Professional Documents
Culture Documents
INDIRECT LABOUR
A Management
1 Project Manager
2 Site Manager
3 Project Control
4 Material Control
5 GA & Finance
6 HSE
7 Engineering
8 Drafter
Sub-total Indirect Labour
DIRECT LABOUR
1 Supervisor
2 Surveyor
3 Operator
4 QC Inspector
5 Mekanik
6 Admin & Logistik
7 Tukang Batu
8 Tukang Kayu
9 Tukang Besi
10 Security
11 Office Boy
12 Helper
Sub-total Indirect Labour
TOTAL
e Disign Engineering
f Safety Expense
Note:
1.
2.
3.
(...................................................) (.................................
LN (Persero)
ucofindo
& EQUIPMENTS
QTY Total QTY Terpakai
REMARK
9:00 10:00 11:00 12:00
...............................)
RELOKASI PLTMG RAWA MINYAK - SIAK
PROJECT CONSTRUCTION ACTIVITY
DAILY ACTIVITIES REPORT
LAND DEVELOPMENT (Cut & Fill)
Number : No. Contract :
Date : Employer : PT. PLN (Persero
Sub-Contractor : PT. Maharani Prima Supervisi : PT. Sucofindo
Contractor : PT. Wika - KSO
INDIRECT LABOUR
A Management
1 Project Manager
2 Site Manager
3 Project Control
4 Material Control
5 GA & Finance
6 HSE
7 Engineering
8 Drafter
Sub-total Indirect Labour
DIRECT LABOUR
1 Supervisor
2 Surveyor
3 Operator
4 QC Inspector
5 Mekanik
6 Admin & Logistik
7 Tukang Batu
8 Tukang Kayu
9 Tukang Besi
10 Security
11 Office Boy
12 Helper
Sub-total Indirect Labour
TOTAL
Today Activities
NO WORKS ACTIVITY
Today Cumulative Unit
a Perataan Lahan
b Timbunan Tanah
c Pasangan Batu
Note:
1.
2.
3.
(...................................................) (....................................
ersero)
ndo
UIPMENTS
QTY Total QTY Terpakai
REMARK
9:00 10:00 11:00 12:00
.......................)
RELOKASI PLTMG RAWA MINYAK - SIAK
PROJECT CONSTRUCTION ACTIVITY
DAILY ACTIVITIES REPORT
PONDASI MESIN (Engine Foundation)
Number : No. Contract :
Date : Employer : PT. PLN (Persero
Sub-Contractor : PT. Maharani Prima Supervisi : PT. Sucofindo
Contractor : PT. Wika - KSO
INDIRECT LABOUR
A Management
1 Project Manager
2 Site Manager
3 Project Control
4 Material Control
5 GA & Finance
6 HSE
7 Engineering
8 Drafter
Sub-total Indirect Labour
DIRECT LABOUR
1 Supervisor
2 Surveyor
3 Operator
4 QC Inspector
5 Mekanik
6 Admin & Logistik
7 Tukang Batu
8 Tukang Kayu
9 Tukang Besi
10 Security
11 Office Boy
12 Helper
Sub-total Indirect Labour
TOTAL
Today Activities
NO WORKS ACTIVITY
Today Cumulative Unit
Note:
1.
2.
3.
(...................................................) (....................................
ersero)
ndo
UIPMENTS
QTY Total QTY Terpakai
REMARK
9:00 10:00 11:00 12:00
.......................)
RELOKASI PLTMG RAWA MINYAK - SIAK
PROJECT CONSTRUCTION ACTIVITY
DAILY ACTIVITIES REPORT
PONDASI TRAFORMER
Number : No. Contract :
Date : Employer : PT. PLN (Persero
Sub-Contractor : PT. Maharani Prima Supervisi : PT. Sucofindo
Contractor : PT. Wika - KSO
Today Activities
NO WORKS ACTIVITY
Today Cumulative Unit
Note:
1.
2.
3.
(...................................................) (....................................
ersero)
ndo
UIPMENTS
QTY Total QTY Terpakai
REMARK
9:00 10:00 11:00 12:00
.......................)
RELOKASI PLTMG RAWA MINYAK - SIAK
PROJECT CONSTRUCTION ACTIVITY
DAILY ACTIVITIES REPORT
RUANG KONTROL (Control Room)
Number : No. Contract :
Date : Employer : PT. PLN (Persero
Sub-Contractor : PT. Maharani Prima Supervisi : PT. Sucofindo
Contractor : PT. Wika - KSO
INDIRECT LABOUR
A Management
1 Project Manager
2 Site Manager
3 Project Control
4 Material Control
5 GA & Finance
6 HSE
7 Engineering
8 Drafter
Sub-total Indirect Labour
DIRECT LABOUR
1 Supervisor
2 Surveyor
3 Operator
4 QC Inspector
5 Mekanik
6 Admin & Logistik
7 Tukang Batu
8 Tukang Kayu
9 Tukang Besi
10 Security
11 Office Boy
12 Helper
Sub-total Indirect Labour
TOTAL
Today Activities
NO WORKS ACTIVITY
Today Cumulative Unit
Note:
1.
2.
3.
