TECHNICAL DEPARTMENT-CIVIL (Replace by Doc. No.

TEC-031100C-MET-DoR-001
the Project Name) (Rev No.)
Insert Main METHOD STATEMENT Issue Date 02 October 2013
Contractors Logo
Rev. Date NA
Method statement for KHK shuttering
Pages 1 of 7

METHOD STATEMENT FOR CUPLOK SHUTTERING

PROJECT : (Replace with the project’s name, at location , city name)

CLIENT : (Replace with the client’s name)

MASTER DEVELOPER : (Replace with the master developer’s name)

PMC : (Replace with the PMC’s name)

LEAD CONSULTANT : (Replace with the lead consultant’s name)

SUB-CONSULTANT : (Replace with the sub-consultant’s name)

MAIN CONTRACTOR : (Replace with the main contractor’s name)

SUB-CONTRACTOR : (Replace with the sub-contractor’s name)

TABLE OF CONTENTS
1. REVISION RECORD............................................................................................................................................3
2. SCOPE / OBJECTIVES........................................................................................................................................4
TECHNICAL DEPARTMENT-CIVIL (Replace by Doc. No.
TEC-031100C-MET-DoR-001
the Project Name) (Rev No.)
Insert Main METHOD STATEMENT Issue Date 02 October 2013
Contractors Logo
Rev. Date NA
Method statement for KHK shuttering
Pages 2 of 7

3. REFERENCES.....................................................................................................................................................4
4. DEFINITIONS / ABBREVIATIONS.......................................................................................................................4
4.1. Definition..........................................................................................................................................................4
4.2. Abbreviations....................................................................................................................................................4
5. RESPONSIBILITIES.............................................................................................................................................5
6. PROCEDURE.......................................................................................................................................................5
6.1. Quality Requirements.......................................................................................................................................5
6.2. Formwork (General - Refer Section 031100 of specification)..........................................................................5
6.3. Erection procedure...........................................................................................................................................6
7. RESOURCE REQUIREMENTS...........................................................................................................................6
7.1. Manpower.........................................................................................................................................................6
7.2. Material.............................................................................................................................................................6
7.3. Plant & equipment............................................................................................................................................6
8. HEALTH, SAFETY, ENVIRONMENT (HSE)........................................................................................................7
9. ATTACHMENTS...................................................................................................................................................7
9.1. Inspection Checklists........................................................................................................................................7
9.2. Inspection Test Plan.........................................................................................................................................7
9.3. Risk Assessment..............................................................................................................................................7
TECHNICAL DEPARTMENT-CIVIL (Replace by Doc. No.
TEC-031100C-MET-DoR-001
the Project Name) (Rev No.)
Insert Main METHOD STATEMENT Issue Date 02 October 2013
Contractors Logo
Rev. Date NA
Method statement for KHK shuttering
Pages 3 of 7

1. REVISION RECORD
This page is a record of all revisions of the document identified below by number and title. All previous revisions are hereby
superseded and are to be destroyed.
Rev Date By Chkd. Approved Description of Revisions

0 First issue

Signature field

Revision
Revision
Number
Date
Prepared by Checked by

Reviewed
By Construction Technical QA/QC MEP Co-
Manager Manager Engineer HSE Officer ordinator Sub-contractor

Approved
By Project
Manager
TECHNICAL DEPARTMENT-CIVIL (Replace by Doc. No.
TEC-031100C-MET-DoR-001
the Project Name) (Rev No.)
Insert Main METHOD STATEMENT Issue Date 02 October 2013
Contractors Logo
Rev. Date NA
Method statement for KHK shuttering
Pages 4 of 7

2. SCOPE / OBJECTIVES
1. This Method Statement details general procedures to be followed for first floor slab shuttering of buildings at
Project.
Separate work Method Statement as appropriate will be generated should there be any need for other floors.
Sequence of related activities
1. Tying up reinforcement
2. Concreting
3. Curing
4. De-shuttering
5. Cleaning
6. Stacking
3. REFERENCES
3.1.Contract documents
1. Project Specification :- Division 3, Section 030100
2. Contract Drawings :-
3.2.Contractors Submittal
3. Project Quality Plan :-
4. Project Safety Plan :-
5. Material approvals
Sr. No. Description Material Sub. No. Rev No. Date Remarks
1
2
3

