Professional Documents
Culture Documents
TEC-CSInnn-MET-DoR-001
Project Name) (Rev No.)
Insert Main METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Method statement for safe erection, operation and dismantling of Rev. Date NA
a slip form shutter Pages 1 of 7
TABLE OF CONTENTS
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-CSInnn-MET-DoR-001
Project Name) (Rev No.)
Insert Main METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Method statement for safe erection, operation and dismantling of Rev. Date NA
a slip form shutter Pages 2 of 7
1. REVISION RECORD..........................................................................................................................................3
2. SCOPE / OBJECTIVES......................................................................................................................................4
3. REFERENCE......................................................................................................................................................4
4. DEFINITIONS / ABBREVIATIONS.....................................................................................................................4
4.1. Definition.........................................................................................................................................................4
4.2. Abbreviations..................................................................................................................................................4
5. RESPONSIBILITIES / SUPERVISION...............................................................................................................4
6. PROCEDURES / METHODS TO BE EMPLOYED............................................................................................5
6.1. General...........................................................................................................................................................5
6.2. Delivery...........................................................................................................................................................5
6.3. Base slab preparation.....................................................................................................................................5
6.4. Assembly........................................................................................................................................................6
6.5. To unload the containers / wagons.................................................................................................................6
6.6. Forms..............................................................................................................................................................6
6.7. Yokes..............................................................................................................................................................6
6.8. Platforms.........................................................................................................................................................7
6.9. Hydraulics and Services.................................................................................................................................7
6.10. Acceptance.....................................................................................................................................................7
6.11. Slip forming Operations..................................................................................................................................7
7. HEALTH, SAFETY AND ENVIRONMENT.........................................................................................................7
7.1. Safety hazards................................................................................................................................................7
7.2. Training...........................................................................................................................................................8
7.3. Working hours.................................................................................................................................................8
7.4. House keeping................................................................................................................................................8
8. EQUIPMENTS/ TOOLS / MANPOWER/MATERIALS........................................................................................8
8.1. Manpower requirements & supervision..........................................................................................................8
8.2. Material requirement.......................................................................................................................................8
8.3. Plant and equipment requirement..................................................................................................................8
9. Q.C APPROVALS AND OTHER DOCUMENTATION.......................................................................................8
1. REVISION RECORD
This page is a record of all revisions of the document identified below by number and title. All previous revisions are hereby superseded
and are to be destroyed.
Rev Date By Chkd. Approved Description of Revisions
0 First issue
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-CSInnn-MET-DoR-001
Project Name) (Rev No.)
Insert Main METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Method statement for safe erection, operation and dismantling of Rev. Date NA
a slip form shutter Pages 3 of 7
Signature field
Revision
Number Revision Date
Prepared by Checked by
Reviewed
By Construction Technical MEP Co-
Manager Manager QA/QC Engineer HSE Officer ordinator Sub-contractor
Approved
By
Project Manager
2. SCOPE / OBJECTIVES
The objective of this Method Statement is to set down the procedures that are involved in the safe erection, operation and
dismantling of a slip form shutter, for the construction of core for the XXXX Tower -1, Jumeirah Lake Towers Project.
3. REFERENCE.
1. Contract Specification
2. Codes and standards referred to in the H & S Plan
3. Slip form project specific drawings
4. Slip form Risk Assessment
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-CSInnn-MET-DoR-001
Project Name) (Rev No.)
Insert Main METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Method statement for safe erection, operation and dismantling of Rev. Date NA
a slip form shutter Pages 4 of 7
5. ITPs
6. XXXX H & S Plan
4. DEFINITIONS / ABBREVIATIONS
4.1.Definition
1. Client -(Replace with clients name)
2. Developer -(Replace with developers name)
3. Consultant -(Replace with consultants name)
4. PMC -(Replace with PMC name)
5. Contractor -(Replace with contractors name)
4.2.Abbreviations
1. Engineer- Representative of “Name of engineering consultancy”
2. ICL - Inspection Check List
3. IR - Inspection Request
4. ITL -Independent Testing Laboratory
5. ITP - Inspection and Test Plan
6. ITR -Inspection & Test Requests
7. MET - Method Statement
8. MIR - Material Inspection Request
9. MSDS - Material Safety Data Sheet
10. PPE -Personal Protective Equipment
11. PQP -Project Quality Plan
12. PTW -Permit To Work ( Working at Height or enclosed spaces)
13. RA -Hazard Identification and Risk Assessment
14. RFIA - Request for Inspection and Approval
15. TBM - Temporary Bench Mark
16. BRM - BRM Construction LLC
5. RESPONSIBILITIES / SUPERVISION
1. Project manager has overall responsibility for the implementation of this method statement and to ensure that all
staff and workforce are aware of the method of working and the associated risks. He is also responsible for
ensuring adequate manpower, plant and materials are available to carry out the work safely and as planned.
2. BRM Construction Manager is responsible for the implementation of the QA/QC procedures for slip forming, as set
down in the XXXX procedures documentation.
3. He also has to ensure that the slip form rig is kept within tolerances for verticality and plan dimensions.
4. The Slip form Manager will ensure that the safety rules and regulations are followed by all slip form personnel
5. QA/QC Engineers should ensure that BRM Construction work is carried out in accordance with contract
specifications and drawings.
6. Safety Engineer should ensure that the Project Safety Plan is complied with.
7. Construction Manager will have the following responsibilities.
1. Monitor BRM for verticality and plan dimensions
2. Monitor workmanship of steel fixing, carpentry and concrete placing
3. Set out and maintain levels for box outs and openings
4. Set out changes in geometry and reinforcement
5. Monitor the quantity of the finished concrete
6. Record and report defects
7. Perform As built surveys
8. To explain in tool box talks the work methods to operatives
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-CSInnn-MET-DoR-001
Project Name) (Rev No.)
