ASSESSOR NAME
BENCHMARK REQUIREMENTS MET
EVIDENCE COLLECTED
1st Attempt 2nd Attempt 3rd Attempt
Project Task 1
Project Task 2
Project Task 3
ASSESSOR INITIAL
Document Name: ICTPMG613 - AT2 Project RTO Code: 52010 CRICOS Code: 03548F
Version: 1.0 Approved on: 22 May 2023 Review Date: 22 May 2028 Page 1 of 21
FEEDBACK TO STUDENT
DATE of
ASSESSOR
FINAL
SIGNATURE
OUTCOME
Document Name: ICTPMG613 - AT2 Project RTO Code: 52010 CRICOS Code: 03548F
Version: 1.0 Approved on: 22 May 2023 Review Date: 22 May 2028 Page 2 of 21
Assessment Task 2: Project
Assessment task instructions:
This is the second (2) assessment task you must successfully complete to be deemed competent in this unit
of competency.
This assessment task requires you to complete a project
You are required to manage ICT project planning in this assessment task.
This assessment task consists of 3 Project Tasks and five (5) activities.
You are required to complete the activities based on the given scenario in this assessment task.
All tasks are untimed and are conducted as open book assessment (this means you can refer to your
textbook during the test).
You must complete the task independently.
You must respond to all questions and submit them to your Trainer/Assessor via Canvas.
You must answer all questions to the required level, e.g. provide an answer within the required word limit, to
be deemed satisfactory in this task
If you are deemed not satisfactory after the first attempt, a maximum of two resubmission attempts will be
allowed.
Document Name: ICTPMG613 - AT2 Project RTO Code: 52010 CRICOS Code: 03548F
Version: 1.0 Approved on: 22 May 2023 Review Date: 22 May 2028 Page 3 of 21
Scenario:
Sales Force Australia is a telemarketing company that has been in business for the last 8 years. It is an ISO
9001 certified company. Experienced staff of Sales Force Australia generate many positive leads for their clients
on an ongoing basis. The company listens to the feedback given by their client’s, and it helps them to be
different, unique and successful compared to their competitors. This also means more word-of-mouth publicity
and more clients' every day for the company. At present the company has the following telecommunication
infrastructure on its premises.
Eight (8) phone sets connected to PBX through copper wire
Eight (8) computer systems
One (1) data server
One (1) Panasonic Hybrid PBX
One (1) internet router
Two (2) networking switches
One (1) Ups system
As they are using a copper wire-based setup, staff are complaining more about the voice quality of the system.
The company wants to increase its infrastructure to facilitate an increasing number of clients, and they would like
to update their existing infrastructure to the following:
Twenty (20) IP phones as VoIP calling is less expensive than the existing setup
Twenty (20) computer systems with updated operating systems and soft phone applications
Forty (40) headphones including mic.
One (1) video conferencing system (to communicate with clients)
Two (2) data servers
One (1) voice server with supporting software such as, asterisk,3cx, Mitel, Sangoma etc.
One (1) router with VPN capability
Four (4) networking switches
To complete this assessment task you are required to participate in a meeting using the template provided
below:
Document Name: ICTPMG613 - AT2 Project RTO Code: 52010 CRICOS Code: 03548F
Version: 1.0 Approved on: 22 May 2023 Review Date: 22 May 2028 Page 4 of 21
The team member will:
Clarify their doubts of the team members
Provide feedback on the improvements required
Document Name: ICTPMG613 - AT2 Project RTO Code: 52010 CRICOS Code: 03548F
Version: 1.0 Approved on: 22 May 2023 Review Date: 22 May 2028 Page 5 of 21
Project Task 1:
Assessment activities
You will be required to participate in the following assessment activities:
1. Establish project control plans and determine project methodology
2. Development of a coherent project management schedule
3. Finalise project budget
Document Name: ICTPMG613 - AT2 Project RTO Code: 52010 CRICOS Code: 03548F
Version: 1.0 Approved on: 22 May 2023 Review Date: 22 May 2028 Page 6 of 21
Document Name: ICTPMG613 - AT2 Project RTO Code: 52010 CRICOS Code: 03548F
Version: 1.0 Approved on: 22 May 2023 Review Date: 22 May 2028 Page 7 of 21
Template 1: Project specifications and attributes document
Equipment Name Quantity Remarks (if any) Equipment Name Quantity Remarks (If any) Feasibility Remarks
required (Yes /NO)
Document Name: ICTPMG613 - AT2 Project RTO Code: 52010 CRICOS Code: 03548F
Version: 1.0 Approved on: 22 May 2023 Review Date: 22 May 2028 Page 8 of 21
Template 2: Project management plan
Project Lifecycle
Development Approaches/methodologies
Project sub-plans
Submission requirements
Document Name: ICTPMG613 - AT2 Project RTO Code: 52010 CRICOS Code: 03548F
Version: 1.0 Approved on: 22 May 2023 Review Date: 22 May 2028 Page 9 of 21
Activity 2: Development of a coherent project management schedule
This activity is in continuation with the previous assessment activity.