6. Shop Drawings
Sr. No. Description Shop Drawings Rev No. Date Remarks
1
2
3

7. Related method Statements


Sr. No. Description MET no. Rev No. Date Remarks
1
2
3

4. DEFINITIONS / ABBREVIATIONS
4.1.Definition
1. Project -(Replace with project name)
2. Client -(Replace with clients name)
3. Developer -(Replace with developers name)
4. Consultant -(Replace with consultants name)
5. PMC -(Replace with PMC name)
6. Contractor -(Replace with contractors name)
7. Sub-contractor -(Replace with sub-contractors name)
8. Supplier -(Replace with suppliers name)
TECHNICAL DEPARTMENT-CIVIL (Replace by Doc. No.
TEC-031100C-MET-DoR-001
the Project Name) (Rev No.)
Insert Main METHOD STATEMENT Issue Date 02 October 2013
Contractors Logo
Rev. Date NA
Method statement for KHK shuttering
Pages 5 of 7

4.2.Abbreviations
1. Engineer - Representative of “Name of engineering consultancy”
2. ICL - Inspection Check List
3. IR - Inspection Request
4. ITL -Independent Testing Laboratory
5. ITP - Inspection and Test Plan
6. ITR -Inspection & Test Requests
7. MAT - Material Submittal
8. MEP - Mechanical Electrical Plumbing
9. MET - Method Statement
10. MIR - Material Inspection Request
11. MSDS - Material Safety Data Sheet
12. PPE -Personal Protective Equipment
13. PQP -Project Quality Plan
14. PTW -Permit To Work ( Working at Height or enclosed spaces)
15. RA -Hazard Identification and Risk Assessment
16. RFIA - Request for Inspection and Approval
17. SPD - Shop Drawing
18. TBM - Temporary Bench Mark
5. RESPONSIBILITIES
1. Project Manager has the overall responsibility for the implementation of this method statement and shall well
ensure that the approved Supplier for shuttering materials as well as other team members is aware of the
requirements of the Method Statement.
2. Project Manager is responsible to coordinate with the company PRO and the local bodies for obtaining necessary
and essential work permits – if any, for proceeding with the works.
3. Construction Manager/ Project Engineer will ensure that the Resources are available to carry out the works as
scheduled.
4. The Project Engineer/Site Engineer is responsible to carry out the works as per approved Shop Drawings, Method
Statements.
5. The Site Engineer/Supervisor is responsible to ensure that the work has been carried out as per specifications &
drawings and inspections are done as per contract.
6. The Surveyor/Site Engineer/Supervisor is responsible for Setting out the area and measuring, monitoring and
controlling the lines and levels.
7. The QA/QC Engineer/ QC inspector is responsible to ensure that the work performed is in compliance with the
approved method statement & other applicable requirements.
8. The Safety Officer is responsible to ensure that all safety precautions are in place and that the personnel on site
possess the necessary and essential PPE.
9. The Safety Officer is responsible to ensure that essential work permits are available prior to the commencement of
the work.
6. PROCEDURE
6.1.Quality Requirements
1. The works shall be performed as mentioned in this procedure and the quality assurance requirements shall be
consistent with the relevant sections of Quality System Procedure Manual of the contractor as well with the Project
Quality Plan.
2. Design drawing to be strictly complied with at the site.
3. Work shall not proceed without formal approval by the Engineer.
4. The materials and material supplier covered by this procedure shall be approved by Engineer prior to the
commencement of using the same for the project.
TECHNICAL DEPARTMENT-CIVIL (Replace by Doc. No.
TEC-031100C-MET-DoR-001
the Project Name) (Rev No.)
Insert Main METHOD STATEMENT Issue Date 02 October 2013
Contractors Logo
Rev. Date NA
Method statement for KHK shuttering
Pages 6 of 7

6.2.Formwork (General - Refer Section 031100 of specification)


