TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.

TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main
METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Rev. Date NA
Method statement for construction concrete walls
Pages 1 of 7

METHOD STATEMENT FOR CONSTRUCTION CONCRETE


WALLS

PROJECT : (Replace with the project’s name, at location , city name)

CLIENT : (Replace with the client’s name)

MASTER DEVELOPER : (Replace with the master developer’s name)

PMC : (Replace with the PMC’s name)

LEAD CONSULTANT : (Replace with the lead consultant’s name)

SUB-CONSULTANT : (Replace with the sub-consultant’s name)

MAIN CONTRACTOR : (Replace with the main contractor’s name)

SUB-CONTRACTOR : (Replace with the sub-contractor’s name)

TABLE OF CONTENTS
1. REVISION RECORD...............................................................................................................................3
2. PURPOSE...............................................................................................................................................4
3. SCOPE OF WORKS...............................................................................................................................4
4. REFERENCES........................................................................................................................................4
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main
METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Rev. Date NA
Method statement for construction concrete walls
Pages 2 of 7

5. DEFINITIONS / ABBREVIATIONS..........................................................................................................4
5.1. Definition.............................................................................................................................................4
5.2. Abbreviations......................................................................................................................................4
6. RESPONSIBILITIES................................................................................................................................4
6.1. Project Manager.................................................................................................................................4
6.2. Construction Manager........................................................................................................................5
6.3. Project Engineer.................................................................................................................................5
6.4. QA/QC Engineer / Inspector...............................................................................................................5
6.5. Surveyor.............................................................................................................................................5
6.6. HSE Engineer/Officer.........................................................................................................................5
6.7. Foremen/ Works Supervisor...............................................................................................................6
7. EQUIPMENTS/ TOOLS / MANPOWER..................................................................................................6
7.1. Equipment’s / Tools............................................................................................................................6
7.2. List of Manpower................................................................................................................................6
7.3. List of Materials...................................................................................................................................6
8. PROCEDURE..........................................................................................................................................6
9. HEALTH, SAFETY AND ENVIRONMENT..............................................................................................7
10. ATTACHMENTS......................................................................................................................................7
10.1. Inspection Checklists..........................................................................................................................7
10.1.1. Earthworks.....................................................................................................................................7
10.1.2. Concrete........................................................................................................................................8
10.2. Inspection Test Plan...........................................................................................................................8
10.3. Risk Assessment................................................................................................................................8
10.4. Technical Data sheet (TDS)...............................................................................................................8
10.5. Material Safety Data Sheet (MSDS)...................................................................................................8

1. REVISION RECORD
This page is a record of all revisions of the document identified below by number and title. All previous revisions
are hereby superseded and are to be destroyed.
Rev Date By Chkd. Approved Description of Revisions
0 15-Aug-13 First issue
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main
METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Rev. Date NA
Method statement for construction concrete walls
Pages 3 of 7

Signature field
Revision
Revision
Number
Date
1-Jan-13 Prepared by Checked by

Reviewed
By Construction Technical QA/QC MEP Co-
Manager Manager Engineer HSE Officer ordinator Sub-contractor

Approved
By Project
Manager

2. PURPOSE
The purpose of this Method Statement is to define the procedure for sequence of works before, during and after casting
vertical RCC elements which include: columns, retaining walls, staircase walls, lift walls, internal walls of water tanks, etc.
3. SCOPE OF WORKS
This method statement applies to Buildings 6A, 6B, 6C and 6D
4. REFERENCES
1. Drawings
2. Technical Specifications
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main
METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Rev. Date NA
Method statement for construction concrete walls
Pages 4 of 7