You are required to complete the following assessment activities
Prepare a coherent project management schedule
You will be required to answer the following requirements:
Further details:
After successfully documenting the project specifications as the project leader, you are required to prepare a
draft project schedule. Your project schedule must include the following information related to the project
component breakdown:
Scope of project
Establishing the sequence of tasks
Group tasks
Timelines/duration of project completion
Timelines/duration for testing the working of equipment installation
Time and efforts required to train IT staff for troubleshooting
Linking task dependencies
Finding the critical path
Assigning resources
Develop and allocate work packages
Establish schedule controls for monitoring project schedule
Document Name: ICTPMG613 - AT2 Project RTO Code: 52010 CRICOS Code: 03548F
Version: 1.0 Approved on: 22 May 2023 Review Date: 22 May 2028 Page 10 of 21
Template 3: Project schedule
Clear Voice
Project schedule Sales Force
Group tasks
Document Name: ICTPMG613 - AT2 Project RTO Code: 52010 CRICOS Code: 03548F
Version: 1.0 Approved on: 22 May 2023 Review Date: 22 May 2028 Page 11 of 21
Clear Voice
Project schedule Sales Force
Assigning resources
Document Name: ICTPMG613 - AT2 Project RTO Code: 52010 CRICOS Code: 03548F
Version: 1.0 Approved on: 22 May 2023 Review Date: 22 May 2028 Page 12 of 21
Clear Voice
Project schedule Sales Force
Signature:
Date:
Document Name: ICTPMG613 - AT2 Project RTO Code: 52010 CRICOS Code: 03548F
Version: 1.0 Approved on: 22 May 2023 Review Date: 22 May 2028 Page 13 of 21
Activity 3: Finalise project budget
This activity is in continuation with the previous assessment activity.
You are required to complete the following assessment activities
Prepare a coherent project budget
You will be required to answer the following requirements:
Determination of resource cost rates
Reserve analysis
Cost of quality
Identify areas of anticipated project spend
Determine dollar amounts and timing of cash flows
Develop and document project budget based on anticipated expenditure and cash flow
Establish controls for monitoring budget
Further details
After successfully documenting the project specifications and schedule as the project leader, you are required to
prepare a project budget. Your project budget must include the following information:
Identify areas of anticipated project spend
Determine dollar amounts and timing of cash flows
Develop and document project budget based on anticipated expenditure and cash flow
Establish controls for monitoring budget
What is required from you:
You must complete the attached project budget template on the basis of information provided.
Instructions to complete the activity:
You must complete all sections required in the template below.
You must conduct your own research to gather information on budget constraints based on the material and
equipment required to update the existing network.
You must complete this activity using the template below.
Document Name: ICTPMG613 - AT2 Project RTO Code: 52010 CRICOS Code: 03548F
Version: 1.0 Approved on: 22 May 2023 Review Date: 22 May 2028 Page 14 of 21
Template 4: Project budget
Discuss the areas of anticipated project spend and the dollar amounts.
Labor
Consultant fees
Raw materials
Software licences
Travel
Telephone charges
Office space
Office equipment
General administration
Company insurance
Equipment
Other costs discussed in the project
Document Name: ICTPMG613 - AT2 Project RTO Code: 52010 CRICOS Code: 03548F
Version: 1.0 Approved on: 22 May 2023 Review Date: 22 May 2028 Page 15 of 21
Project Task 2:
This task is in continuation with the previous assessment tasks.
Further details
In this assessment, you are required to consult with the representative from Sales Force Australia. The
representative will be the CEO of Sales Force Australia. This role will be played by your trainer/assessor.
After preparing the project plan in the last assessment task, you must explain it to Sales Force Australia. You
must explain all technical and non-technical requirements and terms included in the project plan. You must take
notes regarding their views about the project plan.
In the meeting, the CEO of Sales Force Australia wants you to include the following:
An escalation matrix that allows you to specify multiple user contacts to be notified in the event of critical issues.
Information about when a problem is not resolved within the required and/or set time-frame.
Contact details of each level of escalation matrix.
What is required from you:
You must complete the attached meeting minutes template below on the basis of the feedback provided on your
draft by the client.
Remember: This is the time, when you will be discussing all the following requirements with the representative
from Sales Force Australia.