1. Form works shall be designed and constructed in accordance with applicable codes within the specified tolerances
to the shape, lines, and dimension required by the design drawings(s).
2. Forms shall be coated with mould oil or release agent
3. Form exposed corners to produce smooth, square, solid unbroken lines. Provide chamfers for surfaces where
indicated on drawings.
4. For slab work, Shore/ support shall be provided for floor directly under slab being placed so that loads from
construction above will safely transfer directly to these shores.
5. Formwork shall be struck without damaging, disturbing, or overloading the structure. The minimum periods for
striking formwork shall be as agreed with Engineer based on the compressive strength results on test cubes.
Calculations for formwork shall be submitted
6.3.Erection procedure
1. Compact backfilling up to the bottom of grade slab.
2. CUPLOK system will be used as the form work type.
3. Wooden planks of minimum size 300mm wide x 50mm thick and 4mts long are be laid below the universal jack and
socket (adjustable) base. The top of wooden plan is maintained at -0.05m Level as per the design drawing.
4. Universal jacks with adjustable base are then placed apart at spacing equal to the length of ledgers (as per design
drawing) starting from one corner of the building.
5. Standards are then fixed to the jack.
6. The ledgers of specified length are then clamped to the standards to form decking.
7. The height of the first deck of ledger is adjusted from plywood to the allowable depth mentioned in the drawing by
adjusting the jack of adjustable base.
8. The second deck of the ledgers is then clamped to standards at height 1.5 M for first and third deck of ledgers is
clamped to standards at height 1 M from the second deck.
9. The standards must be erected in true verticality.
10. Bracing of standards are done as shown in the design drawing at the specified locations.
11. Universal jack with drop head adapter are then fixed on top of the standards.
12. The upper jack is adjusted to achieve the required height of floor
13. The decking beam 1.8 M is placed on the raised drop head as per the design drawings.
14. M infill beams are then placed resting on the decking beams at 0.35 M c/c (as per the design drawings).
15. 18mm Marine plywood is then placed and fixed.
7. RESOURCE REQUIREMENTS
7.1.Manpower
- Site Engineer - Carpenters
- Supervisor - Helpers (skilled, semi-skilled)
- Surveyor
7.2.Material
1. - Formwork material (ply board, soft wood, nails, Tie Rods, Clamps)
2. - Base plate/Adaptor, Universal jack, Spigot jack, Drop head
3. - Standards, Ledgers, Bracings
4. - Props, U-head
5. - Support (Decking) Beam, Infill Beam
6. - Mould Release Oil

7.3.Plant & equipment


1. - Crane
2. - Skip
3. - Cutter
4. - Theodolite/Total station
TECHNICAL DEPARTMENT-CIVIL (Replace by Doc. No.
TEC-031100C-MET-DoR-001
the Project Name) (Rev No.)
Insert Main METHOD STATEMENT Issue Date 02 October 2013
Contractors Logo
Rev. Date NA
Method statement for KHK shuttering
Pages 7 of 7

5. - Dumpy Level
6. - Carpentry tools (hammer, hacksaw, crowbar etc.)
8. HEALTH, SAFETY, ENVIRONMENT (HSE)
1. The entire works will be carried out as per the guidelines established in the Project Specific HSE Plan.
2. Utmost importance shall be given to safety of personnel and protection of existing above /underground services. It
will be ensured that the personnel involved are thoroughly aware of the “Name of the contracting company”/
Employer Safety regulations. To achieve the above the following shall also be ensured:
3. Tool Box Meetings will be conducted before starting the works.
4. All personnel will be provided with suitable Personal Protective Equipment.
5. Required permits will be obtained from the Engineer/ authorities concerned before starting the works.
6. Plant & Equipment’s shall be fully tested & certified by an independent testing agency. Copies of certificates shall
be submitted to Engineer
7. All pneumatic / lifting equipment’s including booms, slings; chain blocks etc. shall be fully tested & certified by an
independent testing agency. Copies of certificates should be available.
8. Scaffolding and working platforms will be checked for its safety.
9. ATTACHMENTS
9.1.Inspection Checklists
9.2.Inspection Test Plan
9.3.Risk Assessment