You are on page 1of 63

DAILY PROGRESS REPORT for 10 MW PV PL Cloudy weather throughout day.

Report for Day

8/1/2013
TOTAL Qty Sch. Date Activity of Start date completio as per L2 n as per Sch L2

(A).

SITE PREPARATION WORK :

Unit

(1). (2). (3).

Tree felling Tree logging & delivering to NTPC Removal of roots from ground

Nos Tractor Nos

331 331 331

(B). (1). (2). (3). (4). (4). (C.) (D) (D.) (G). (H). (I).

FENCING : Trench excavation Bottom PCC Brick Work below GL Brick Work above GL Fencing with chain link Land leveling

Meter Meter Meter Metre Meter Acres

3150 3150 3150 3150 3150

Temporary Main Road preparation Meter Pile foundation Nos

125 10560

Module Support Structure mounting Nos Fitting Modules on structures Module series cabling till JB Nos Nos 42240 3520

SS REPORT for 10 MW PV PLANT NTPC UNCHAHAR

oughout day.

Cumulativ Qty Actual e Target for Complete start date complete tomorrow d today d 0 1 0 338 331 0 4

Remarks

Activity completed on 21-07-13 Activity completed on 27-07-13 Total qty unknown due to earlier cut trees.

0 0 0 0

317.5 317.5 317.5 317.5

No work possible due to soil conditions.

De-watering done. Surveying to be done WBM laying under progress. After land leveling

After pile foundation After structure fixing Aftter module fitting

DAILY PROGRESS REPORT for 10 MW PV PLANT NT

Weather Details : Rain from 6:00PM to 6:30PM


Report for Day

8/2/2013
SITE PREPARATION WORK : Unit TOTAL Qty 331 Sch. Date Activity of Start date completio as per L2 n as per Sch L2

(A).

(1). (2). (3).

Tree felling Tree logging & delivering to NTPC Removal of roots from ground

Nos Tractor Nos

(4).

Disposal of roots

Nos.

(B). (1). (2). (3). (4). (4). (C.) (D) (D.) (G). (H). (I).

FENCING : Trench excavation Bottom PCC Brick Work below GL Brick Work above GL Fencing with chain link Land leveling Temporary Main Road preparation Pile foundation Module Support Structure mounting Fitting Modules on structures Module series cabling till JB

Meter Meter Meter Metre Meter Acres Meter Nos Nos Nos Nos

3150 3150 3150 3150 3150

125 10560

42240 3520

RT for 10 MW PV PLANT NTPC UNCHAHAR

ain from 6:00PM to 6:30PM. Cloudy weather throughout day.


Cumulativ Qty Actual e Target for Complete start date complete tomorrow d today d 0 331 0

Remarks

Activity completed on 21-07-13 Activity completed on 27-07-13

338

Total qty unknown due to earlier cut trees. 30 Total qty unknown due to earlier cut trees. Total roots pending to be disposed shall be provided.

22

0 0 0 0

317.5 317.5 317.5 317.5

No work possible due to soil conditions.

De-watering done. Surveying to be done tomorrow. WBM laying under progress. After land leveling

After pile foundation After structure fixing Aftter module fitting

DAILY PROGRESS REPORT for 10 MW P

Weather Details : Rain from 8:00PM


Report for Day

8/3/2013
TOTAL Qty Activity Start date as per L2 Sch

(A).

SITE PREPARATION WORK :

Unit

(1). (2).

Tree felling Tree logging & delivering to NTPC

Nos Tractor

331

(3).

Removal of roots from ground

Nos

(4).

Disposal of roots

Nos.

(B). (1). (2). (3). (4). (4).

FENCING : Trench excavation Bottom PCC Brick Work below GL Brick Work above GL Fencing with chain link

Meter Meter Meter Metre Meter

3150 3150 3150 3150 3150

(C.)

Land leveling

Acres

(D) (D.) (G). (H). (I).

Temporary Main Road preparation Pile foundation Module Support Structure mounting Fitting Modules on structures Module series cabling till JB

Meter Nos Nos Nos Nos

125 10560

42240 3520

SS REPORT for 10 MW PV PLANT NTPC UNCHAHAR

etails : Rain from 8:00PM to 10:30PM. Cloudy weather throughout day.

Sch. Date of Qty Actual Cumulative Target for completion Complete start date completed tomorrow as per L2 d today 0 331 0

Remarks

Activity completed on 21-07-13 Activity completed on 27-07-13 Total qty unknown due to earlier cut trees.

338

22

50

Total qty unknown due to earlier cut trees. Total roots pending to be disposed shall be provided.

0 0 0 0

317.5 317.5 317.5 317.5

No work possible due to soil conditions.

1)Machinary mobilised at site. Temporary approach road for tractor movement to be started tomorrow.2) Surveyors arrived at site to verify and mark the coordinates. WBM laying under progress. After land leveling

After pile foundation After structure fixing Aftter module fitting

DAILY PROGRESS REPORT for

Weather Details : Cloudy weather throug


Report for Day (A). (1). (2).

8/4/2013
SITE PREPARATION WORK : Tree felling Tree logging & delivering to NTPC Unit Nos Tractor TOTAL Qty 331 Activity Start date as per L2 Sch

(3).

Removal of roots from ground

Nos

(4).

Disposal of roots

Nos.

(B). (1). (2). (3). (4). (4).

FENCING : Trench excavation Bottom PCC Brick Work below GL Brick Work above GL Fencing with chain link

Meter Meter Meter Metre Meter

3150 3150 3150 3150 3150

(C.)

Land leveling

Acres

(D) (D.) (G). (H). (I).

Temporary Main Road preparation Pile foundation Module Support Structure mounting Fitting Modules on structures Module series cabling till JB

Meter Nos Nos Nos Nos

125 10560

42240 3520

PROGRESS REPORT for 10 MW PV PLANT NTPC UNCHAHAR Cloudy weather throughout day.
Sch. Date of Actual start completion date as per L2 Qty Completed today 0 Cumulative completed 331 Target for tomorrow 0

338

50

50

0 0 0 0

317.5 317.5 317.5 317.5

Remarks Activity completed on 21-07-13 Activity completed on 27-07-13

Total qty unknown due to earlier cut trees. Total qty unknown due to earlier cut trees. Total roots pending to be disposed shall be provided.

No work possible due to soil conditions.

1)Machinary could not work due to slushy soil conditions.2)Dozer to be mobilised tomorrow for road formation.

WBM laying under progress. After land leveling

After pile foundation After structure fixing Aftter module fitting

DAILY PROGRESS REPORT for 10 MW PV PLA

Weather Details : Cloudy weather through


Report for Day

8/5/2013
Activity Start date as per L2 Sch

(A).

SITE PREPARATION WORK :

Unit

TOTAL Qty

(1). (2). (3).

Tree felling Tree logging & delivering to NTPC Removal of roots from ground

Nos Tractor Nos

331

(4).

Disposal of roots

Nos.

(B). (1). (2). (3). (4). (4).

FENCING : Trench excavation Bottom PCC Brick Work below GL Brick Work above GL Fencing with chain link

Meter Meter Meter Metre Meter

3150 3150 3150 3150 3150

(C.)

Land leveling

Acres

(D) (D.) (G). (H). (I).

Temporary Main Road preparation Pile foundation Module Support Structure mounting Fitting Modules on structures Module series cabling till JB

Meter Nos Nos Nos Nos

125 10560

42240 3520

ESS REPORT for 10 MW PV PLANT NTPC UNCHAHAR

ails : Cloudy weather throughout day.

Cumulativ Sch. Date of Qty Actual e Target for completion Complete start date complete tomorrow as per L2 d today d 0 331 0

Remarks

Activity completed on 21-07-13 Activity completed on 27-07-13

338

Total qty unknown due to earlier cut trees. Total qty unknown due to earlier cut trees. Total roots pending to be disposed shall be provided.

22

25

0 0 0 0

317.5 317.5 317.5 317.5

No work possible due to soil conditions.

1)Machinary could not work due to slushy soil conditions.2)Dozer to be mobilised tomorrow for road formation. WBM laying under progress. After land leveling

After pile foundation After structure fixing Aftter module fitting

DAILY PROGRESS REPORT for 10 MW PV PLANT

Weather Details : Rain came at 5AM to 8AM


Report for Day

8/6/2013
TOTAL Qty Sch. Date Activity of Start date completio as per L2 n as per Sch L2

(A).

SITE PREPARATION WORK :

Unit

(1). (2).

Tree felling Tree logging & delivering to NTPC

Nos Tractor

331

(3).

Removal of roots from ground

Nos

(4).

Disposal of roots

Nos.

(B). (1). (2). (3). (4). (4).

FENCING : Trench excavation Bottom PCC Brick Work below GL Brick Work above GL Fencing with chain link

Meter Meter Meter Metre Meter

3150 3150 3150 3150 3150

(C.)

Land leveling

Acres

(D) (D.) (G). (H). (I).

Temporary Main Road preparation Pile foundation Module Support Structure mounting Fitting Modules on structures Module series cabling till JB

Meter Nos Nos Nos Nos

125 10560

42240 3520

RT for 10 MW PV PLANT NTPC UNCHAHAR

ain came at 5AM to 8AM.Cloudy weather throughout day.

Cumulativ Qty Actual e Target for Complete start date complete tomorrow d today d 0 331 0

Remarks

Activity completed on 21-07-13 Activity completed on 27-07-13 Total qty unknown due to earlier cut trees. Total qty unknown due to earlier cut trees. Total roots pending to be disposed shall be provided.

338

16

15

0 0 0 0

317.5 317.5 317.5 317.5

No work possible due to soil conditions.

1)Machinary could not work due to slushy soil conditions.2)Dozer to be mobilised tomorrow for road formation. WBM laying under progress. After land leveling

After pile foundation After structure fixing Aftter module fitting

DAILY PROGRESS REPORT for 10 MW PV PLANT NTP Weather Details : Rain came at 4PM to 6PM.Cloudy
Report for Day

8/7/2013
SITE PREPARATION WORK : Unit TOTAL Qty 331 Sch. Date Activity of Start date Actual completio as per L2 start date n as per Sch L2

(A).

(1). (2). (3).

Tree felling Tree logging & delivering to NTPC Removal of roots from ground

Nos Tractor Nos

(4).

Disposal of roots

Nos.

(B). (1). (2). (3). (4). (4).

FENCING : Trench excavation Bottom PCC Brick Work below GL Brick Work above GL Fencing with chain link

Meter Meter Meter Metre Meter

3150 3150 3150 3150 3150

(C.)

Land leveling

Acres

(D) (D.) (G). (H). (I).

Temporary Main Road preparation Meter Pile foundation Nos

125 10560

Module Support Structure mounting Nos Fitting Modules on structures Module series cabling till JB Nos Nos 42240 3520

10 MW PV PLANT NTPC UNCHAHAR

t 4PM to 6PM.Cloudy weather throughout day.


Cumulativ Qty e Target for Complete complete tomorrow d today d 0 331 0

Remarks

Activity completed on 21-07-13 Activity completed on 27-07-13

338

Total qty unknown due to earlier cut trees. 7 Total qty unknown due to earlier cut trees. Total roots pending to be disposed shall be provided.

10

0 0 0 0

317.5 317.5 317.5 317.5

No work possible due to soil conditions.

1)Machinary could not work due to slushy soil conditions and water logging. WBM laying under progress. After land leveling

After pile foundation After structure fixing Aftter module fitting

DAILY PROGRESS REPORT for 10 MW PV PLANT NTPC U

Weather Details : Rain came at 5AM to 7AM.Cloud


Report for Day

8/8/2013
SITE PREPARATION WORK : Unit TOTAL Qty Sch. Date Activity of Start date Actual completio as per L2 start date n as per Sch L2

(A).

(1). (2). (3). (4).

Tree felling Tree logging & delivering to NTPC Removal of roots from ground Disposal of roots

Nos Tractor Nos Nos.

331

(B). (1). (2). (3). (4). (4).

FENCING : Trench excavation Bottom PCC Brick Work below GL Brick Work above GL Fencing with chain link

Meter Meter Meter Metre Meter

3150 3150 3150 3150 3150

(C.)

Land leveling

Acres

(D) (D.) (G). (H). (I).

Temporary Main Road preparation Meter Pile foundation Nos

125 10560

Module Support Structure mounting Nos Fitting Modules on structures Module series cabling till JB Nos Nos 42240 3520

MW PV PLANT NTPC UNCHAHAR

t 5AM to 7AM.Cloudy weather throughout day.


Cumulativ Qty e Target for Complete complete tomorrow d today d 0 331 0

Remarks

Activity completed on 21-07-13 Activity completed on 27-07-13

338 0 7

Total qty unknown due to earlier cut trees. Total qty unknown due to earlier cut trees. Total roots pending to be disposed shall be provided.

0 0 0 0

317.5 317.5 317.5 317.5

No work possible due to soil conditions.

1)Machinary could not work due to slushy soil conditions and water logging. WBM laying under progress. After land leveling

After pile foundation After structure fixing Aftter module fitting

DAILY PROGRESS REPORT for 10 MW PV PLANT NTP

Weather Details : Rain at 7AM to 8:30AM & 12PM t


Report for Day

8/9/2013
SITE PREPARATION WORK : Unit TOTAL Qty 331 Sch. Date Activity of Start date Actual completio as per L2 start date n as per Sch L2

(A).

(1). (2). (3).

Tree felling

Nos

Tree logging & delivering to NTPC Tractor Removal of roots from ground Nos

(4).

Disposal of roots

Nos.

(B). (1). (2). (3). (4). (4).

FENCING : Trench excavation Bottom PCC Brick Work below GL Brick Work above GL Fencing with chain link

Meter Meter Meter Metre Meter

3150 3150 3150 3150 3150

(C.)

Land leveling

Acres

(D) (D.) (G). (H). (I).

Temporary Main Road preparationMeter Pile foundation Nos

125 10560

Module Support Structure mounting Nos Fitting Modules on structures Module series cabling till JB Nos Nos 42240 3520

10 MW PV PLANT NTPC UNCHAHAR

M to 8:30AM & 12PM to 1 PM.Cloudy weather throughout day.


Cumulativ Qty e Target for Complete complete tomorrow d today d 0 331 0

Remarks

Activity completed on 21-07-13 Activity completed on 27-07-13

338

Total qty unknown due to earlier cut trees. 7 Total qty unknown due to earlier cut trees. Total roots pending to be disposed shall be provided.

0 0 0 0

317.5 317.5 317.5 317.5

No work possible due to soil conditions.

1)Machinary could not work due to slushy soil conditions and more water logging. WBM laying under progress. After land leveling

After pile foundation After structure fixing Aftter module fitting

DAILY PROGRESS REPORT for 10 MW PV PLANT NTPC

Weather Details :intermittent drizzling throughou


Report for Day

8/10/2013
SITE PREPARATION WORK : Unit TOTAL Qty 331 Sch. Date Activity of Start date completio as per L2 n as per Sch L2

(A).

(1). (2). (3).

Tree felling Tree logging & delivering to NTPC Removal of roots from ground

Nos Tractor Nos

(4).

Disposal of roots

Nos.

(B). (1). (2). (3). (4). (4).

FENCING : Trench excavation Bottom PCC Brick Work below GL Brick Work above GL Fencing with chain link

Meter Meter Meter Metre Meter

3150 3150 3150 3150 3150

(C.)

Land leveling

Acres

(D) (D.) (G). (H). (I).

Temporary Main Road preparation Meter Pile foundation Nos

125 10560

Module Support Structure mounting Nos Fitting Modules on structures Module series cabling till JB Nos Nos 42240 3520

RT for 10 MW PV PLANT NTPC UNCHAHAR

ermittent drizzling throughout the day.


Cumulativ Qty Actual e Target for Complete start date complete tomorrow d today d 0 331 0

Remarks

Activity completed on 21-07-13 Activity completed on 27-07-13

338

Total qty unknown due to earlier cut trees. Total qty unknown due to earlier cut trees. Total roots pending to be disposed shall be provided.

17

0 0 0 0

317.5 317.5 317.5 317.5

No work possible due to soil conditions.

Machinary could not work due to slushy soil conditions and water logging. WBM laying under progress. After land leveling

After pile foundation After structure fixing Aftter module fitting

DAILY PROGRESS REPORT for 10 MW PV PLANT NTPC U Weather Details : Cloudy weather throughout day.
Report for Day

8/11/2013
SITE PREPARATION WORK : Unit TOTAL Qty Sch. Date Activity of Start date Actual completio as per L2 start date n as per Sch L2

(A).

(1). (2). (3).

Tree felling

Nos

331

Tree logging & delivering to NTPC Tractor Removal of roots from ground Nos

(4).

Disposal of roots

Nos.

(B). (1). (2). (3). (4). (4).

