Project:

TMX EXPANSION PROJECT


Date MOS Performed:
Title MOS-3
16-Dec-2021
FIRE SYSTEM PIPE AND VALVE INSTALLATION METHOD Date of Technical individual Meeting:

STATEMENT
12/16/2021
REGIONAL
DESIGN: SITE: QC CONTRACTOR
OFFICE

Design Manager Senior Site Health and


Engineer in Chief Quality QAQC Responsible Safety
GM Design GM (Arch, Str. or Project Project charge M&E Safety Officer Manager on site Officer
M&E) Director Manager
(foreman)

Sign/ Numa Eiichi Tanagi Diaz Uriel Yamaguchi Valdivia Hernandez Catena Raul Casas
Name Tsukasa Luis Jorge Adrian Gabriel

Date

Comment(Question・Report・Other)

CONTENT:

1 *Minute of meeting with subcontractor

2 *Organization chart

3 *Schedule work

4 *Method of Statement
MINUTA DE COORDINACION DE: / MEETING COORDINATION OF:
FIRE SYSTEM PIPE AND VALVE INSTALLATION METHOD STATEMENT
Fecha / Date: 12/16/2021
Attend: Shimizu staff: Contratctor:
Proyecto / Project: TMX Presentes: Luis Yamaguchi Contratista: TAKASAGO
Cliente / Client: Toto Mexico S.A. de C.C. Uriel Díaz Infante Raul Casas
Ubicación/ Location: Ciénega de Flores, Nuevo León, Mexico Rodolfo Pérez
Junta en/ Meeting location : TMX Site
Contratista/ Contractor: TAKASAGO ENGINEERING MEXICO
Trabajo / Work: SLURRY PIPE INSULATION WORK
Existing Factory Area
JUNTA DE COORDINACION / MEETING COORDINATION

COMENTARIOS / REMARKS

1 introduction of staff
2 safety equipment
3 MOS explanation
4 route explanation
5 schedule coordination
6 responsibility definition

Photo of meeting Photo actual site condition


2.-
Organization Chart

Director Mr. Numa

PD Mr. Tanagi

SPM Mr. Carlos Salazar

Project.Mngr.Mr. Jose Rodriguez

Safety QA/QC
Hernandez Adrian
Mr. Gabriel Catena

Superintendant
Mr. Diaz Uriel /Yamaguchi


Subcontractor
TAKASAGO ENGINEERINGMEXICO

Raul Casas Soto


3.- Schedule Work
2.2 施工管理シート/ Quality control sheet Rev. 1 MOS-3
Division Project Name PD SPM PM Sub-con Person in Cheage

SNA Mexico TMX PROJECT FIRE SYSTEM PIPE AND VALVE INSTALLATION METHOD STATEMENT

Check point Check point


1. Material / Equipment 3. Work proceduce
ESP
1.-Cierre de bomba ,valvulas y despresurizacion
1-Safty hat with chinstrap scaffold agua en tuberia
2-Safty lasses
3-Safty best with reflective tape
Welding Machine (Generator) 2.-Preparacion de area de trabajo para
4-Long sleave shirt and long pants evitar daño a instalacion existente y
5-Safty shoes retiro de material que impida realizar trabajo
6_Mouth covers

Drill 3.-Intalacion de andamio multirireccional

Grooved Pipe

toolkit extinguisher 4.- Trazos de tuberia existente


,perforacion de tuberia para posteriormente soldar niple
Valve 100A

Fire network Polisher 5.-Conexion de Valvula mariposa ranurada


accessories

6.-Instalacion de soporteria para tuberia proveniente


de valvula de paso y tendido de tuberia
2.- Work plan and layout
7.Finalizada la instalacion de tuberia, la valvula instalada
permanecera cerrada y quedara aviso a personal de TOTO estatus de la misma

cortina para
soldar
1: Cleaning the superface of the pipe. Using vacume cleaner for to avoid flyng
the dust.
2: Install insulance material over the slurry sus pipe
3: Fix insulance materis with galvanized wire
4: Install PVC sheet over the insulance material
5: Fix the PVC sheet using glue
6: Go to next area
*The discharge area with Tees, shoul be leave blank,
as image above
2.2 施工管理シート/ Quality control sheet Rev. 1 MOS-3
Division Project Name PD SPM PM Sub-con Person in Cheage

SNA Mexico TMX PROJECT FIRE SYSTEM PIPE AND VALVE INSTALLATION METHOD STATEMENT

Check point Check point


1. 材料 / 工具 3. Work proceduce

個人安全装具 高所作業車。梯子が使用出来ない
場所で使う。
1-ヘルメットと顎ひもの着用
2-安全眼鏡
3-安全ベスト(反射テープ付き)
4-長袖、長ズボン
5-安全靴
6_マスク

保温材 (1インチ厚)

伸縮梯子。場所の制約により脚立の使用が難しい
場所で使う。固定して使用。更に両手作業が出来るように
腰ベルトを使用する。

ラッキング用PVCシート ( t=0.8mm/白色) 2.- Work plan and layout

1: パイプ表面の清掃を行う。ほこり飛散防止の為に掃除機を使用
する。
2: パイプに保温材を被せる
3: ガルバワイヤーで保温材を固定する。
4: 保温材表面にPVCシートを設置する。
5: 接着剤によってPVCシートを固定する。
6: 次の工程に進む。
*上の図のように、泥取り出しチーズ部分は保温しない。

脚立。大部分で使用する。
直径 3/8" インチ のワイヤーの命綱及び
ナイロン製スリング、リトラクタブル固定点
と併用。