Professional Documents
Culture Documents
TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main
METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Rev. Date NA
Method statement for construction concrete walls
Pages 1 of 7
TABLE OF CONTENTS
1. REVISION RECORD...............................................................................................................................3
2. PURPOSE...............................................................................................................................................4
3. SCOPE OF WORKS...............................................................................................................................4
4. REFERENCES........................................................................................................................................4
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main
METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Rev. Date NA
Method statement for construction concrete walls
Pages 2 of 7
5. DEFINITIONS / ABBREVIATIONS..........................................................................................................4
5.1. Definition.............................................................................................................................................4
5.2. Abbreviations......................................................................................................................................4
6. RESPONSIBILITIES................................................................................................................................4
6.1. Project Manager.................................................................................................................................4
6.2. Construction Manager........................................................................................................................5
6.3. Project Engineer.................................................................................................................................5
6.4. QA/QC Engineer / Inspector...............................................................................................................5
6.5. Surveyor.............................................................................................................................................5
6.6. HSE Engineer/Officer.........................................................................................................................5
6.7. Foremen/ Works Supervisor...............................................................................................................6
7. EQUIPMENTS/ TOOLS / MANPOWER..................................................................................................6
7.1. Equipment’s / Tools............................................................................................................................6
7.2. List of Manpower................................................................................................................................6
7.3. List of Materials...................................................................................................................................6
8. PROCEDURE..........................................................................................................................................6
9. HEALTH, SAFETY AND ENVIRONMENT..............................................................................................7
10. ATTACHMENTS......................................................................................................................................7
10.1. Inspection Checklists..........................................................................................................................7
10.1.1. Earthworks.....................................................................................................................................7
10.1.2. Concrete........................................................................................................................................8
10.2. Inspection Test Plan...........................................................................................................................8
10.3. Risk Assessment................................................................................................................................8
10.4. Technical Data sheet (TDS)...............................................................................................................8
10.5. Material Safety Data Sheet (MSDS)...................................................................................................8
1. REVISION RECORD
This page is a record of all revisions of the document identified below by number and title. All previous revisions
are hereby superseded and are to be destroyed.
Rev Date By Chkd. Approved Description of Revisions
0 15-Aug-13 First issue
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main
METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Rev. Date NA
Method statement for construction concrete walls
Pages 3 of 7
Signature field
Revision
Revision
Number
Date
1-Jan-13 Prepared by Checked by
Reviewed
By Construction Technical QA/QC MEP Co-
Manager Manager Engineer HSE Officer ordinator Sub-contractor
Approved
By Project
Manager
2. PURPOSE
The purpose of this Method Statement is to define the procedure for sequence of works before, during and after casting
vertical RCC elements which include: columns, retaining walls, staircase walls, lift walls, internal walls of water tanks, etc.
3. SCOPE OF WORKS
This method statement applies to Buildings 6A, 6B, 6C and 6D
4. REFERENCES
1. Drawings
2. Technical Specifications
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main
METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Rev. Date NA
Method statement for construction concrete walls
Pages 4 of 7
5. DEFINITIONS / ABBREVIATIONS
5.1.Definition
1. Client -(Replace with clients name)
2. Developer -(Replace with developers name)
3. Consultant -(Replace with consultants name)
4. PMC -(Replace with PMC name)
5. Contractor -(Replace with contractors name)
5.2.Abbreviations
1. Engineer- Representative of “Name of engineering consultancy”
2. ICL - Inspection Check List
3. IR - Inspection Request
4. ITL -Independent Testing Laboratory
5. ITP - Inspection and Test Plan
6. ITR -Inspection & Test Requests
7. MET - Method Statement
8. MIR - Material Inspection Request
9. MSDS - Material Safety Data Sheet
10. PPE -Personal Protective Equipment
11. PQP -Project Quality Plan
12. PTW -Permit To Work ( Working at Height or enclosed spaces)
13. RA -Hazard Identification and Risk Assessment
14. RFIA - Request for Inspection and Approval
15. TBM - Temporary Bench Mark
6. RESPONSIBILITIES
6.1. Project Manager
1. Ensuring that the project works in his zone are carried out in accordance with Company policies and in accordance
with the requirements of this Quality plan.
2. Ensuring the full compliance of subcontractors with Company Quality policies and with the requirements of this
Quality plan.
3. To ensure that all the equipment required to execute the works according to the construction programme are
available, in good condition, and provide any additional equipment that might be required.
4. To co-ordinate with the Construction Manager, Project Engineer, Safety Engineer, Foreman and Surveyor for a
safe and proper execution of the works.
5. To guide specific attention to all safety measures in co-ordination with the safety officer/engineer.
6.2.Construction Manager
1. Ensure area is ready and safe to start the works.
2. Set up required equipment and plant through discussion with the Project Manager and Project Engineer/Works
Supervisor.
3. Ensure the works are carried out according to the specification, quality and approved shop drawings.
4. Liaise and co-ordinate with the Project Manager for the agreed sequence of works with respect to the construction
programme.
5. Allocation of required manpower through co-ordination with the Project Manager.
6. Provide the risk assessments for the works in hand.
7. Provide sufficient and safe access for operatives, trucks and pumps.
8. Take precautionary measures with regards to protecting works from hot weather, wind, rain and sun.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main
METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Rev. Date NA
Method statement for construction concrete walls
Pages 5 of 7
8. To avoid serration of the aggregates concrete placement shall be so that free fall concrete is less than 1.5m height. To
ensure proper compaction and vibration, concrete shall be placed in layers. Concrete will be properly vibrated to ensure
good compaction and prevent honeycombs in the concrete and will be finished to required level.
9. Once the concrete placement is completed the top level shall be rechecked. A final check of the plumb shall be done; if
any adjustments are required to be made they shall be made at this juncture.
10. Curing:-After de-shuttering the cast element shall be covered by hessian cloth and curing will be carried out as per
specification requirements.
11. Testing:-All necessary tests for concrete prior and after concreting work, i.e. temperature, slump test and test cubes, will
be done as per the specified requirement in Section 3300 and will be submitted to consultant for review and approval.
12. Retaining:-Walls
all tie rod holes shall be filled and the approved waterproofing membrane and protection board shall be applied to the
retaining walls. Back filling shall commence once the next level of the slab has been cast. Back filling shall be done in
200mm layers and compacted. Each layer shall be tested and must be 95% compaction. All debris and rocks shall be
removed from the back fill area.
9. HEALTH, SAFETY AND ENVIRONMENT
10. ATTACHMENTS
10.1. Inspection Checklists
10.1.1.Earthworks
1. QA/QC C2-01 Setting out
2. QA/QC C2-04 Dewatering
3. QA/QC C2-05 Excavation
4. QA/QC C2-06 Backfilling & compaction
10.1.2.Concrete
1. QA/QC C3-01 Blinding
2. QA/QC C3-02 Scaffoldings / Formworks
3. QA/QC C3-03 Rebar’s check during fixing
4. QA/QC C3-04 Rebar’s check prior to fixing
5. QA/QC C3-05 MGI Pre-concreting
10.2. Inspection Test Plan
1. ITP 4 – Excavation & Backfilling
2. ITP 5 – Steel Reinforcement
3. ITP 6 - Civil Works Concrete – Concrete Placement
4. ITP 7 - Civil Works Concrete – Finishing & Curing