Develop and document project management plan according to organisational requirements
Develop and document management sub-plans
Lodge documents according to organisational policies and procedures
Assess models of project management according to organisational requirements
Assess product development approach
Select project management and systems development methodology
Tailor and document methodologies to solution requirements
Lodge documentation according to organisational policies and procedures
Develop project component breakdown according to project requirements
Estimate project effort and duration
Create project schedule and document according to organisational policies and procedures
Develop and allocate work packages
Establish schedule controls for monitoring project schedule
Identify areas of anticipated project spend
Determine dollar amounts and timing of cash flows
Develop and document project budget based on anticipated expenditure and cash flow
Establish controls for monitoring budget
You must record all discussions and feedback in the meeting minutes template below.
Document Name: ICTPMG613 - AT2 Project RTO Code: 52010 CRICOS Code: 03548F
Version: 1.0 Approved on: 22 May 2023 Review Date: 22 May 2028 Page 16 of 21
Learner Observation Instructions.
Please log into canvas to access the observation checklist – OBC1 (AT2) Meeting with CEO
Read the instructions provided.
Once you have read and understood the instructions, please write " I understand and I am ready
for assessment" click submit to continue.
The assessor will then set up a time to complete this observation and complete the checklist on Canvas.
Your trainer/assessor will ask you relevant questions related to the project plan you completed as part of
previous activity.
To be assessed as satisfactory (S) in this assessment task you need to demonstrate competency in the following
critical aspects of evidence
f) Answer the relevant questions asked by assessor related to the following areas:
Develop and document project management plan according to organisational requirements
Develop and document management sub-plans
Lodge documents according to organisational policies and procedures
Assess models of project management according to organisational requirements
Assess product development approach
Select project management and systems development methodology
Tailor and document methodologies to solution requirements
Lodge documentation according to organisational policies and procedures
Develop project component breakdown according to project requirements
Estimate project effort and duration
Create project schedule and document according to organisational policies and procedures
Develop and allocate work packages
Establish schedule controls for monitoring project schedule
Identify areas of anticipated project spend
Determine dollar amounts and timing of cash flows
Develop and document project budget based on anticipated expenditure and cash flow
Establish controls for monitoring budget
Document Name: ICTPMG613 - AT2 Project RTO Code: 52010 CRICOS Code: 03548F
Version: 1.0 Approved on: 22 May 2023 Review Date: 22 May 2028 Page 17 of 21
Project Task 3:
This task is in continuation with the previous assessment tasks.
Further details
In this assessment, you are required to submit the final copy of the project plan to the representative from Sales
Force Australia. The representative will be the CEO of Sales Force Australia. This role will be played by your
trainer/assessor.
The final project plan must include the following:
The amended scope of the project
Current legislation and industry codes
Budget requirements of the project
Timelines of project completion
Timelines for testing the working of equipment installation
Time required to train it staff for troubleshooting
The time frame to resolve the problem (if not resolved by local it team)
Escalation matrix
Contact details for each level of escalation
Roles of installation team
Auditing of services including procedure and frequency of audit
Remember: This is the time, when you will be writing down all the following requirements again through a
revised project plan.
Develop and document project management plan according to organisational requirements
Develop and document management sub-plans
Lodge documents according to organisational policies and procedures
Assess models of project management according to organisational requirements
Assess product development approach
Select project management and systems development methodology
Tailor and document methodologies to solution requirements
Lodge documentation according to organisational policies and procedures
Develop project component breakdown according to project requirements
Estimate project effort and duration
Create project schedule and document according to organisational policies and procedures
Develop and allocate work packages
Establish schedule controls for monitoring project schedule
Identify areas of anticipated project spend
Determine dollar amounts and timing of cash flows
Develop and document project budget based on anticipated expenditure and cash flow
Establish controls for monitoring budget
What is required from you:
You must write the project plan within 1500-2500 words. You must complete the attached final project plan,
using the below Template and obtain the sign off from the client.
Your trainer/assessor will ask you relevant questions related to the project plan you completed as part of
previous activity.
Document Name: ICTPMG613 - AT2 Project RTO Code: 52010 CRICOS Code: 03548F
Version: 1.0 Approved on: 22 May 2023 Review Date: 22 May 2028 Page 18 of 21
Template 5 - Project Plan Template
Clear Voice
Project Plan Sales Force
Document Name: ICTPMG613 - AT2 Project RTO Code: 52010 CRICOS Code: 03548F
Version: 1.0 Approved on: 22 May 2023 Review Date: 22 May 2028 Page 19 of 21
Clear Voice
Project Plan Sales Force
Time frame to resolve the problem (If not resolved by local IT team)
Escalation matrix
Document Name: ICTPMG613 - AT2 Project RTO Code: 52010 CRICOS Code: 03548F
Version: 1.0 Approved on: 22 May 2023 Review Date: 22 May 2028 Page 20 of 21
Clear Voice
Project Plan Sales Force
Signature:
Date: