Professional Documents
Culture Documents
TEC-221300-MET-DoR-004
Project Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Method statement for construction on manhole in Rev. Date NA
garage area Pages 1 of 10
TABLE OF CONTENTS
1. REVISION RECORD..........................................................................................................................................3
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-221300-MET-DoR-004
Project Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Method statement for construction on manhole in Rev. Date NA
garage area Pages 2 of 10
2. PURPOSE..........................................................................................................................................................4
3. SCOPE OF WORKS...........................................................................................................................................4
4. REFERENCES...................................................................................................................................................4
4.1. Contract documents.......................................................................................................................................4
4.2. Contractors Submittal....................................................................................................................................4
5. DEFINITIONS / ABBREVIATIONS.....................................................................................................................5
5.1. Definition........................................................................................................................................................5
5.2. Abbreviations.................................................................................................................................................5
6. RESPONSIBILITIES...........................................................................................................................................5
6.1. Project Manager.............................................................................................................................................5
6.2. Construction Manager....................................................................................................................................6
6.3. Project Engineer............................................................................................................................................6
6.4. QA/QC Engineer / Inspector..........................................................................................................................6
6.5. Surveyor.........................................................................................................................................................7
6.6. HSE Engineer/Officer.....................................................................................................................................7
6.7. Foremen/ Works Supervisor..........................................................................................................................7
7. EQUIPMENTS/ TOOLS / MANPOWER/MATERIALS........................................................................................7
7.1. List of Equipment’s/Tools...............................................................................................................................7
7.2. List of Manpower............................................................................................................................................7
7.3. List of Materials..............................................................................................................................................8
8. PROCEDURE FOR CONSTRUCTION OF MANHOLE INSIDE THE VILLAS...................................................8
8.1. Setting out......................................................................................................................................................8
8.2. Excavation and Compaction Works...............................................................................................................8
8.3. Placement of Blinding....................................................................................................................................9
8.4. Installation of Solid Block...............................................................................................................................9
8.5. Laying of Block works....................................................................................................................................9
8.6. Plastering the walls......................................................................................................................................10
8.7. Waterproofing Works...................................................................................................................................10
8.8. Backfilling, Compaction and Termite treatment...........................................................................................10
9. HEALTH, SAFETY AND ENVIRONMENT.......................................................................................................11
10. ATTACHMENTS...............................................................................................................................................11
10.1. Inspection Checklists...................................................................................................................................11
10.2. Inspection Test Plan....................................................................................................................................11
10.3. Risk Assessment.........................................................................................................................................11
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-221300-MET-DoR-004
Project Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Method statement for construction on manhole in Rev. Date NA
garage area Pages 3 of 10
1. REVISION RECORD
This page is a record of all revisions of the document identified below by number and title. All
previous revisions are hereby superseded and are to be destroyed.
Rev Date By Chkd. Approved Description of Revisions
0 First issue
Signature field
Revision
Revision
Number
Date
Prepared by Checked by
Reviewed
By Construction Technical QA/QC MEP Co- Sub-
Manager Manager Engineer HSE Officer ordinator contractor
Approved
By Project
Manager
2. PURPOSE
The purpose of this Method Statement is to define the procedure for the preparation and construction of
Manhole inside the Villas in accordance with the requirements specified in the relevant specifications,
procedures and drawings, considering safety and quality of the work activities.
3. SCOPE OF WORKS
This Method Statement is applicable for the complete Project.
4. REFERENCES
4.1. Contract documents
1. Project Specification :- Division 22, Section 221300
2. Contract Drawings :-
6. Shop Drawings
Sr.
Description Shop Drawings Rev No. Date Remarks
No.
1
2
3
5. DEFINITIONS / ABBREVIATIONS
5.1. Definition
1. Project -(Replace with project name)
2. Client -(Replace with clients name)
3. Developer -(Replace with developers name)
4. Consultant -(Replace with consultants name)
5. PMC -(Replace with PMC name)
6. Contractor -(Replace with contractors name)
7. Sub-contractor -(Replace with sub-contractors name)
8. Supplier -(Replace with suppliers name)
5.2. Abbreviations
1. Engineer - Representative of “Name of engineering consultancy”
2. ICL - Inspection Check List
3. IR - Inspection Request
4. ITL -Independent Testing Laboratory
5. ITP - Inspection and Test Plan
6. ITR -Inspection & Test Requests
7. MAT - Material Submittal
8. MEP - Mechanical Electrical Plumbing
9. MET - Method Statement
10.MIR - Material Inspection Request
11.MSDS - Material Safety Data Sheet
12.PPE -Personal Protective Equipment
13.PQP -Project Quality Plan
14.PTW -Permit To Work ( Working at Height or enclosed spaces)
15.RA -Hazard Identification and Risk Assessment
16.RFIA - Request for Inspection and Approval
17.SPD - Shop Drawing
18.TBM - Temporary Bench Mark
6. RESPONSIBILITIES
6.1. Project Manager
1. Ensures that the project works in his sector are carried out in accordance with Company policies and in
accordance with the requirements of the quality plan, specifications and contract.
2. Ensures the full compliance of subcontractors with Company Quality policies and with the
requirements of this method statement.
3. To ensure that all the equipment required to execute the works according to the construction
programme are available, in good condition, and provide any additional equipment that might be
required.
4. To co-ordinate with the Construction Manager, Project Engineer, Safety Engineer, Foreman and
Surveyor for a safe and proper execution of the works.
5. To guide specific attention to all safety measures in co-ordination with the safety officer/engineer.
6.5. Surveyor
1. To establish benchmarks from agreed reference points, provide required setting out and level
markings and follow up with regular checks.
2. Co-ordinate with the Project Engineer / Foreman and ensure the approved shop
drawings/construction drawings will be implemented properly.
3. Maintain survey details and reports, periodically check the progressing works and advise the Project
Manager of any deviation from the drawings.