Professional Documents
Culture Documents
Contract
Contractor Name: Project Type:
No.:
6.3 Clean and sweep the ground as Manual handling. Waste materials if not Facilitate training for manual handling.
necessary. properly segregated and Observe proper posture during manual lifting, pushing, pulling, etc.
disposed could cause
environmental
contamination
6.4 Remove tools and materials and Scattered lifting gears (no storage Tools and materials if not Provide storage box for lifting gears.
keep on the designated storage area, etc.), uncoiled web sling or wire properly arranged could All lifting web sling belt and wire rope must be coiled after each
area. rope, etc. cause slip trip and fall day of work.
which results to injury of a
person
Wearing an inadequate
PPE may cause skin
irritation
Waste materials if not
properly segregated and
disposed could cause
environmental
contamination.
7. Closing of Permit to Work
7.1 Returning of the Permit to Work
to Permit Issuer for closing.
7.2 Verifying the site condition as per Poor housekeeping. Significant property and Permit Receiver shall ensure that housekeeping is done before,
requirements mentioned in the Undisposed waste materials. appurtenances damage during and after the work.
closing of Permit to Work by both Unaccounted workers. Governmental violation All waste materials generated from the work shall be properly
the Permit Issuer and Permit Unsecured electrical equipment Environmental complaint disposed and shall not be left unattended at the worksite.
Receiver. /energized equipment. Loss of production Electrical equipment shall be properly secured, distribution board
Poor storage of chemical, flammable Accident resulting serious closed and padlocked.
and combustible materials and etc. injury or death to worker All materials used at the site such as chemicals, flammable and
Unattended unsafe condition. Significant cost due to combustible materials shall be stored at the designated storage at
Unfamiliarity with access to the areas damages. the end of each day.
OHS Forms Procedure Reference Revision Number Revision Date
P a g e | 12 JOB SAFE PROCEDURE OHS-PR-09-03-F07 (A) 0 MAY 2021
HAZARD IDENTIFICATION & RISK ASSESSMENT (HIRA)
OHS-PR-09-03-F07 (A) JOB SAFE PROCEDURE