TABLE OF CONTENTS
Page No.
PURPOSE ............................................................................................. 3
SCOPE AND APPLICABILITY.............................................................. 3
ROLES AND RESPONSIBILITIES ........................................................ 3
PROCEDURAL STEPS ......................................................................... 4
4.1 IDENTIFY SAT REQUIREMENTS ......................................................................... 4
4.2 INCLUSION OF SAT(S) REQUIREMENTS IN EPIC SCOPE OF WORK (SOW) .. 4
4.3 PREPARE SAT(S) STRATEGY ............................................................................. 4
4.4 PREPARE PROJECT SPECIFIC SAT PROCEDURES DURING IHC ................... 4
4.5 PRE-REQUISITES OF AN SAT ............................................................................. 5
4.6 PERFORM SAT(S) ................................................................................................. 5
4.7 INFRASTRUCTURE AND CIVIL PROJECTS ........................................................ 6
REFERENCES TO OTHER DOCUMENTS ........................................... 7
DEFINITIONS ........................................................................................ 8
APPENDIX................................................................................................... 10
APPENDIX A - REVISION HISTORY LOG .................................................................... 10
APPENDIX B - LIST OF ABBREVIATIONS ................................................................... 11
APPENDIX C - FLOWCHART........................................................................................ 12
Page 2 of 12
CLASSIFICATION: C1 - CONTROLLED
PURPOSE
This corporate Procedure is a supplement to Commissioning and Handover Procedure
CORP-ENG-PRC-005 and defines the process, interfaces, key deliverables and required
approvals for the planning, preparation, and execution of Site Acceptance Tests (SATs) for
the projects executed by VP within QatarEnergy.
PROJECT TEAM
• Assists with the development of the SAT requirements with support of the
contractor and vendors as appropriate.
• Assists with preparation of the strategy for SAT(s).
• Assists with preparation of project specific SAT Procedures.
• Assists with completion of SAT(s).
• Assists with preparation of the SAT Report(s).
• Coordinates distribution of documentation to the Commissioning Team and
Asset Holder for review and approval, as applicable.
• Ensures that necessary provisions for SAT(s) are made in the EPIC contract.
COMMISSIONING TEAM
ASSET HOLDER
Page 3 of 12
CLASSIFICATION: C1 - CONTROLLED
PROCEDURAL STEPS
A flowchart of the SAT process is included as Appendix C.
4.1 IDENTIFY SAT REQUIREMENTS
The Commissioning Team that is led by the Asset Holder team member shall lead identifying
the requirements of the various SATs during the FEED stage with full support of the Project
Team, contractor, and vendors.
The intent of the SAT is to demonstrate:
a. The Equipment, Systems and Plant operations meet the design intent
b. The safe operability of Equipment, Systems and Plant so that Operational
and Final handover can be made
These tests should include, but are not limited to, the following:
• Acceptance criteria
• Duration of each SAT
• Methodology
• Test parameters
• Acceptance criteria
• Duration of each SAT
• Data to be collected
• Methodology
• Parameters to be monitored
• Roles and responsibilities of parties involved in the test
• Test parameters
• Test report formats.
Page 4 of 12
CLASSIFICATION: C1 - CONTROLLED
For the Plant SAT, the Pre-start-up Safety Review and plant start-up shall be completed
before the SAT.
4.6 PERFORM SAT(S)
4.6.1 EQUIPMENT AND SYSTEM SAT(S)
a. The Commissioning Team shall perform the Equipment and System SATs
as per the approved Procedures after their successful pre-commissioning,
with the full support of the Project Team, contractor, and vendors.
b. Generally, a 72-hour non-interrupted Equipment or System operation shall
be considered as a successful SAT.
c. The Performance Test should also be performed along with the SAT for
Equipment or Systems, if possible.
d. If the SAT fails, the Commissioning Team and Project Team shall jointly
identify the root cause and rectify the shortcomings with full support of the
Contractor and Vendors based on contractual agreements (in case of
design-related issues, Project team shall rectify). In such a case, the
Commissioning Team shall repeat the SAT after the necessary rectification
is carried out.
e. All relevant parties who witness the SAT (i.e., representatives of Asset
Holder, Commissioning Team, Project Team, Contractor, Vendor, etc.) shall
sign off the test records/logs at agreed intervals, as defined in the project
specific SAT Procedures.
f. The SAT information (i.e. log sheets, etc.) shall be collected by the
Commissioning Team with support of the Project Team, contractor, and
vendors.
g. The Commissioning Team shall prepare the SAT Report with the full
support of the Project Team, Contractor and Vendors.
a. After Start-up and Plant stabilization, the Asset Holder shall perform the
Plant SAT. They shall have full support of the Commissioning Team, Project
Page 5 of 12
CLASSIFICATION: C1 - CONTROLLED
Team, Contractor and Vendors. The criteria for an acceptable Plant SAT
shall be as defined and agreed in the project-specific Commissioning Plan.
A predefined, project-specific period (generally 72 hours) of non-interrupted
and stable Plant operation should be considered as a successful Plant SAT.
b. The Performance Test should also be performed along with the SAT, if
possible.
c. If the Plant SAT fails, the Asset Holder and Project Team shall jointly identify
the root cause and rectify the shortcomings with full support of the
Contractor and Vendors based on contractual agreements (in case of
design-related issues, Project team shall rectify). In such a case, the Asset
Holder shall repeat the SAT after the necessary rectification is carried out.
d. All relevant parties who witness the Plant SAT (i.e. representatives of Asset
Holder, Commissioning Team, Project Team, Contractor, Vendor, etc.) shall
sign off the test records/logs at agreed intervals, as defined in the project
specific SAT Procedures.
e. Once the Plant SAT is successful, the information (i.e. log sheets, etc.) shall
be collected by the Asset Holder with support of the Project Team,
Commissioning Team, Contractor and Vendors.
f. The Asset Holder shall prepare and approve the Plant SAT Report with full
support of the Project Team, Commissioning Team, contractor, and
vendors.
g. After a successful Plant SAT, the Plant Performance Test should be
implemented in accordance with CORP-ENG-PRC-010 Procedure for
Performance Test.
Page 6 of 12
CLASSIFICATION: C1 - CONTROLLED
Internal/External
Document Document
Document Title Document (if
Number Referencing
any)
Page 7 of 12
CLASSIFICATION: C1 - CONTROLLED
DEFINITIONS
TABLE 2: KEY TERMS DEFINED
Term Definition
Category ‘A’ Punch Punch List item that will prevent the safe operation of the
List Item Equipment, System or Plant and may jeopardise personnel or
environment. Such items, as agreed, shall be cleared before the
Equipment, System or Plant can progress to the next stage of the
Commissioning and Handover phase.
Category ‘B’ Punch Punch List item that will not endanger the safe operation of the
List Item Equipment, System or Plant or personnel and/or environment.
Such items, as agreed, can be carried over to the next stage and
may be cleared later.
Page 8 of 12
CLASSIFICATION: C1 - CONTROLLED
Page 9 of 12
CLASSIFICATION: C1 - CONTROLLED
APPENDIX
IP-ENG-038 Rev Fast-Track update to only reflect the new organizational All
A1.2. Sept 2015 changes.
Remarks:
Nil.
Page 10 of 12
CLASSIFICATION: C1 - CONTROLLED
Abbreviation Description
Page 11 of 12
CLASSIFICATION: C1 - CONTROLLED
Page 12 of 12