FENCING : Trench excavation Bottom PCC Brick Work below GL Brick Work above GL Fencing with chain link

Meter Meter Meter Metre Meter

3150 3150 3150 3150 3150

(C.)

Land leveling

Acres

(D) (D.) (G). (H). (I).

Temporary Main Road preparation Meter Pile foundation Nos

125 10560

Module Support Structure mounting Nos Fitting Modules on structures Module series cabling till JB Nos Nos 42240 3520

0 MW PV PLANT NTPC UNCHAHAR

her throughout day.


Cumulativ Qty e Target for Complete complete tomorrow d today d 0 331 0

Remarks

Activity completed on 21-07-13 Activity completed on 27-07-13

338

Total qty unknown due to earlier cut trees. 17 Total qty unknown due to earlier cut trees. Total roots pending to be disposed shall be provided.

0 0 0 0

317.5 317.5 317.5 317.5

No work possible due to soil conditions.

Machinary could not work due to slushy soil conditions and more water logging. WBM laying under progress. After land leveling

After pile foundation After structure fixing Aftter module fitting

DAILY PROGRESS REPORT for 10 MW PV PLANT NTPC U

Weather Details :cloudy weather throughout the da


Report for Day

8/12/2013
SITE PREPARATION WORK : Unit TOTAL Qty 331 Sch. Date Activity of Start date Actual completio as per L2 start date n as per Sch L2

(A).

(1). (2). (3).

Tree felling

Nos

Tree logging & delivering to NTPC Tractor Removal of roots from ground Nos

(4).

Disposal of roots

Nos.

(B). (1). (2). (3). (4). (4).

FENCING : Trench excavation Bottom PCC Brick Work below GL Brick Work above GL Fencing with chain link

Meter Meter Meter Metre Meter

3150 3150 3150 3150 3150

(C.)

Land leveling

Acres

(D) (D.) (G). (H). (I).

Temporary Main Road preparationMeter Pile foundation Nos

125 10560

Module Support Structure mounting Nos Fitting Modules on structures Module series cabling till JB Nos Nos 42240 3520

MW PV PLANT NTPC UNCHAHAR

her throughout the day.


Cumulativ Qty e Target for Complete complete tomorrow d today d 0 331 0

Remarks

Activity completed on 21-07-13 Activity completed on 27-07-13

338

Total qty unknown due to earlier cut trees. 18 Total qty unknown due to earlier cut trees. Total roots pending to be disposed shall be provided.

0 0 0 0

317.5 317.5 317.5 317.5

No work possible due to soil conditions.

For storing the PV modules,50x20sq.m. ground leveling has started near Muslim Grave yard area. WBM laying under progress. After land leveling

After pile foundation After structure fixing Aftter module fitting

DAILY PROGRESS REPORT for 10 MW PV PLANT NTPC U

Weather Details : Sunny day till 4:00PM. Rain at 6:


Report for Day

8/13/2013
SITE PREPARATION WORK : Unit TOTAL Qty Sch. Date Activity of Start date completio as per L2 n as per Sch L2

(A).

(1). (2). (3).

Tree felling Tree logging & delivering to NTPC Removal of roots from ground

Nos Tractor Nos

331

(4).

Disposal of roots

Nos.

(B). (1). (2). (3). (4). (4).

FENCING : Trench excavation Bottom PCC Brick Work below GL Brick Work above GL Fencing with chain link

Meter Meter Meter Metre Meter

3150 3150 3150 3150 3150

(C.)

Land leveling

Acres

(D) (D.) (G). (H). (I).

Temporary Main Road preparation Meter Pile foundation Nos

125 10560

Module Support Structure mounting Nos Fitting Modules on structures Module series cabling till JB Nos Nos 42240 3520

RT for 10 MW PV PLANT NTPC UNCHAHAR

nny day till 4:00PM. Rain at 6:00PM.


Cumulativ Qty Actual e Target for Complete start date complete tomorrow d today d 0 331 0

Remarks

Activity completed on 21-07-13 Activity completed on 27-07-13

338

Total qty unknown due to earlier cut trees. Total qty unknown due to earlier cut trees. Total roots pending to be disposed shall be provided.

18

0 0 0 0

317.5 317.5 317.5 317.5

No work possible due to soil conditions.

For storing the PV modules,50x20sq.m. ground leveling has started near Muslim Grave yard area. WBM laying under progress. After land leveling

After pile foundation After structure fixing Aftter module fitting

DAILY PROGRESS REPORT for 10 MW PV PLANT NTPC UN

Weather Details : Intermittent drizzling & cloudy weat


Report for Day

8/14/2013
SITE PREPARATION WORK : Unit TOTAL Qty 331 Sch. Date Activity of Start date Actual completio as per L2 start date n as per Sch L2

(A).

(1). (2). (3).

Tree felling Tree logging & delivering to NTPC Removal of roots from ground

Nos Tractor Nos

(4).

Disposal of roots

Nos.

(B). (1). (2). (3). (4). (4).

FENCING : Trench excavation Bottom PCC Brick Work below GL Brick Work above GL Fencing with chain link

Meter Meter Meter Metre Meter

3150 3150 3150 3150 3150

(C.)

Land leveling

Acres

(D) (D.) (G). (H). (I).

Temporary Main Road preparation Meter Pile foundation Nos

125 10560

Module Support Structure mountingNos Fitting Modules on structures Module series cabling till JB Nos Nos 42240 3520

MW PV PLANT NTPC UNCHAHAR

t drizzling & cloudy weather throughout the day.


Cumulativ Qty e Target for Complete complete tomorrow d today d 0 331 0

Remarks

Activity completed on 21-07-13 Activity completed on 27-07-13

338

Total qty unknown due to earlier cut trees. 18 Total qty unknown due to earlier cut trees. Total roots pending to be disposed shall be provided.

0 0 0 0

317.5 317.5 317.5 317.5

No work possible due to soil conditions.

For storing the PV modules,50x20sq.m. ground leveling has started near Muslim Grave yard area. WBM laying under progress. After land leveling

After pile foundation After structure fixing Aftter module fitting

DAILY PROGRESS REPORT for 10 MW PV PLANT NTPC UN

Weather Details : Sunny day till 12:30PM. Rain at 1:00


Report for Day

8/16/2013
SITE PREPARATION WORK : Unit TOTAL Qty 331 Sch. Date Activity of Start date Actual completio as per L2 start date n as per Sch L2

(A).

(1). (2). (3).

Tree felling Tree logging & delivering to NTPC Removal of roots from ground

Nos Tractor Nos

(4).

Disposal of roots

Nos.

(B). (1). (2). (3). (4). (4).

FENCING : Trench excavation Bottom PCC Brick Work below GL Brick Work above GL Fencing with chain link

Meter Meter Meter Metre Meter

3150 3150 3150 3150 3150

(C.)

Land leveling

Acres

(D) (D.) (G). (H). (I).

Temporary Main Road preparation Meter Pile foundation Nos

125 10560

Module Support Structure mounting Nos Fitting Modules on structures Module series cabling till JB Nos Nos 42240 3520

MW PV PLANT NTPC UNCHAHAR

ll 12:30PM. Rain at 1:00PM to 2:00 PM & 4:30PM to 5:00PM.


Cumulativ Qty e Target for Complete complete tomorrow d today d 0 331 338 0

Remarks

Activity completed on 21-07-13 Activity completed on 27-07-13 Total qty unknown due to earlier cut trees. Total qty unknown due to earlier cut trees. Total roots pending to be disposed shall be provided.

18

0 0 0 0

317.5 317.5 317.5 317.5

No work possible due to soil conditions.

For storing the PV modules,50x20sq.m. ground leveling has started near Muslim Grave yard area. WBM laying under progress. After land leveling

After pile foundation After structure fixing Aftter module fitting

DAILY PROGRESS REPORT for 10 MW PV PLAN

Weather Details :Cloudy weather full day. Rain f


Report for Day (A). (1). (2). (3). (4). (B). (1). (2). (3). (4). (4). (C.) (D) (D.) (G). (H). (I).

8/17/2013
SITE PREPARATION WORK : Tree felling Tree logging & delivering to NTPC Removal of roots from ground Disposal of roots FENCING : Trench excavation Bottom PCC Brick Work below GL Brick Work above GL Fencing with chain link Land leveling Temporary Main Road preparation Pile foundation Module Support Structure mounting Fitting Modules on structures Module series cabling till JB Unit Nos Tractor Nos Nos. Activity Sch. Date of Start date TOTAL Qty completion as as per L2 per L2 Sch 331

Meter Meter Meter Metre Meter Acres Meter Nos Sets Nos Nos

3150 3150 3150 3150 3150

125 10560 3520 42240 3520

NOTE :

Further activities shall be added as and when commenced.

RT for 10 MW PV PLANT NTPC UNCHAHAR

weather full day. Rain from 01:30PM to 2:00PM.


Qty Actual Completed start date today 0

Cumulative completed 331 338

Target for tomorrow

Remarks Activity completed on 21-07-13 Activity completed on 27-07-13 Completed.

0 0 0 0

317.5 317.5 317.5 317.5

0 0 0 0

No work possible due to wet soil conditions.

For storing the PV modules, 50x20sq.m. ground leveling completed near Grave yard area. Completed. After land leveling After pile foundation After structure fixing Aftter module fitting

DAILY PROGRESS REPORT for 10 MW PV PLAN

Weather Details :Cloudy weather full day. Rain f


Report for Day (A). (1). (2). (3). (4). (B). (1). (2). (3). (4). (4). (C.) (D) (D.) (G). (H). (I).

8/18/2013
SITE PREPARATION WORK : Tree felling Tree logging & delivering to NTPC Removal of roots from ground Disposal of roots FENCING : Trench excavation Bottom PCC Brick Work below GL Brick Work above GL Fencing with chain link Land leveling Temporary Main Road preparation Pile foundation Module Support Structure mounting Fitting Modules on structures Module series cabling till JB Unit Nos Tractor Nos Nos. Activity Sch. Date of Start date TOTAL Qty completion as as per L2 per L2 Sch 331

Meter Meter Meter Metre Meter Acres Meter Nos Sets Nos Nos

3150 3150 3150 3150 3150

125 10560 3520 42240 3520

NOTE :

Further activities shall be added as and when commenced.

RT for 10 MW PV PLANT NTPC UNCHAHAR

weather full day. Rain from 12:30PM to 1:00PM.


Qty Actual Completed start date today 0

Cumulative completed 331 338

Target for tomorrow

Remarks Activity completed on 21-07-13 Activity completed on 27-07-13 Completed.

0 0 0 0

317.5 317.5 317.5 317.5

0 0 0 0

No work possible due to wet soil conditions.

For storing the PV modules, 50x20sq.m. ground leveling completed near Grave yard area. Completed. After land leveling After pile foundation After structure fixing Aftter module fitting

DAILY PROGRESS REPORT for 10 MW PV PLANT N

Weather Details : Clear weather full day. Rain from 0


Report for Day (A). (1). (2). (3). (4). (B). (1). (2). (3). (4). (4).

