Professional Documents
Culture Documents
(Record Approval)
Exhaust extension for existing standby AFRIWATT 365 PTY LTD
Nature of the work Principal Contractor Name
generator set
106 York Street, George, Eastern Cape NIL
Contractor, other than the
Principle Contractor,
Site / Building Name
carrying out the work (sub-
contractor)
Location (Indoor / OUTDOOR AREA Planned Start Date TBA Time 08h00
Outdoor Area, Building
Section, Floor, Room, TBA
Planned Finish Date Time
etc.)
Name of appointed Lindiwe Mqweba +27 67 703 4159 Number of 3
Mobile Phone Number
Supervisor on Site Persons
Name(s) of Emergency KEVIN DHAPI Office Telephone or Cell 011 864 2584 / 067 698 5418
Contact Person(s) MUTONDI SADIKI Phone Number 067 699 4139
Name(s) of the Client VONGANI CHIRINDI Office Telephone or Cell
Contact Person(s) Phone Number
Risk Rating
Health and Safety Environmental Business time loss Matrix
Methodology
Catastrophic, Fatality, Loss of limb 80% of the environmental impact is irreversible 1 day or more 3 3 6 9
Severity Lost Time Injury (> 3 days) 60% of the environmental impact is irreversible Less than 1 day 2 2 4 6
First Aid Treatment / Near Miss The environmental impact is fully reversible 1 hour or less 1 1 2 3
Acceptable Risk Control High Risk (4-9) - Supervision, Safe Work Procedure(s), Permit to Work System, as well as the controls listed below 1 Unlikely 2 Likely 3 Certain
Level for Medium and Low Risk. Probability
Medium Risk (2-3) - Competent Workers, Site Risk Assessment and Risk Controls Training.
Low Risk (1) - Method Statement Awareness Training.
Sequence of events
Potential Hazards and Risks Appropriate Controls
Risk Rating (S x P)
Job Step / Task
Probability (P)
Sequence No.:
Severity (S)
Activity / Task
Occupational driving/ driving Poorly maintained or improperly Construction vehicles to be Project manager /
1 onsite handled vehicles can lead to 2 2 4 installed with reverse alarms, Supervisor
crushing injuries onsite and ensure they are functioning on all
collisions. vehicles.
Designate a spotter for direction
and assistance of driver when
driving vehicle onsite
Competent driver of vehicles,
ensure vehicle is fit for purpose
and in good working order – pre-
inspection of vehicles before use
Positioning of truck Unstable or Wet ground and Position the truck on level ground. Operator
2 Uneven surfaces 2 2 4 All the wheels of the truck to be Supervisor
Truck losing balance resulting in chocked and in contact with the
property damage and injuries. ground when the outriggers are set
(suspension not to be completely
unloaded).
Load test certificate for the crane
truck
Driver must have a valid certificate
for operating the crane.
The crane must be inspected prior
to start of work activities
3 Suspended load Equipment can fail unexpectedly, 3 3 9 The work area must be barricaded Operator
and operator errors can have off to avoid public interference. Supervisor
serious ramifications including No one must be under the
Using a ladder Working at height -Fall risk 3 3 9 Fall protection and rescue paln Site Supervisor
10 must be implemented.
Employees must be trained on
SWP for working at heights
Employees must hook up at
heights
Ladders must be inspected prior to
use
SWP for Ladder must be trained on
employees
Vehicles and Mobile Plant Truck mounted crane Equipment to be used Ladder, generator unit,
(Cherry Picker, Back Actor, etc., (Scaffold / Ladder, Compressor, Porta
List Registration Numbers) Pack, Welding Machine, etc.)
Cement, Palisade poles, concrete mix, Chemicals to be used (Paint, oil, Cement, coolant, engine oil, diesel
Materials to be used reinforcement steel, cable, Thinners, etc.)
Safety Signage and Site safety board, No entry, danger – Incident Management ✘ First Aid Kit available on site and adequate
Barricading to be used lifting operations. (Mark the item with an “X” if applicable) ✘ Spillage Kit available on site and adequate
The following records to be submitted as part of the Safe Work Method Statement conditional Site/Team/
Vendor
approval process. Clearly mark “X” in the appropriate block to indicate the location where Portal
Vehicle N/A Specify
documents can be reviewed. SHE File
Certificates of Specialised Equipment e.g. Lifting Equipment / Devices, Slings, etc. ☐ ☒ ☒ ☐ Submit records to ensure
compliance with CR and DMR
18
Company / Supervisor / Technical Staff Competency Records ☐ ☒ ☒ ☐ Qualifications of the Electrical
(e.g. HVAC, Electrical, Fire and Access, Plumbing, Carpentry, Welding, etc.). competent person
Site Supervisor
Fall Protection Plan and Rescue Plan ☐ ☐ ☐ ☒
Legal Appointments (Site Supervisor, Risk Assessor, Fall Protection Planner, First Aider, Rigger, ☐ ☒ ☒ ☐ Supervisory person on site
etc.).
Material Safety Data Sheets for Hazardous Chemical Substances ☐ ☒ ☒ ☐ Diesel, Antifreeze, oil,
(Risk of exposure to the product, e.g. toxic fumes / poisonous / corrosive substances, etc.). sanitiser
Mandatory / Section 37.2 Agreement Signed ☒ ☒ ☐ ☐
Medical Certificates of Fitness (Working at Heights, Suspended Platforms, Cranes, Mobile ☒ ☒ ☐ ☐
Elevated Work Platforms).
Public Liability Insurance / Contractor’s All Risk Insurance ☒ ☐ ☐ ☐
Safe Work Procedures (Working at Heights, Suspended Platforms, Cranes, Mobile Elevated Work ☐ ☒ ☒ ☐ Related to the Project and
Platforms, Electrical and Mechanical Equipment). LOTO
Site Induction (Client / Bidvest Facilities Management / Safe Work Method Statement). ☐ ☒ ☒ ☐ Toolbox for the site
installation
Statutory Training Certificates, e.g. Scaffold Supervisor, Erector and Inspector, Mobile Elevated ☐ ☒ ☐ ☐ Basic Fire Training
Work Platform Operator, Rope Access and Fall Prevention Certificates, etc.). First Aider
Mobile Crane Operator
Valid Letter of Good Standing (Compensation for Occupational Injuries and Diseases Act 130 of ☒ ☒ ☐ ☐
1993)
Vehicles, Mobile Plant and Equipment Inspections as per the list above. ☐ ☒ ☐ ☐
Certificates of Specialised Equipment e.g. Lifting Equipment / Devices, Slings, etc. ☐ ☒ ☒ ☐ Submit records to ensure
compliance with CR and DMR
18
Company Authority Name (I confirm, to the best of my knowledge, that the information above is correct and I will ensure that the prescribed
Confirmation (Designated health, safety and environmental precautions are implemented before work commences on site.)
Contractor Representative) Name: Mutondi Sadiki Designation: 16.2 Signature: Date: 2023 / 06 / 23
Bidvest Facilities Management Authority Name / Permit Issuer (I confirm, to the best of my knowledge, that the above information is
correct and that all prescribed health, safety and environmental precautions have been verified as indicated.
Conditional Approval
Conditional Approval to proceed with the work is subject to the following conditions being implemented by the Designated Contractor
Representative, prior to work commencement on site);
Herewith provide conditional Hand tools, electrical tools, ladders and equipment inspected and in good condition.
approval to proceed with the Personal protective equipment / wear (PPE / PPW) inspected and in good condition.
work, subject All appropriate controls / precautionary measures, related to the Risk Assessment above, implemented.
All employees have received awareness training on the content of this document.
Documentation in the site / team / vehicle Safety, Health and Environment (SHE) file reviewed prior to work commencement.
A Daily Site Risk Control Check (Task Risk Assessment) or Daily Safety Task Instruction (DSTI) conducted and risk controls
implemented.
All conditions of this Permit to Work implemented.
Other, specify:
Name: Designation: Signature: Date:
DESIGNATED CONTRACTOR REPRESENTATIVE TO COMPLETE THE FOLLOWING BEFORE WORK COMMENCEMENT ON SITE
Register and inspection of the condition of hand and electrical tools, ladders, equipment and personal protective equipment / wear (PPE / PPW)
List of critical tools, ladder(s) and Tool Identification Condition Employee Name List of PPE / PPW Condition
equipment Number (Good or Bad) (Good or Bad)
WORK COMPLETION
Designated Contractor Representative (I hereby certify that the work specified in this Safe Work Method Statement has been completed.
In addition, I confirm that:
All persons under my supervision, together with all work materials and equipment have been withdrawn, and that the site has been left clean, tidy, safe and free
of any risks (including fire) for normal work to resume.
The completed Safe Work Method Statement and the attached Daily Site Risk Control Check (Task Risk Assessment) or DSTI will be submitted to the Bidvest
Facilities Management Facilities Manager or Technical Manager for record keeping.
Name: Designation: Signature: Date:
Bidvest Facilities Management Authority Name / Permit Issuer (I confirm, to the best of my knowledge, that the work has been completed, that equipment has
been tested, and that the area is safe and free of risk (including fire) for normal work to resume).