5. DEFINITIONS / ABBREVIATIONS
5.1.Definition
1. Client -(Replace with clients name)
2. Developer -(Replace with developers name)
3. Consultant -(Replace with consultants name)
4. PMC -(Replace with PMC name)
5. Contractor -(Replace with contractors name)
5.2.Abbreviations
1. Engineer- Representative of “Name of engineering consultancy”
2. ICL - Inspection Check List
3. IR - Inspection Request
4. ITL -Independent Testing Laboratory
5. ITP - Inspection and Test Plan
6. ITR -Inspection & Test Requests
7. MET - Method Statement
8. MIR - Material Inspection Request
9. MSDS - Material Safety Data Sheet
10. PPE -Personal Protective Equipment
11. PQP -Project Quality Plan
12. PTW -Permit To Work ( Working at Height or enclosed spaces)
13. RA -Hazard Identification and Risk Assessment
14. RFIA - Request for Inspection and Approval
15. TBM - Temporary Bench Mark
6. RESPONSIBILITIES
6.1. Project Manager
1. Ensuring that the project works in his zone are carried out in accordance with Company policies and in accordance
with the requirements of this Quality plan.
2. Ensuring the full compliance of subcontractors with Company Quality policies and with the requirements of this
Quality plan.
3. To ensure that all the equipment required to execute the works according to the construction programme are
available, in good condition, and provide any additional equipment that might be required.
4. To co-ordinate with the Construction Manager, Project Engineer, Safety Engineer, Foreman and Surveyor for a
safe and proper execution of the works.
5. To guide specific attention to all safety measures in co-ordination with the safety officer/engineer.
6.2.Construction Manager
1. Ensure area is ready and safe to start the works.
2. Set up required equipment and plant through discussion with the Project Manager and Project Engineer/Works
Supervisor.
3. Ensure the works are carried out according to the specification, quality and approved shop drawings.
4. Liaise and co-ordinate with the Project Manager for the agreed sequence of works with respect to the construction
programme.
5. Allocation of required manpower through co-ordination with the Project Manager.
6. Provide the risk assessments for the works in hand.
7. Provide sufficient and safe access for operatives, trucks and pumps.
8. Take precautionary measures with regards to protecting works from hot weather, wind, rain and sun.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main
METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Rev. Date NA
Method statement for construction concrete walls
Pages 5 of 7

6.3. Project Engineer


1. The engineer shall carry out his duties in a manner that shall be co-ordinated by the project manager on a daily
basis, and shall ensure proper distribution of the workforce and equipment at required locations.
2. To be aware of test frequencies related to the formation level.
3. To control disposal of waste excavated material according to the instructions received from the Project Manager.
4. To co-ordinate with the Safety Officer to maintain safe working and proper housekeeping of the site. To comply
with the safety measures and ensure that all Safety Officer Teams are aware of the same to prevent accident and
loss.
5. To monitor and check all activities and ensure that works shall be carried out according to specifications, quality
and approved drawings.
6. To inform the QC Inspector of the areas ready for inspection.
6.4. QA/QC Engineer / Inspector
1. Ensuring that Consultant/Client inspection requests are implemented.
2. Compilation of all necessary quality control checklists
3. Assisting Consultants during the Inspections.
4. Coordinating with the third party lab regarding tests and results.
5. The control of work performance by means of checking the work before consultants’ inspection and issuing RFIs &
punch lists as necessary.
6. Completion of documentation to verify the work performed.
7. Controlling all inspection activities on-site in line with ITPs.
8. Ensuring that all test equipment including surveying equipment is calibrated and is suitable for use on-site.
6.5. Surveyor
1. To establish benchmarks from agreed reference points, provide required setting out and level markings and follow
up with regular checks.
2. Co-ordinate with the Project Engineer / Foreman and ensure the approved shop drawings/construction drawings
shall be implemented properly.
3. Maintain survey details and reports, periodically check the progressing works and advise the project manager of
any deviation from the drawings.
6.6. HSE Engineer/Officer
1. To ensure implementation of all safety measures related to the nature of works being carried out, and in
accordance with the Project Safety Plan.
2. To ensure that all the persons involved in the works are aware of their responsibilities, and that they have enough
understanding of the safety procedures.
3. The safety officer in co-ordination with the Project Manager shall ensure that all the implemented safety measures
are effective enough to maintain safe working on the site.
4. To maintain continuous inspections of the site activities, advise and train persons on a daily basis to prevent
accidents and personnel injury.
5. To give special concern to housekeeping, and ensure that the site is maintained clean and tidy.
6. To ensure all the relevant safety sign boards for different works are in place.
6.7.Foremen/ Works Supervisor
1. Ensure the works are progressed in the sequence as agreed with the Project Manager.
2. Liaise with the Project / Construction Manager for the allocation of the work force, ensuring adequate manpower is
available.
3. Liaise with the site manager to ensure all the required plant / materials are available to construct the works.
4. Full time supervision shall be required to ensure the works are carried out in accordance to specifications, quality
and approved drawings.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main
METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Rev. Date NA
Method statement for construction concrete walls
Pages 6 of 7

