MERALCO
Work Instruction on.
Pole Dressing
By:
STS Construction and Maintenance Documentation Teama WEDTC-212.00
M1] Work Instruction Rev. Code: 0 Page 2 of 6
anezaico
Business Process: Substation Services Asset Management _| Effectivity Date: January 01, 2018
Project Name: Work Instruction on Pole Dressing
Process: STS Construction and Maintenance
PERSON RESPONSIBLI
SUPERVISOR / CREW
STEPS:
A. Procedures Before Pole Dressing
1. Review the engineering plan and determine the construction point for pole dressing,
2. Check completeness of materials withdrawn at Stores for the assigned pole dressing
job.
3. Check logistics requirement of either gondola or non-gondola work.
4, Toavoid any inconvenience to the public, clearance shall be secured from concerned
traffic authorities or local barangay officials prior to actual work, if necessary.
5. Check existing overhead distribution/sub-transmission facilities if there is a need to
interrupt affected lines. Submit a request for Pre-arranged Job Interruption to
Operations Planning Unit if needed.
B. Procedures during Pole Dressing
1. The supervisor shall conduct tailgate conference before starting work, in order to
instruct linemen on the work to be done and the safety precautions to be observed,
2. Position line trucks and mechanized equipment so as not to obstruct or interfere
with vehicular traffic or driveways.
3. Post early warning devices or caution signs at the job site for safety,
4, For night work, set up the floodlights energized through a portable generator,
installed in an appropriate location for optimum visibility.
5. Electrically ground all mechanized equipment using equipment supplied
grounding cable or with additional grounding clusters, if necessary.
6. RequestSystem Operation (DELTA) for the appropriate clearance tag when working
near energized overhead distribution lines. (Refer to Meralco Safety Code - Tagging
Rules.)
7. For work with pre-arranged job interruption, coordinate with System Operation
(DELTA) for the clearance to work on the interrupted line. Perform line testing on
the interrupted line then enclose the work area with grounding clusters prior to
commence with the assigned activity.
8, Install conductor covers or other insulated protective cover when working near
overhead distribution facilities.? WEDTC-212.00
Work Instruction Rev. Code: 0 Page3 of 6
MERAICO
Business Process: Substation Services Asset Management _| Effectivity Date: January 01, 2018
Project Name: Work Instruction on Pole Dressing
Process: STS Construction and Maintenance
9. For work using a gondola, secure the gondola to the crane hook and installa safety
rope to act as back up support for the gondola, Linemen who will work in the
gondola must secure their safety belts and harness to the gondola steel frame for
safety. The crane operators will then extend the crane boom and maneuver the
gondola to the position where pole dressing will be performed.
10, For work without a gondola, a linemen will climb the sub-transmission pole
bringing with him a hand line which will be used for raising tools and line
materials needed for pole dressing. When working on 90ft concrete segmented
pole, pole steps (5/8” machine bolts or equivalent) must be installed prior to
installation of hand line.
Notes:
1, Before & while working on the pole, the involved personnel shall
observe all the safety rules and regulations as stated in the latest
edition of the Company Safety Code to ensure their safety.
2. If there are parked vehicle(s) under the pole, request the
owner(s)/driver(s) to relocate the vehicle in a safe place.
. Installation of Pole Dressing.
1. Assemble the insulators and other line hardware at the ground prior to installation,
2. Damaged insulators should be removed and replaced. The insulators should be
clean and free of contamination
3. Insulators and hardware, when properly aligned, should fit together without using
undue force.
4, Raise the insulators and other line hardware.
5, Care should be taken in raising the insulators so as to avoid damage or breakage.
6. Attach the insulators and other line hardware into the pole using bolts specified in
the engineering plan. Ensure that all machine bolt nuts were properly tightened,
7. After the installation of pole dressing on 90ft. segmented concrete pole, remove all
installed pole steps and hand line.
8. For the dressing of polymer insulators, refer to NGK manual on Handling
Instructions for Polymer Insulators, reference no. 20010727-1
D. Procedures before Leaving the Work Area.
1, Check that all members of crew are all accounted for and have climbed down the
pole.@
MERALCO
WEDTC-212.00
Work Instruction Rev. Code: 0
Paged of 6
Business Process: Substation Services Asset Management
Effectivity Date: January 01, 2018
Project Name: Work Instruction on Pole Dressing
Process: STS Construction and Maintenance
Remove any installed groundings, conductor covers or other insulated protective
covers.
Properly dispose all waste materials and clean the surroundings.
Remove the early warning device or caution signs posted at the job site.
Call System Operations (DELTA) to clear appropriate clearances tag. (Refer to
Meralco Safety Code - Tagging rules) or to restore interrupted overhead@
MBRALCO
Work Instruction
WEDTC-212.00
Rev. Code: 0 Page 5 of 6
Business Process: Substation Services Asset Management
Effectivity Date: January 01, 2018
Project Name: Work Instruction on Pole Dressing,
Process: STS Construction and Maintenance
VALIDATING PERSONNEL
NAME
OFFICE,
Nestor J. Divina
Sub-Transmission Lines@
MERALCO
Work Instruction
WEDTC-212.00
Rev. Code: 0 Page 6 of 6
Business Process: Substation Services Asset Management
Effectivity Date: January 01, 2018
Project Name: Work Instruction on Pole Dressing
Process: STS Construction and Maintenance
SIGN-OFF SHEET
PREPARED BY: RECOMMENDED BY:
Jose P. So TIT com D, Feli: jo
Document Lead, STL Line Construction Lend, Process Committe
Name & Signature Name & Signature
Date 12/2/17 Date (lia
‘APPROVED BY:
Head, STS Construbtion & Maintenance Council &
Sub-Transwission Services
Benjamin U. Cusi
Head, Networks Asset Management
Name & Signature
Name & Signature
Date
Date
ified