PAYMENT SCHEDULE FOR SUZLON SITE No.

s of WTG Cost Per WTG (Rs in Lac) Total Cost of Project (Rs in Lac) Bifurcations of payment 25% 35% 15% 10% 10% 5% 100% 5 1120 5600 Valekarwadi Amount (Rs in Lac) 1400 1960 840 560 560 280 5600 Date 2-Jul-2011 1-Mar-2012 3-Mar-2012 22-Feb-2012 27-Mar-2012 31-Mar-2012

Sl/no 1 2 3 4 5 6

Particulars Advance & Purchase Order Nacelle Delivery Complete Rotor Blades Delivery Tower Delivery Erecting of Mech, Elect & Civil Works WTG Erecting upon Commissioning Total

UZLON SITE 12 1120 13440 Jasdan Amount (Rs in Lac) 3360 4704 2016 1344 1344 672 13440 Date 2-Jul-2011 14-Nov-2011 14-Nov-2011 14-Nov-2011 14-Dec-2011 3-Jan-2012

PAYMENT SCHEDULE FOR REGEN SITE No.s of WTG Supply (Rs in Lac) Erectioning & Commissioning (Rs in Lac) Land (Rs in Lac) Cost Per WTG (Rs in Lac) Total NCV (Rs in Lac) Bifurcations of payment 1% 19% 32.50% 13% 13% 7% 10% 5% 100% 33 845 60 40 945 31185 Peth Shivpur Amount (Rs in Lac) 312 5925 10135 4054 4054 2027 3119 1559 31185

Particulars 1 2 3 4 5 6 7 8 Sl/no 1 2 3 4 5 6 7 8 LOI Payment (1% of NCV) Advance Payment (19 % of NCV) Payment Nacelle Delivery Against Blades Delivery material Tower Delivery Receipt Hub & Control Delivery Commissioning of WTGs Commissioning n Statutory Compliance TOTAL

E FOR REGEN SITE 33 845 60 40 945 31185 Peth Shivpur Date 1-Feb-2011 9-Apr-2012 11-Apr-2012 4-Apr-2012 9-Apr-2012 15-Jun-2012 29-Jun-2012