BATTERY ENERGY STORAGE SYSTEM
(BESS) FACILITY
Project Location:
SAN MANUEL, PANGASINAN
Document Title:

METHOD OF STATEMENT – CONCRETING


Date Name Sign Subcontractor :
Drawn CB

Checked

Approved

Scale Size Document No.


NTS A4 (4)BESS-SM-3Q90041-QAMS-005

Page No. Total Page


1 5
(4)BESS-SM-3Q90041-QAMS-005 METHOD OF STATEMENT -CONCRETING.docx
C:\UserData\z0047aud\Documents\ENG20012 SIEMENS SAN MANUEL\600 Output\METHOD OF
STATEMENT\(4)BESS-SM-3Q90041-QAMS-005 METHOD OF STATEMENT -CONCRETING.docx

Unrestricted
Project Document no.
BATTERY ENERGY STORAGE SYSTEM (4)BESS-SM-3Q90041-QAMS-005
(BESS) FACILITY
Title Rev. page of
A 2 5
METHOD OF STATEMENT – CONCRETING

REVISION HISTORY

PAGE NO. REVISIONS REMARKS

A B

All x First issued

Unrestricted
Project Document no.
BATTERY ENERGY STORAGE SYSTEM (4)BESS-SM-3Q90041-QAMS-005
(BESS) FACILITY
Title Rev. page of
A 3 5
METHOD OF STATEMENT – CONCRETING

Description
of the Task / CONCRETING WORKS
Activity
Required As needed
Manpower
1. Hand saw, wire cutter, brush shovel
2. Steel brush
Tools and 3. Plumb bob
Equipment 4. Line dory
Required 5. Concrete Pump
6. Vibrator
7. Trowel
Materials Ready-mix concrete, Cement, Gravel, Sand, water
Required
Other (i.e. access platforms, winches, ladders, etc.)

Ladders, Platforms, Scaffoldings


Essential
Equipment
Specific Working in high Elevation from Ground, Falling Debris
Identified
Residual
Hazards
Specific Staff Basic occupational safety and health Training
Training
Requirement
s
Predecessor Rebar & Form Works, Electrical Works
Activity
1. Appropriate arrangement and approval for conveying concrete (Chutes,
pump, manual) shall be obtained from client.
2. Cranes, concrete bucket, pumps, chute, shovel and manual methods will be
used as per the elevation’ quantity of concrete and to suit the site condition
towards conveying and spreading concrete.
3. Concrete shall be delivered to site within 75 minutes after the introduction
Work Method of the water to the cement, and shall be placed and compacted within 45
(Specifying methods of
working, tools, materials minutes of arrival. The concrete shall be compacted and in its finial position
and equipment utilized)
within 120 minutes of the introduction of the cement to the aggregate.
4. Concrete, during and immediately after depositing, shall be thoroughly
compacted. The compacting shall be done by mechanical vibrator.
5. The vibration shall be of sufficient duration and intensity to compact the
concrete thoroughly but shall not be continued so as to cause segregation.
6. Pouring height should not exceed more than 1.5m to prevent segregation.

Unrestricted
Project Document no.
BATTERY ENERGY STORAGE SYSTEM (4)BESS-SM-3Q90041-QAMS-005
(BESS) FACILITY
Title Rev. page of
A 4 5
METHOD OF STATEMENT – CONCRETING

7. Each layer shall be compacted so as to avoid the formation of construction


joint with the previous layer which has not taken initial settlement.
8. Concrete cover to maintain as per drawings during casting operation.
9. Concrete temperature shall be maintained below 30° C at the time of pour.
10. Adequate illuminations shall be provided during night concreting.
11. Concrete temperature shall not exceed 30° C at the time of placing and
during hot weather the forms shall be shaded and sprayed with water. To
prevent the premature drying of concrete it shall be covered with polythene
and reflective sheets.
12. During hot weather pouring will be carried out in such a way that there will
be no formation of cold joint. If concreting activities are carried out during
night time adequate illumination shall be provided. Concrete shall be
placed in shallow layers enough to assure vibration well into the layers
below and the elapsed time between the layers be minimized to avoid
cold joints.
Fall (i.e. Guard Rails/ Toe Boards/ Brick Guards/ Safety Harnesses/ Exclusion Zones etc)

Guard Rails, Exclusion Zones


Protection
Measures
(Where work at height
cannot be eliminated –
consider both Personnel
& Materials)
(i.e. Lubricants/ Solvents/ Flammable Materials/ Refrigerants/ Welding Gases etc)

Hazardous
Substances
Very Toxic Harmful / Corrosive Dangerous Oxidizing Highly Explosive
Irritant for the Flammable
environment
Applicable N N N N N N N
(Y/N)
Safe Working (Detail any limits on the loading applicable to temporary plant/equipment or fixed elements of the structure where the work is
taking place.)
Load
Required Other:

Personnel 1.
Protective 2.
Safety Hard Safety Hearing Respirator Eye 3.
Equipment Boots Hats Gloves Protectio y Protectio
n Protection n
Applicable Y Y Y Y
(Y/N)

Unrestricted
Project Document no.
BATTERY ENERGY STORAGE SYSTEM (4)BESS-SM-3Q90041-QAMS-005
(BESS) FACILITY
Title Rev. page of
A 5 5
METHOD OF STATEMENT – CONCRETING

Emergency FIRE – When a fire occur, take the following action:


Procedures 1. Evacuate immediately at the closest exit.
2. When leaving the building, close all windows and doors. This will stop the
spread of fire.
3. If you encounter smoke, drop down to the floor and stay low until you
reach the exit.
4. When evacuating the building, always use the stairs, never use the
elevator, because power could be lost, trapping you on the floor of the fire.
5. If physically impaired, know your places of refuge. Please list places of
refuge for Physically Impaired personnel.
6. Meet a designated area, which should be at least 50 feet from building. Fill
in designated assembly area.

ACCIDENT – when an accident occur, take the following action:


1. Call emergency hotline immediately
2. Avoid leaving injured person(s) except to summon help.
3. Do not move the injured person(s).
4. Render First aid or CPR if you are trained and feel comfortable doing so.
5. Protect yourself before and after rendering assistance.