Contractor Name: Project Type:
No.:
1.2 Attaching all the required Incompetent assigned personnel. Significant property and All the involved personnel dealing with all the required documents
documents such as a related Unidentified or incomplete hazards appurtenances damage shall be qualified, competent and trained.
checklist, risk assessment, and risk information. Safe work practice shall be identified to reduce the possibilities of
method statement and other accidents/incidents.
forms necessary to fulfill the Ensure that all required supporting documents shall be available as
request. per PTW requirements.
All the required related documents as identified to be attached in
PTW shall be reviewed and evaluated by issuer and receiver to
ensure that all hazard and risk is identified and complete.
1.3 Verifying the site condition as per Open areas, protruding sharp objects, Loss of production The workplace shall be pre-checked, free from any obstruction and
requirements mentioned in the falling objects limited illuminations Accident resulting serious in safe good working conditions prior to a combined verification
application of Permit to Work by and other construction hazards may injury or death to worker visit.
both the Permit Receiver and cause accidents during the All Issuer and receiver must be aware of the hazard present in the
Permit Issuer. verification visit. area and must be familiar with the ingress and egress of the
Unfamiliarity with access to the project site.
areas.
1.4 Issuance of approved Permit to Untrained personnel. Significant cost due to Permit Issuer and Receiver must be qualified, trained and
Work from Permit Issuer to Incomplete information on Permit to damages competent.
Permit Receiver. work. Permit Issuer shall ensure that the site was visited to ensure that
workplace hazards and risks are adequately identified and
mitigating measures shall be established.
Permit Issuer and Receiver shall ensure that all the information
required in the permit to work is reviewed, completed and signed.
1.5 Verifying the approved Permit to Inadequate coordination and area Governmental violation Permit to Work shall be displayed at the worksite
Work by the assigned SEC control protocol. Environmental complaint Permit Receiver shall not leave the area for the whole duration of
Consultant. Unauthorized work to be performed permit to work.
within a defined location and Work shall not proceed without the presence of approved PTW
boundary. and the Permit Receiver overseeing the activity.
Permit Receiver shall account all workers under his Permit to Work
before the start of work.
Work shall not be started until duly approved Permit to Work is
available at the site and that Safety Toolbox meeting was
conducted.
3.2 Attachment of lifting gears and Defective lifting gears. Significant cost due to Pre-inspection of all lifting gears to ensure all are in a good and
tackles and tag line onto load to Underrated lifting gears. damages. safe condition.
be lifted. Unqualified personnel doing the Property damage due to Ensure that SWL of all prepared lifting gears is adequate for the
OHS Forms Procedure Reference Revision Number Revision Date
Page |4 JOB SAFE PROCEDURE OHS-PR-09-03-F07 (A) 0 MAY 2021
HAZARD IDENTIFICATION & RISK ASSESSMENT (HIRA)
OHS-PR-09-03-F07 (A) JOB SAFE PROCEDURE
Defective lifting equipment. Property damage due to Only trained and certified rigger shall be assigned for the rigging of
Improper rigging. fall of materials the load.
Miscommunication among team Use tagline to control swaying of the load during lifting and
members. lowering.
Unauthorized personnel. Gradual lifting and lowering of the load to avoid sudden swaying of
the load.
Only trained and certified rigger shall be giving the signal to the
operator to avoid any confusion.
No unauthorized person shall be allowed in the work area.
No person shall be allowed to stay under suspended load at any
time at any circumstances.
5. Pulling of pilot wire by workers especially at plain and high terrain area such as mountains, valley, cliff (Manual Handling)
5.1 Station worker on the cable drum Unqualified personnel. Significant cost due to Assign experienced with know-how knowledge for the task.
of paying out the wire. Lack of proper communication damages. Ensure the established effective mode of communication such as
between team members. Property damage due to radio, etc. between team members.
fall of materials
5.2 Assign an adequate number of Unqualified personnel. Property damage due to Assign experienced personnel for the task.
workers to pull paying out the Inadequate personnel. fall of materials Ensure to assign adequate personnel for the task.
wire. Unfit personnel. Illness due to bad Ensure that assigned personnel are fit for the task.
ergonomics All personnel must undergo a medical examination and have
Injury due to Slip, Trip and medical clearance for the task.
fall on the same level
5.3 Start pulling the wire while Ergonomics (repetitive movement). Muscular injuries (Back Rotation of workers to limit exposure to prolonged repetitive
releasing from the drum Exposure to sharp material. pain, strain, fractures) movement.
gradually. Exposure to dust. Heat Stress (stroke, cramps, All personnel must be equipped with appropriate PPEs such as (list
Adverse weather conditions. skin rashes etc.) all applicable PPEs for the task).
irritation to the eyes, skin Continuous monitoring of weather conditions.
and respiratory tract Work shall be suspended in case of inclement weather conditions.
Provision of sufficient breaks and rehydrating drinks for all
personnel.
Provision of resting shelter for all personnel.
6. Pulling of pilot wire by using the vehicle and payloader
8.4 Sweeping and cleaning the area. Inadequate PPE Hand injuries due to Appropriate personal protective equipment should be observed
Presence of waste material contact with sharp tools like coverall, hand gloves, eye protection, and etc.
Inappropriate tools and objects Observe the “use the right tool” rule.
Slip and trip Close supervision by the Engineer, Supervisor or Foreman must
observe.
9. Closing of Permit to Work
9.1 Returning of the Permit to Work
to Permit Issuer for closing.
9.2 Verifying the site condition as per Poor housekeeping. Environmental complaint Permit Receiver shall ensure that housekeeping is done before,
requirements mentioned in the Undisposed waste materials. Accident resulting serious during and after the work.
closing of Permit to Work by both Unaccounted workers. injury or death to worker All waste materials generated from the work shall be properly
the Permit Issuer and Permit Unsecured electrical equipment Governmental violation disposed of and shall not be left unattended at the worksite.
Receiver. /energized equipment. Accident resulting serious Electrical equipment shall be properly secured, distribution board
Poor storage of chemical, flammable injury or death to worker closed and padlocked.
and combustible materials and etc. Significant cost due to All materials used at the site such as chemicals, flammable and
Unattended unsafe condition. damages combustible materials shall be stored at the designated storage at
Unfamiliarity with access to the areas the end of each day.
and the present construction hazard. Mobile equipment shall properly park on a designated equipment
laydown.
Ensure that all workers are accounted and there was no
OHS Forms Procedure Reference Revision Number Revision Date
Page |9 JOB SAFE PROCEDURE OHS-PR-09-03-F07 (A) 0 MAY 2021
HAZARD IDENTIFICATION & RISK ASSESSMENT (HIRA)
OHS-PR-09-03-F07 (A) JOB SAFE PROCEDURE