(...................................................) (....................................
ersero)
ndo
UIPMENTS
QTY Total QTY Terpakai
REMARK
9:00 10:00 11:00 12:00
.......................)
RELOKASI PLTMG RAWA MINYAK - SIAK
PROJECT CONSTRUCTION ACTIVITY
DAILY ACTIVITIES REPORT
RUANG ADMIN (Admin Room)
Number : No. Contract :
Date : Employer : PT. PLN (Persero
Sub-Contractor : PT. Maharani Prima Supervisi : PT. Sucofindo
Contractor : PT. Wika - KSO
INDIRECT LABOUR
A Management
1 Project Manager
2 Site Manager
3 Project Control
4 Material Control
5 GA & Finance
6 HSE
7 Engineering
8 Drafter
Sub-total Indirect Labour
DIRECT LABOUR
1 Supervisor
2 Surveyor
3 Operator
4 QC Inspector
5 Mekanik
6 Admin & Logistik
7 Tukang Batu
8 Tukang Kayu
9 Tukang Besi
10 Security
11 Office Boy
12 Helper
Sub-total Indirect Labour
TOTAL
Today Activities
NO WORKS ACTIVITY
Today Cumulative Unit
Note:
1.
2.
3.
(...................................................) (....................................
ersero)
ndo
UIPMENTS
QTY Total QTY Terpakai
REMARK
9:00 10:00 11:00 12:00
.......................)
RELOKASI PLTMG RAWA MINYAK - SIAK
PROJECT CONSTRUCTION ACTIVITY
DAILY ACTIVITIES REPORT
WEREHOUSE
Number : No. Contract :
Date : Employer : PT. PLN (Persero
Sub-Contractor : PT. Maharani Prima Supervisi : PT. Sucofindo
Contractor : PT. Wika - KSO
INDIRECT LABOUR
A Management
1 Project Manager
2 Site Manager
3 Project Control
4 Material Control
5 GA & Finance
6 HSE
7 Engineering
8 Drafter
Sub-total Indirect Labour
DIRECT LABOUR
1 Supervisor
2 Surveyor
3 Operator
4 QC Inspector
5 Mekanik
6 Admin & Logistik
7 Tukang Batu
8 Tukang Kayu
9 Tukang Besi
10 Security
11 Office Boy
12 Helper
Sub-total Indirect Labour
TOTAL
Today Activities
NO WORKS ACTIVITY
Today Cumulative Unit
Note:
1.
2.
3.
(...................................................) (....................................
ersero)
ndo
UIPMENTS
QTY Total QTY Terpakai
REMARK
9:00 10:00 11:00 12:00
.......................)
RELOKASI PLTMG RAWA MINYAK - SIAK
PROJECT CONSTRUCTION ACTIVITY
DAILY ACTIVITIES REPORT
WATER TANK AND OIL SHELSET WATER TANK
Number : No. Contract :
Date : Employer : PT. PLN (Persero
Sub-Contractor : PT. Maharani Prima Supervisi : PT. Sucofindo
Contractor : PT. Wika - KSO
INDIRECT LABOUR
A Management
1 Project Manager
2 Site Manager
3 Project Control
4 Material Control
5 GA & Finance
6 HSE
7 Engineering
8 Drafter
Sub-total Indirect Labour
DIRECT LABOUR
1 Supervisor
2 Surveyor
3 Operator
4 QC Inspector
5 Mekanik
6 Admin & Logistik
7 Tukang Batu
8 Tukang Kayu
9 Tukang Besi
10 Security
11 Office Boy
12 Helper
Sub-total Indirect Labour
TOTAL
Today Activities
NO WORKS ACTIVITY
Today Cumulative Unit
Note:
1.
2.
3.
(...................................................) (....................................
ersero)
ndo
UIPMENTS
QTY Total QTY Terpakai
REMARK
9:00 10:00 11:00 12:00
.......................)
RELOKASI PLTMG RAWA MINYAK - SIAK
PROJECT CONSTRUCTION ACTIVITY
DAILY ACTIVITIES REPORT
CIVIL WORK
Number : No. Contract :
Date : Employer : PT. PLN (Perse
Sub-Contractor : PT. Maharani Prima Supervisi : PT. Sucofindo
Contractor : PT. Wika - KSO
INDIRECT LABOUR
A Management
1 Project Manager
2 Site Manager
3 Project Control
4 Material Control
5 GA & Finance
6 HSE
7 Engineering
8 Drafter
Sub-total Indirect Labour
DIRECT LABOUR
1 Supervisor
2 Surveyor
3 Operator
4 QC Inspector
5 Mekanik
6 Admin & Logistik
7 Tukang Batu
8 Tukang Kayu
9 Tukang Besi
10 Security
11 Office Boy
12 Helper
Sub-total Indirect Labour
TOTAL
Today Activities
NO WORKS ACTIVITY
Today Cumulative Unit
Note:
1.
2.
3.
(...................................................) (...................................
G RAWA MINYAK - SIAK
STRUCTION ACTIVITY
VITIES REPORT
IL WORK
:
: PT. PLN (Persero)
: PT. Sucofindo
REMARK
9:00 10:00 11:00 12:00
(...................................................)