7. EQUIPMENTS/ TOOLS / MANPOWER


7.1.Equipment’s / Tools
1. Truck Load Mixer (Concrete supplier)
2. Concrete Pumps
3. Vibrators
4. Hand Tools
5. Plumb bob
7.2.List of Manpower
1. Project Manager
2. Construction Manager
3. Project Engineer
4. QA/QC Inspector
5. Safety Officer
6. Foremen / Work Supervisors
7. Equipment Operators
8. Skilled and unskilled labourers
7.3.List of Materials
1. Scaffolding
2. Formwork
3. Concrete
4. Steel Reinforcement
Note: Quantity of manpower, materials and equipment’s shall be submitted on the daily progress report.
8. PROCEDURE
1. Layout of wall and columns the surveyor shall mark the layout of the element to be cast. Doors or windows in walls shall
be laid out and marked on the concrete slab. Distances from the grid lines shall be checked against the latest approved
shop drawings.
2. Water bars:-In the case of retaining walls and tank walls water bars shall be used at construction joints. Kickers will be
formed monolithically with the slab concrete. Horizontal water bars shall be cleaned and protected to ensure that no
damage occurs to them during the fixing of the steel. As the steel installation proceeds the vertical water bars shall be
welded and secured to the steel bars to prevent movement.
3. MEP Installations: - the starter bars shall be cleaned and if required straightened. As the steel installation progresses
MEP installations work will start. Junction and distribution box fixing, conduiting, pipes, sleeves and openings shall be
fixed and inspected.
4. Reinforcement Inspection:- A Work Inspection Request (WIR) shall be raised, prior to closing of shuttering, to inspect
the completed steel reinforcement, dimensions, cover blocks, column/ wall layout, MEP works, etc. (see checklists)
5. Form Work: - once the reinforcement is checked, approved and released, the closing of formwork shall proceed. Prior
to closing the formwork all debris shall be cleared away from inside the element. The reinforcement cage cover blocks
shall be secured to the steel to ensure that proper cover is maintained. The formwork shall be coated with the approved
form release agent and shall be closed Using clamps and/ or tie rods the column/ wall shutters shall be fixed to ensure
that no concrete gel leaks from the joints during the concrete placement process. In the case of water tanks and sub
structure special type of tie rods shall be used.
6. Form Work Inspection:- During the formwork inspection the following shall be confirmed: alignment, plumb of the
formwork, the securing and supports, correct covers, cleanliness, etc. (see checklists)
7. Concrete Placement:-Concrete placement shall start only when the required pre-concreting QC checklist is prepared
and signed off in accordance to Inspection & Testing Requirements; and the work is released by the consultant. Prior to
starting the concrete climatic conditions shall be considered.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main
METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Rev. Date NA
Method statement for construction concrete walls
Pages 7 of 7

8. To avoid serration of the aggregates concrete placement shall be so that free fall concrete is less than 1.5m height. To
ensure proper compaction and vibration, concrete shall be placed in layers. Concrete will be properly vibrated to ensure
good compaction and prevent honeycombs in the concrete and will be finished to required level.
9. Once the concrete placement is completed the top level shall be rechecked. A final check of the plumb shall be done; if
any adjustments are required to be made they shall be made at this juncture.
10. Curing:-After de-shuttering the cast element shall be covered by hessian cloth and curing will be carried out as per
specification requirements.
11. Testing:-All necessary tests for concrete prior and after concreting work, i.e. temperature, slump test and test cubes, will
be done as per the specified requirement in Section 3300 and will be submitted to consultant for review and approval.
12. Retaining:-Walls
all tie rod holes shall be filled and the approved waterproofing membrane and protection board shall be applied to the
retaining walls. Back filling shall commence once the next level of the slab has been cast. Back filling shall be done in
200mm layers and compacted. Each layer shall be tested and must be 95% compaction. All debris and rocks shall be
removed from the back fill area.
9. HEALTH, SAFETY AND ENVIRONMENT
10. ATTACHMENTS
10.1. Inspection Checklists
10.1.1.Earthworks
1. QA/QC C2-01 Setting out
2. QA/QC C2-04 Dewatering
3. QA/QC C2-05 Excavation
4. QA/QC C2-06 Backfilling & compaction
10.1.2.Concrete
1. QA/QC C3-01 Blinding
2. QA/QC C3-02 Scaffoldings / Formworks
3. QA/QC C3-03 Rebar’s check during fixing
4. QA/QC C3-04 Rebar’s check prior to fixing
5. QA/QC C3-05 MGI Pre-concreting
10.2. Inspection Test Plan
1. ITP 4 – Excavation & Backfilling
2. ITP 5 – Steel Reinforcement
3. ITP 6 - Civil Works Concrete – Concrete Placement
4. ITP 7 - Civil Works Concrete – Finishing & Curing

10.3. Risk Assessment


10.4. Technical Data sheet (TDS)
10.5. Material Safety Data Sheet (MSDS)