Section (Yard)
20-12-2022
Reviewed By Zeyar ACM
20-12-2022
Approved By Sailesh SPJM
Date of Revision
Work Method Statement
05/05/2022
Document Number (WMS-CA-C021) Rev.08
Summary of Changes
Rev. Date of Description of Change Page Ref. Requested
Revision By
1.1 Purpose
The purpose of this activity is to demonstrate the bunkering from Bunker Ship to onboard GIMI-
5DB MGO Service Tank along with its integral sub-systems and equipment. The objective is to
carry out implementation of the safe operation and can achieve the given ‘Acceptance Criteria’.
The activities will be executed by:
• Completing the sub systems and system P&ID lines which associated with all bunkered tanks.
• Completing the commissioning test procedure for all the equipment and packages in the
system.
Project Manager
OSP NA
P&M NA
Others NA
2.2
5
Area Controller
HSE Zeyar / Myat Moe
Hadikul / Hariz 82225287 / 98429095
85338445 / 84827935 Channel 10
Channel 1
Engineers
Jairus / Ronald
86464113 / 90936455
Channel 10
Machinery Commissioning
(Supervisor / Technicians) (Supervisor / Technicians)
Channel 9 Channel 10
OSP NA
P&M NA
Others NA
3.
3.1 Definition:
To carry out bunkering from Bunker Ship to GIMI Onboard 5 DB (Port) MGO Service
Tank as shown in the following arrangement.
Sequence
Keplift will be in between of the Bunker Ship and GIMI so that the bunker hose
(approximately 200 meter) and accessories can be lifted onboard by use of
Keplift and laid upto the Bunker Station at GIMI Onboard Main Deck Port .
Capacity of 5DB Tank is 1600 m3 and plan to bunker 1000 m3 into the tank,
Hence there will be no chance of overflow.
It is to make sure that there will be no hot works at all onboard vessel.
After every hook up & line up has been completed, start the bunker pump at the
tanker to commence bunkering.
The flow rate to be set at minimum at the beginning and check, observe whether
any leak or spillage through out of the bunker line.
Constantly monitor to the activities and communicate among the team for
updated conditions such as tank level, any spillage, weather condition, source of
fire etc.
Once bunkering is completed the preset amount, air blow to be performed into
hose with tanker pump to make sure no residual oil left inside the hose.
Hose will be removed from the tank and lift down to bunker ship after air blow is
completed.
Demobilize the activities and perform specific house keeping.
Location
GOLAR GIMI at Quay-3 and Bunker Ship will be moored at the port alongside of
GIMI
5.3 Access Control: Mechnical Lead (Myat Moe) and In-charge engineer (Sai)
Area Controller
HSE Zeyar / Myat Moe
Hadikul / Hariz 82225287 / 98429095
85338445 / 84827935 Channel 10
Channel 1
Engineers
Jairus / Ronald
86464113 / 90936455
Channel 10
10
OSP NA
P&M NA
Others NA
Walkie-Talkie Channel: 10
6. Emergency Prepareness
7.
6.1 Roles & Responsibilities
11
OSP NA
Walkie-Talkie Channel: 10
7.Management of Change
7
7.1 Clear definition on Condition of Change
In Case of heavy Rain which may affect the visibility, Water ingress and Blackout
during the operation.
13
Walkie-Talkie Channel: 10
14