TEC-031513N-MET-DoR-001
Project Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Method statement for the fixing of the non swell type Rev. Date NA
waterstop in the sub structure concrete works Pages 1 of 12
TABLE OF CONTENTS
1. REVISION RECORD............................................................................................................................3
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-031513N-MET-DoR-001
Project Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Method statement for the fixing of the non swell type Rev. Date NA
waterstop in the sub structure concrete works Pages 2 of 12
2. PURPOSE.............................................................................................................................................4
3. SCOPE OF WORKS.............................................................................................................................4
4. REFERENCES......................................................................................................................................4
4.1. Contract documents..............................................................................................................................4
4.2. Contractors Submittal............................................................................................................................4
5. DEFINITIONS / ABBREVIATIONS.......................................................................................................4
5.1. Definition...............................................................................................................................................4
5.2. Abbreviations........................................................................................................................................4
6. RESPONSIBILITIES.............................................................................................................................5
6.1. Project Manager....................................................................................................................................5
6.2. Construction Manager...........................................................................................................................5
6.3. The Project Engineer............................................................................................................................5
6.4. QA/QC Engineer / Inspector.................................................................................................................5
6.5. Surveyor................................................................................................................................................6
6.6. HSE Engineer/Officer............................................................................................................................6
6.7. Foremen/ Works Supervisor.................................................................................................................6
7. EQUIPMENTS/ TOOLS / MANPOWER................................................................................................6
7.1. Equipment’s / Tools...............................................................................................................................6
7.2. List of Manpower...................................................................................................................................6
7.3. List of Materials.....................................................................................................................................6
8. PROCEDURE.......................................................................................................................................7
8.1. General.................................................................................................................................................7
8.2. Lift Pit....................................................................................................................................................7
8.3. Manholes...............................................................................................................................................7
8.4. Raft........................................................................................................................................................8
8.5. The raft and the retaining wall.............................................................................................................10
8.6. Expansion Joints.................................................................................................................................11
9. HEALTH, SAFETY AND ENVIRONMENT..........................................................................................12
10. ATTACHMENTS.................................................................................................................................12
10.1. Inspection Checklists..........................................................................................................................12
10.2. Inspection Test Plan............................................................................................................................12
10.3. Risk Assessment.................................................................................................................................12
10.4. Technical Data sheet (TDS)................................................................................................................12
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-031513N-MET-DoR-001
Project Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Method statement for the fixing of the non swell type Rev. Date NA
waterstop in the sub structure concrete works Pages 3 of 12
TABLE OF FIGURES
Figure 1: Lift Pit Plan & Section A-A......................................................................................................7
Figure 2: Sequence of panel casting is shown..........................................................................................8
Figure 3: Construction Joints....................................................................................................................8
Figure 4: Raft-in-fill strips........................................................................................................................9
Figure 5: Retaining wall & Water Tanks..................................................................................................9
Figure 6: Wall & water tanks-1...............................................................................................................10
Figure 7: Wall & water tanks-2...............................................................................................................10
Figure 8 ; Retaining wall.........................................................................................................................11
Figure 9 ; Expansion joint.......................................................................................................................11
Figure 10: Backing rod...........................................................................................................................12
1. REVISION RECORD
This page is a record of all revisions of the document identified below by number and title. All previous revisions
are hereby superseded and are to be destroyed.
Rev Date By Chkd. Approved Description of Revisions
0 2-Oct-13 First issue
Signature field
Revision
Revision
Number
Date
2-Oct-13 Prepared by Checked by
Reviewed
By Construction Technical QA/QC MEP Co-
Manager Manager Engineer HSE Officer ordinator Sub-contractor
Approved
By Project
Manager
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-031513N-MET-DoR-001
Project Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Method statement for the fixing of the non swell type Rev. Date NA
waterstop in the sub structure concrete works Pages 4 of 12
2. PURPOSE
The purpose of this method statement is to define the fixing of the water stop in the sub structure concrete works
as per the manufacturer’s requirements and drawings, considering all the necessary safety and quality aspects of
the work activities.
