ID: 82449129-1F9E-481F-8FEC-7B4C92003993

WP-MS-120
Project Quality Plan
Rev. Code : 0 Page 3 of 8

: Section: Work Procedures Effectivity : July 2021

: Subject: WP-MS-120 Method Statement for Masonry Works

1 SCOPE OF WORK
This method statement for fit out works covers the following scope:
1) Supply and installation of CHB, Lintel beams and stiffener column

The aforementioned scope of works is intended for MDC The Avida Towers Makati
Southpoint.

2 REFERENCE DOCUMENTS
 Division 4, Masonry, Structural Specification
 MSDS of approved materials to be used
 Shop Drawings

3 WORK METHODOLOGY

3.1 Pre-activity Methodology

3.1.1. Assure all methodologies, materials, mock-ups, and shop drawings are
approved prior start of activity

3.1.2. Secure all necessary permits prior work activity (work request, tool permits,
Etc.) thru Submittal Tool in Procore System

3.1.3. Secure material delivery inspection (MDI) form per delivery thru Forms Tool
in Procore System

3.1.4. Assure proper handover procedure is implemented on-site. Handover forms


are created thru Forms tool in Procore System

3.1.5. Check all materials if in good condition prior installation.

3.2 Preparation

3.2.1 All construction materials, tools and equipment should be prepared and
readily available on site as well as the work force needed to complete the
project.

3.2.2 Masonry delivered to site shall be carefully unloaded and handed to


adequate size.

3.2.3 In dry and hot climate, masonry units will be wetted before laying to prevent
quick drying and shrinkage of cement based mortars.

3.2.4 Verify that all reinforcing, anchors, dowels, lintels flashing and other built-in
items are on hand, of proper size and locations established.

3.2.5 Chb must be cut with a circular power tools using the appropriate blade to
the materials being cut.

9/16/2021
Checked By: Approved By: 9/16/2021

Jerome Cortez Gareth John Galang


Project Superintendent Project-in-Charge
DocuSign Envelope ID: 82449129-1F9E-481F-8FEC-7B4C92003993

WP-MS-120
Project Quality Plan
Rev. Code : 0 Page 4 of 8

: Section: Work Procedures Effectivity : July 2021

: Subject: WP-MS-120 Method Statement for Masonry Works

3.3 Application

3.3.1 Always verify wall setting-out

3.3.2 6” CHB shall be used for partition walls and 4” shall be used for utility
chases.

3.4 Laying

3.4.1 A thorough surface preparation shall be required prior to the laying of CHB
wall partition.

3.4.2 The Project in Charge assigned will inspect the rebars placed as per plan
before placing of CHB.

3.4.3 Vertical and Horizontal bar must be provided base on the given plan, refer
to the Masonry Notes on details of spacing and schedule of rebars.

3.4.4 Lay mortar for full bed width and for a length of 3 blocks at a time and 12mm
thickness.

3.4.5 Use a line thread from end to end with a line pin.

3.4.6 Lay one block at a time and gently pressing it in the mortar bed.

3.4.7 The whole block wall work to be built in uniform layers.

3.4.8 The PIC assigned will make sure that the wall will be plumb before
plastering can proceed.

3.4.9 At the end of the day, the Foreman will see to it that the work area is clean
before retiring.

3.5 Plastering
(Surface ready to receive paint)

3.5.1 Clean the newly aid block wall from all the dirt.

3.5.2 Clearing of mortar droppings.

3.5.3 Chipping and clearing of unevenness in the masonry.

3.5.4 Layout the correct and final alignment of markings on the concrete structure
and masonry wall. Layout the required thickness for the plastering.

3.5.5 Provide sack at the bottom part of the wall to avoid laitance to accumulate
on the floor.

3.5.6 The thickness of plaster shall be 20mm as specified. They shall be carried
out in three coats.

9/16/2021 9/16/2021
Checked By: Approved By:

Jerome Cortez Gareth John Galang


Project Superintendent Project-in-Charge
DocuSign Envelope ID: 82449129-1F9E-481F-8FEC-7B4C92003993

WP-MS-120
Project Quality Plan
Rev. Code : 0 Page 5 of 8

: Section: Work Procedures Effectivity : July 2021

: Subject: WP-MS-120 Method Statement for Masonry Works

3.5.7 Wet the surface to receive the plaster.

3.5.8 Plastering shall start from the top and work downwards to the floor

3.5.9 Throw mortar on the area covered by the straight edge, both vertically and
horizontally in one batch.

3.5.10. Level the surface using the straightedge.

3.5.11 Float the surface and finish as per specification.

3.5.12. Intermittently check the surface using the plumb line and level to make up
all imperfection.

3.5.13. To prevent further cracks, use fire proof sealant on both sides for the fire
rated wall, ordinary sealant for non-fire rated wall.

3.5.14. Interior masonry wall top join details adapt. (Bulletin no. QA. 34)

3.5.15. Put sealant on each side of the wall

3.6 Supply and installation of 1500mmW THK x 300mmH zoccallo including rebars

3.6.1 Prepare the installation form for the 150mmW THK x 300mmH height from
the given wall plan, install and ensure side support to maintain the proper
lay-out.

3.6.2 Vertical bar must be provided, 12mm diameter for embedment length
spaced at 400mm.

3.6.3 Mix concrete as required proportion of 1:2:3 (class A).

3.6.4 Lay the mixed concrete on while gently pressing it.

3.6.5 Remove the excess concrete coming out on the form. Should be taken out
by using the trowel and return to the mixing board.

3.6.6 Use mixing board (phenolic board) for mixing the concrete.

9/16/2021 9/16/2021
Checked By: Approved By:

Jerome Cortez Gareth John Galang


Project Superintendent Project-in-Charge
DocuSign Envelope ID: 82449129-1F9E-481F-8FEC-7B4C92003993

WP-MS-120
Project Quality Plan
Rev. Code : 0 Page 6 of 8

: Section: Work Procedures Effectivity : July 2021

: Subject: WP-MS-120 Method Statement for Masonry Works

4 MAJOR PLANT AND EQUIPEMENT

Masonry Trowel Masonry Rudela

Level bar/ Spirit Level Hand Drill

Hand Grinder Cutting Disc

9/16/2021 9/16/2021
Checked By: Approved By:

Jerome Cortez Gareth John Galang


Project Superintendent Project-in-Charge
DocuSign Envelope ID: 82449129-1F9E-481F-8FEC-7B4C92003993

WP-MS-120
Project Quality Plan
Rev. Code : 0 Page 7 of 8

: Section: Work Procedures Effectivity : July 2021

: Subject: WP-MS-120 Method Statement for Masonry Works

Level Hose Sealant Gun

Plumb Bob

5 SAFETY PRECAUTIONS

Appendix A – Job Hazard & Aspects Analysis / Risk Assessment

6 ENVIRONMENTAL PROTECTION MEASURES

Appendix A – Job Hazard & Aspects Analysis / Risk Assessment

7 QUALITY ASSURANCE / CONTROL


A. TESTS
Refer to Project – WP-ITP-120 – Inspection and test plan/ Construction
Specifications

B. MEASURING AND TESTING EQUIPMENT TO BE CALIBRATED


N/A

9/16/2021 9/16/2021
Checked By: Approved By:

Jerome Cortez Gareth John Galang


Project Superintendent Project-in-Charge
DocuSign Envelope ID: 82449129-1F9E-481F-8FEC-7B4C92003993

WP-MS-120
Project Quality Plan
Rev. Code : 0 Page 8 of 8

: Section: Work Procedures Effectivity : July 2021

: Subject: WP-MS-120 Method Statement for Masonry Works

C. INSPECTIONS
Refer to WP-ITP-185 – Inspection & Test Plans for Fitout Works
Refer to WP-Forms – Inspection Checklists and Forms

D. PARTIES AND PRODUCTS REQUIRING ACREDITATION OR


CERTIFICATION
N/A

8 RESPONSIBILITIES
 Project-in-Charge (PIC) – the PIC will have overall responsibility for the execution of
the fitout works. He/ She shall be responsible for the control and safety of the workers,
shall arrange safe working plan, and supervise the workforce to acheive proper and
safe execution of work. Maintains project schedule by monitoring project progress,
coordinating activities, resolving problems, recommending action, and ensures the
implementation of the Project Quality Plan (PQP), plans, and others as required by the
Contract

 QAQC Engineer – the QAQC engineer will be responsible for the quality control of
installation of materials including documentation and inspection. He/She shall be
responsible for ensuring that works comply with drawings/specifications, materials and
methodology are properly implemented on-site and carried out as per PQP and
contract requirements.

 Safety Officer – the Safety Officer will make sure that all the safety requirements are
fulfilled prior to start and during the scope of work. Ensures that the JHA and RA are
strictly implemented.

 Foreman/Leadman – Responsible for setting out of and installation of the works as


directed by any or all of the above. Ensuring quality of product, installation and program
compliance at all times.

9 APPENDICES
Appendix – Job Hazard & Aspects Analysis / Risk Assessment

Checked By: 9/16/2021 Approved By: 9/16/2021

Jerome Cortez Gareth John Galang


Project Superintendent Project-in-Charge