8/19/2013
SITE PREPARATION WORK : Tree felling Tree logging & delivering to NTPC Removal of roots from ground Disposal of roots FENCING : Trench excavation Bottom PCC Brick Work below GL Brick Work above GL Fencing with chain link Unit Nos Tractor Nos Nos. Activity Start date TOTAL Qty as per L2 Sch 331

Meter Meter Meter Metre Meter

3150 3150 3150 3150 3150

(C.)

Land leveling

Acres

(D) (D.) (G). (H). (I).

Temporary Main Road preparation Pile foundation Module Support Structure mounting Fitting Modules on structures Module series cabling till JB

Meter Nos Sets Nos Nos

125 10560 3520 42240 3520

(D).

MATERIAL RECEIPT PV Moudles receipt Nos 42240

NOTE :

Further activities shall be added as and when commenced.

AILY PROGRESS REPORT for 10 MW PV PLANT NTPC UNCHAHAR

ther Details : Clear weather full day. Rain from 06:00PM to 06:20PM.
Sch. Date of Actual completion as start date per L2 Qty Completed today 0

Cumulative completed 331 338

Target for tomorrow

Remarks Activity completed on 21-07-13 Activity completed on 27-07-13 Completed.

0 0 0 0

317.5 317.5 317.5 317.5

0 0 0 0

No work possible due to wet soil conditions.

For storing the PV modules, 50x20sq.m. ground leveling completed near Grave yard area. Due to rain soil got wet and spread dry soil carried out to make storage yard feasible. Completed. After land leveling After pile foundation After structure fixing Aftter module fitting

Out 4032 Nos, 768 Nos in 4 Lorry reached Unchahar. Shall be unloaded tomarrow. Balance on the way.

DAILY PROGRESS REPORT for 10 MW PV PLANT N Weather Details : Clear weather full day.
Report for Day (A). (1). (2). (3). (4). (B). (1). (2). (3). (4). (4).

8/20/2013
SITE PREPARATION WORK : Tree felling Tree logging & delivering to NTPC Removal of roots from ground Disposal of roots FENCING : Trench excavation Bottom PCC Brick Work below GL Brick Work above GL Fencing with chain link Unit Nos Tractor Nos Nos. Activity Start date TOTAL Qty as per L2 Sch 331

Meter Meter Meter Metre Meter

3150 3150 3150 3150 3150

(C.)

Land leveling

Acres

(D) (D.) (G). (H). (I).

Temporary Main Road preparation Pile foundation Module Support Structure mounting Fitting Modules on structures Module series cabling till JB

Meter Nos Sets Nos Nos

125 10560 3520 42240 3520

(D).

MATERIAL RECEIPT PV Moudles receipt Nos 42240

NOTE :

Further activities shall be added as and when commenced.

AILY PROGRESS REPORT for 10 MW PV PLANT NTPC UNCHAHAR

ther Details : Clear weather full day.


Sch. Date of Actual completion as start date per L2 Qty Completed today 0

Cumulative completed 331 338

Target for tomorrow

Remarks Activity completed on 21-07-13 Activity completed on 27-07-13 Completed.

0 0 0 0

317.5 317.5 317.5 317.5

0 0 0 0

No work possible due to wet soil conditions.

For storing the PV modules, 50x20sq.m. ground leveling completed near Grave yard area. Due to rain soil got wet and spread dry soil carried out to make storage yard feasible. Completed. After land leveling After pile foundation After structure fixing Aftter module fitting

8 Lorry PV modules reached site and unloaded at site.

DAILY PROGRESS REPORT for 10 MW PV PLANT N Weather Details : Clear weather full day.
Report for Day (A). (1). (2). (3). (4). (B). (1). (2). (3). (4). (4).

8/21/2013
SITE PREPARATION WORK : Tree felling Tree logging & delivering to NTPC Removal of roots from ground Disposal of roots FENCING : Trench excavation Bottom PCC Brick Work below GL Brick Work above GL Fencing with chain link Unit Nos Tractor Nos Nos. Activity Start date TOTAL Qty as per L2 Sch 331

Meter Meter Meter Metre Meter

3150 3150 3150 3150 3150

(C.)

Land leveling

Acres

(D) (D.) (G). (H). (I).

Temporary Main Road preparation Pile foundation Module Support Structure mounting Fitting Modules on structures Module series cabling till JB

Meter Nos Sets Nos Nos

125 10560 3520 42240 3520

(D).

MATERIAL RECEIPT PV Moudles receipt Nos 42240

NOTE :

Further activities shall be added as and when commenced.

AILY PROGRESS REPORT for 10 MW PV PLANT NTPC UNCHAHAR

ther Details : Clear weather full day.


Sch. Date of Actual completion as start date per L2 Qty Completed today 0

Cumulative completed 331 338

Target for tomorrow

Remarks Activity completed on 21-07-13 Activity completed on 27-07-13 Completed.

0 0 0 0

317.5 317.5 317.5 317.5

0 0 0 0

No work possible due to wet soil conditions.

For storing the PV modules, 50x20sq.m. ground leveling completed near Grave yard area. Due to rain soil got wet and spread dry soil carried out to make storage yard feasible. Completed. After land leveling After pile foundation After structure fixing Aftter module fitting

1536

2 Lorry PV modules reached Unchaha. Shall be unloaded tomarrow.

DAILY PROGRESS REPORT for 10 MW PV PLANT N Weather Details : Clear weather full day.
Report for Day (A). (1). (2). (3). (4). (B). (1). (2). (3). (4). (4).

8/22/2013
SITE PREPARATION WORK : Tree felling Tree logging & delivering to NTPC Removal of roots from ground Disposal of roots FENCING : Trench excavation Bottom PCC Brick Work below GL Brick Work above GL Fencing with chain link Unit Nos Tractor Nos Nos. Activity Start date TOTAL Qty as per L2 Sch 331

Meter Meter Meter Metre Meter

3150 3150 3150 3150 3150

(C.)