Insert Main METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Method statement for safe erection, operation and dismantling of Rev. Date NA
a slip form shutter Pages 5 of 7
components supplied for the contract. At the discretion of the SLIPFORM INTERNATIONAL supervisor, internal
bracings are usually fitted at this stage to aid in setting up and maintaining position of the forms.
3. The forms shall be set up with the correct amount of taper, equally applied to both sides of a wall. Correct position,
thickness and form taper of each wall shall be confirmed by the relative position of the form panels from the offset
lines and timber spacers inserted in between the top of the forms. Equal taper shall be confirmed by spirit level
readings taken on both sides of the forms.
6.7.Yokes
1. There are two preparatory stages prior to the installation of the yokes onto completed sections of wall forms:
2. Pre-assemble yokes in the designated area. Two frames are required per lifting point shown on the drawings.
3. Pre-drill the top deck timbers to the schedule given on the drawings. It is essential that the 18mm holes are drilled
straight and true and on the centre line of the timbers.
4. As sections of wall form are assembled and internally braced, yokes can be fitted into position. Centre line
positions of the lifting points are marked off on each side and a ‘waling bracket’ loosely bolted to each waling. The
SLIPFORM INTERNATIONAL supervisor will advise as to the type of connection to use as it is dependent upon the
orientation of the wailings as described above.
5. Each yoke frame is uplifted from the pre-assembly area and transferred to the slip form by crane and carefully
guided into position by two operatives working one on either side of the wall form. The legs are loosely bolted to
the waling brackets and checked for plumb.
6. As yokes are lifted into position top deck timbers are positioned and loosely bolted to upper cross beams. The
sequence of this operation can be determined by studying the working platform drawings. Once sections are
completed the process of fixing the yokes into position and tightening the bolts can take place. This involves
plumbing the yokes and checking the forms for position and taper as described in 4.1 above.
6.8.Platforms
1. It should be noted that only the working deck (i.e. that which is sited directly on top of the forms) and the top deck,
can only be assembled at this stage. The suspended platform can only be installed after slip forming operations
begin and the slip form has climbed 1.8 m.
2. Initially the top deck 100 x 100mm timbers are prepared in accordance with the cutting schedule. The timbers are
erected and bolted to the top of the yolk legs. An access deck should be provided to the underside of the deck to
allow the safe installation of the top deck timbers.
3. The main working platform supported by timber bearers mounted on top of steel platform brackets which are bolted
to the wailings. Generally these brackets are installed after the yokes have been set and fixed in position to provide
the maximum working space around the yoke legs. However in some instances particularly on internal forms
where diagonal bracings are shown on the drawings to pass through them they need to be fitted on beforehand.
To compensate for the different orientation of the wailings, 10 mm thick plate washers are provided as packers.
4. Unless directed by the Slip form International supervisor, the external waling bracing can be fixed at the same time
as the platform brackets are fitted but before the decking is laid.
5. Decking timber and toe boards should be installed in accordance with the working drawings. Openings for access
to upper and lower decks shall be made in positions agreed with the Slip form International supervisor.
6. As external platforms are laid at either the main working or upper level so the handrail posts shall be fixed in
positions as shown on the drawings. Guardrails shall be fitted as soon as is practicably possible.
6.9.Hydraulics and Services
1. The Slip form International supervisor will show how the jacks and hydraulics are installed but will usually
undertakes the pressure testing operations.
2. Testing will necessarily involve the use of the hydraulic pump. Therefore at the stage when jacks and hydraulics
are being installed the electrical services provide by the main contractor should be installed. Although shown on
drawing, the Slip form International supervisor will ultimately decide where the hydraulic pump is to be located.
3. Provisions for lighting and power supplies to the illuminated target boxes should also be installed.
6.10. Acceptance
1. It is usual to fix the first lift of vertical steel, lace the horizontal bars up to the underside of the cross bars and install
any inserts that can be fixed. Under no circumstances should any part of the slip form be used as anchorages or
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-CSInnn-MET-DoR-001
Project Name) (Rev No.)
Insert Main METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo
Method statement for safe erection, operation and dismantling of Rev. Date NA
a slip form shutter Pages 7 of 7
supports to gain leverage in correcting reinforcement that is out of position irrespective of whether it is by the use
crow bars, props or pulling devices.
2. Final checks and acceptance of the slip form as fit to commence slip forming operations is given only after the
reinforcement has been checked and approved. Acceptance by the client shall be given on Slip form International
form 600.
6.11. Slip forming Operations
3. Slip forming of the core will be done on day shifts only. This involves sliding the top half of the forms clear after
concreting finishes for the day to prevent bonding overnight. It is necessary to clean the exposed top section of the
forms, usually by using pressure washers with a rated capacity of 2000 psi. Or other approved methods. Failure to
do so will cause a marked deterioration in the concrete finish as well as increasing the drag on the forms.
7. HEALTH, SAFETY AND ENVIRONMENT
7.1.Safety hazards
1. Safety Lighting – to be supplied by the main contractor
2. Task lighting – to be supplied by the main contractor under the supervision of BRM
3. Emergency Arrangements – BRM personnel will comply with the XXXX arrangements
4. Risks and Controls - See separate Risk Assessment
7.2.Training
All personnel are safety trained in the UK and have CSCS safety certification as required by current UK legislation.
7.3.Working hours
As required by the main contractor up to 60 hours per week for erection and dismantling. 12 hours per day during slip
forming. No work on Fridays.
7.4.House keeping
The slip form supervisors will ensure that the slip form decks are kept in a tidy and orderly fashion.