Land leveling

Acres

(D) (D.) (G). (H). (I).

Temporary Main Road preparation Pile foundation Module Support Structure mounting Fitting Modules on structures Module series cabling till JB

Meter Nos Sets Nos Nos

125 10560 3520 42240 3520

(D).

MATERIAL RECEIPT

PV Moudles receipt
NOTE :

Nos

42240

Further activities shall be added as and when commenced.

AILY PROGRESS REPORT for 10 MW PV PLANT NTPC UNCHAHAR

ther Details : Clear weather full day.


Sch. Date of Actual completion as start date per L2 Qty Completed today 0

Cumulative completed 331 338

Target for tomorrow

Remarks Activity completed on 21-07-13 Activity completed on 27-07-13 Completed.

0 0 0 0

317.5 317.5 317.5 317.5

0 0 0 0

No work possible due to wet soil conditions.

For storing the PV modules, 50x20sq.m. ground leveling completed near Grave yard area. Due to rain soil got wet and spread dry soil carried out to make storage yard feasible. Completed. After land leveling After pile foundation After structure fixing Aftter module fitting

576

2112

3 Trucks PV modules unloaded today.

DAILY PROGRESS REPORT for 10 MW PV PLANT N Weather Details : Clear weather full day.
Report for Day (A). (1). (2). (3). (4). (B). (1). (2). (3). (4). (4).

8/23/2013
SITE PREPARATION WORK : Tree felling Tree logging & delivering to NTPC Removal of roots from ground Disposal of roots FENCING : Trench excavation Bottom PCC Brick Work below GL Brick Work above GL Fencing with chain link Unit Nos Tractor Nos Nos. Activity Start date TOTAL Qty as per L2 Sch 331

Meter Meter Meter Metre Meter

3150 3150 3150 3150 3150

(C.)

Land leveling

Acres

(D) (D.) (G). (H). (I).

Temporary Main Road preparation Pile foundation Module Support Structure mounting Fitting Modules on structures Module series cabling till JB

Meter Nos Sets Nos Nos

125 10560 3520 42240 3520

(D).

MATERIAL RECEIPT

PV Moudles receipt
NOTE :

Nos

42240

Further activities shall be added as and when commenced.

AILY PROGRESS REPORT for 10 MW PV PLANT NTPC UNCHAHAR

ther Details : Clear weather full day.


Sch. Date of Actual completion as start date per L2 Qty Completed today 0

Cumulative completed 331 338

Target for tomorrow

Remarks Activity completed on 21-07-13 Activity completed on 27-07-13 Completed.

0 0 0 0

317.5 317.5 317.5 317.5

0 0 0 0

No work possible due to wet soil conditions.

For storing the PV modules, 50x20sq.m. ground leveling completed near Grave yard area. Due to rain soil got wet and spread dry soil carried out to make storage yard feasible. Completed. After land leveling After pile foundation After structure fixing Aftter module fitting

1152

3264

6 Trucks PV modules unloaded today.

DAILY PROGRESS REPORT for 10 MW PV PLANT N Weather Details : Clear weather full day.
Report for Day (A). (1). (2). (3). (4). (B). (1). (2). (3). (4). (4).

8/24/2013
SITE PREPARATION WORK : Tree felling Tree logging & delivering to NTPC Removal of roots from ground Disposal of roots FENCING : Trench excavation Bottom PCC Brick Work below GL Brick Work above GL Fencing with chain link Unit Nos Tractor Nos Nos. Activity Start date TOTAL Qty as per L2 Sch 331

Meter Meter Meter Metre Meter

3150 3150 3150 3150 3150

(C.)

Land leveling

Acres

(D) (D.) (G). (H). (I).

Temporary Main Road preparation Pile foundation Module Support Structure mounting Fitting Modules on structures Module series cabling till JB

Meter Nos Sets Nos Nos

125 10560 3520 42240 3520

(D).

MATERIAL RECEIPT

PV Moudles receipt

Nos

42240

NOTE :

Further activities shall be added as and when commenced.

AILY PROGRESS REPORT for 10 MW PV PLANT NTPC UNCHAHAR

ther Details : Clear weather full day.


Sch. Date of Actual completion as start date per L2 Qty Completed today 0

Cumulative completed 331 338

Target for tomorrow

Remarks Activity completed on 21-07-13 Activity completed on 27-07-13 Completed.

0 0 0 0

317.5 317.5 317.5 317.5

0 0 0 0

No work possible due to wet soil conditions.

For storing the PV modules, 50x20sq.m. ground leveling completed near Grave yard area. Due to rain soil got wet and spread dry soil carried out to make storage yard feasible. Completed. After land leveling After pile foundation After structure fixing Aftter module fitting

3264

3 truck modules reached site. Since Crane got stuck 576 in soil, unloading could not take place.

DAILY PROGRESS REPORT for 10 MW PV PLANT N Weather Details : Clear weather full day.
Report for Day (A). (1). (2). (3). (4). (B). (1). (2). (3). (4). (4).

8/25/2013
SITE PREPARATION WORK : Tree felling Tree logging & delivering to NTPC Removal of roots from ground Disposal of roots FENCING : Trench excavation Bottom PCC Brick Work below GL Brick Work above GL Fencing with chain link Unit Nos Tractor Nos Nos. Activity Start date TOTAL Qty as per L2 Sch 331

Meter Meter Meter Metre Meter

3150 3150 3150 3150 3150

(C.)

Land leveling

Acres

(D) (D.) (G). (H). (I).

Temporary Main Road preparation Pile foundation Module Support Structure mounting Fitting Modules on structures Module series cabling till JB

Meter Nos Sets Nos Nos

125 10560 3520 42240 3520

(D).

MATERIAL RECEIPT

PV Moudles receipt
NOTE :

Nos

42240

Further activities shall be added as and when commenced.

AILY PROGRESS REPORT for 10 MW PV PLANT NTPC UNCHAHAR

ther Details : Clear weather full day.


Sch. Date of Actual completion as start date per L2 Qty Completed today 0

Cumulative completed 331 338

Target for tomorrow

Remarks Activity completed on 21-07-13 Activity completed on 27-07-13 Completed.

0 0 0 0

317.5 317.5 317.5 317.5

0 0 0 0

No work possible due to wet soil conditions.

For storing the PV modules, 50x20sq.m. ground leveling completed near Grave yard area. Due to rain soil got wet and spread dry soil carried out to make storage yard feasible. Completed. After land leveling After pile foundation After structure fixing Aftter module fitting

3840

192

3 truck modules unloaded at site.

DAILY PROGRESS REPORT for 10 MW PV PLANT N Weather Details : Clear weather full day.
Report for Day (A). (1). (2). (3). (4). (B). (1). (2). (3). (4). (4). (C.) (D) (D.) (G). (H). (I).

8/26/2013
SITE PREPARATION WORK : Tree felling Tree logging & delivering to NTPC Removal of roots from ground Disposal of roots FENCING : Trench excavation Bottom PCC Brick Work below GL Brick Work above GL Fencing with chain link Land leveling Temporary Main Road preparation Pile foundation Module Support Structure mounting Fitting Modules on structures Module series cabling till JB Unit Nos Tractor Nos Nos. Activity Start date TOTAL Qty as per L2 Sch 331

Meter Meter Meter Metre Meter Acres Meter Nos Sets Nos Nos

3150 3150 3150 3150 3150

125 10560 3520 42240 3520

(D).

MATERIAL RECEIPT

PV Moudles receipt
NOTE :

Nos

42240

Further activities shall be added as and when commenced.

AILY PROGRESS REPORT for 10 MW PV PLANT NTPC UNCHAHAR

ther Details : Clear weather full day.


Sch. Date of Actual completion as start date per L2 Qty Completed today 0

Cumulative completed 331 338

Target for tomorrow

Remarks Activity completed on 21-07-13 Activity completed on 27-07-13 Completed.

0 0 0 0

317.5 317.5 317.5 317.5

0 0 0 0

No work possible due to wet soil conditions. De-watering started for levelling preparation. Completed. After land leveling After pile foundation After structure fixing Aftter module fitting

3840

192

Total 20 truck received so far.

DAILY PROGRESS REPORT for 10 MW PV PLAN Weather Details :Cloudy weather full day.
Report for Day (A). (1). (2). (3). (4). (B). (1). (2). (3). (4). (4). (C.) (D) (D.) (G). (H). (I).

8/27/2013
SITE PREPARATION WORK : Tree felling Tree logging & delivering to NTPC Removal of roots from ground Disposal of roots FENCING : Trench excavation Bottom PCC Brick Work below GL Brick Work above GL Fencing with chain link Land leveling Temporary Main Road preparation Pile foundation Module Support Structure mounting Fitting Modules on structures Module series cabling till JB Unit Nos Tractor Nos Nos. Activity Sch. Date of Start date TOTAL Qty completion as as per L2 per L2 Sch 331

Meter Meter Meter Metre Meter Acres Meter Nos Sets Nos Nos

3150 3150 3150 3150 3150 125 10560 3520 42240 3520

(D).

MATERIAL RECEIPT PV Moudles receipt

Nos

42240

NOTE :

Further activities shall be added as and when commenced.

RT for 10 MW PV PLANT NTPC UNCHAHAR

weather full day.


Qty Actual Completed start date today 0

Cumulative completed 331 338

Target for tomorrow

Remarks Activity completed on 21-07-13 Activity completed on 27-07-13 Completed.

0 0 0 0

317.5 317.5 317.5 317.5

0 0 0 0

No work possible due to wet soil conditions.

Completed. After land leveling After pile foundation After structure fixing Aftter module fitting

3840

0 Total 20 truck received so far.

DAILY PROGRESS REPORT for 10 MW PV PLAN

Weather Details :Cloudy weather full day.Slightl


Report for Day (A). (1). (2). (3). (4). (B). (1). (2). (3). (4). (4). (C.) (D) (D.) (G). (H). (I).

8/28/2013
SITE PREPARATION WORK : Tree felling Tree logging & delivering to NTPC Removal of roots from ground Disposal of roots FENCING : Trench excavation Bottom PCC Brick Work below GL Brick Work above GL Fencing with chain link Land leveling Temporary Main Road preparation Pile foundation Module Support Structure mounting Fitting Modules on structures Module series cabling till JB Unit Nos Tractor Nos Nos. Activity Sch. Date of Start date TOTAL Qty completion as as per L2 per L2 Sch 331

Meter Meter Meter Metre Meter Acres Meter Nos Sets Nos Nos

3150 3150 3150 3150 3150 125 10560 3520 42240 3520

(D).

MATERIAL RECEIPT PV Moudles receipt Nos 42240

NOTE :

Further activities shall be added as and when commenced.

RT for 10 MW PV PLANT NTPC UNCHAHAR

weather full day.Slightly showers between 10:45AM to 11:15AM


Qty Actual Completed start date today 0

Cumulative completed 331 338

Target for tomorrow

Remarks Activity completed on 21-07-13 Activity completed on 27-07-13 Completed.

0 0 0 0

317.5 317.5 317.5 317.5

0 0 0 0

No work possible due to wet soil conditions.

Completed. After land leveling After pile foundation After structure fixing Aftter module fitting

3840

192

Total 20 truck received so far. 21st truck received today.

You might also like