3. SCOPE OF WORKS
This scope of works is for substructure concrete works in the project. (Basement with raft + UG water tank)
4. REFERENCES
4.1.Contract documents
1. Project Specification :- Division 3, Section 031513
2. Contract Drawings :-
4.2.Contractors Submittal
3. Project Quality Plan :-
4. Project Safety Plan :-
5. Material approvals
Sr. No. Description Material Sub. No. Rev No. Date Remarks
1 Fosroc Supercast Water foil 250
2
3
5. DEFINITIONS / ABBREVIATIONS
5.1.Definition
1. Project -(Replace with project name)
2. Client -(Replace with clients name)
3. Developer -(Replace with developers name)
4. Consultant -(Replace with consultants name)
5. PMC -(Replace with PMC name)
6. Contractor -(Replace with contractors name)
7. Sub-contractor -(Replace with sub-contractors name)
8. Supplier -(Replace with suppliers name)
5.2.Abbreviations
1. Engineer - Representative of “Name of engineering consultancy”
2. ICL - Inspection Check List
3. IR - Inspection Request
4. ITL -Independent Testing Laboratory
5. ITP - Inspection and Test Plan
6. ITR -Inspection & Test Requests
7. MAT - Material Submittal
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-031513N-MET-DoR-001
Project Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Method statement for the fixing of the non swell type Rev. Date NA
waterstop in the sub structure concrete works Pages 5 of 12
6.2.Construction Manager
1. Ensure the area is ready and safe to start the works.
2. Set up the required equipment and allocate required manpower through discussion with the Project Manager and
Project Engineer / Works Foreman.
3. Ensure the works are carried out according to the specification, quality plan, approved shop drawings and the
construction program.
4. Provide Risk Assessment for the works in hand.
5. Provide sufficient and safe access for operatives, trucks and pumps.
6. Ensure that all the works are carried out in accordance with approved procedures and drawings.
6.5. Surveyor
1. To establish bench marks from agreed reference points, provide required setting out and level markings and follow
up with regular checks.
2. Co-ordinate with Project Engineer and foreman to ensure the location of works carried out according to the
approved shop drawings/construction drawings.
3. Maintain survey details and report, periodically check the progressing works and notify the Project Manager if any
deviation from the drawings.
7.2.List of Manpower
1. Project Manager
2. Construction Manager
3. Works Foremen
4. Supervisors
5. Skilled and unskilled labourers
7.3.List of Materials
1. Supercast PVC
2. Binding wire
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-031513N-MET-DoR-001
Project Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Method statement for the fixing of the non swell type Rev. Date NA
waterstop in the sub structure concrete works Pages 7 of 12
Note: Quantity of manpower, materials and equipment’s shall be submitted on the daily progress report.
8. PROCEDURE
8.1.General
Supercast Watafoil 250mm wide shall be used in raft at construction joints, in-fill strips, retaining walls, lift pits walls,
manhole to raft connections. All installation of Supercast PVC Water stop shall be in accordance to the manufacturer’s
recommendations attached.
8.2.Lift Pit
The lift pit consists of three lifts of concrete: the pile cap/lift pit bottom, the lift pit walls and the connection to the raft. The
waterbar shall be installed in each of the construction joints. 250mm Supercast Watafoil used in the wall lifts.
8.3.Manholes
Manhole shall be a precast element that shall be places in position, levelled, backfilled and ready for raft cast.250mm
Supercast Watafoil used in: the manhole base and wall between the wall and the raft. Note that in Stage 2 the wall ends
below the raft bottom level to accommodate the raft reinforcement steel.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-031513N-MET-DoR-001
Project Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Method statement for the fixing of the non swell type Rev. Date NA
waterstop in the sub structure concrete works Pages 8 of 12
8.4.Raft
The raft shall be cast in sections and pour strips. The following cases shall be encountered:
1. Raft shown above is cast in the centre of the building as in the case of. In such cases there are no retaining walls
or edges to consider the waterbar used is 250mm wide Supercast Rearguard R.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-031513N-MET-DoR-001
Project Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Method statement for the fixing of the non swell type Rev. Date NA
waterstop in the sub structure concrete works Pages 9 of 12
`
Figure 4: Raft-in-fill strips
2. For in-fill strips 250mm wide Supercast Rearguard R shall be used as shown above.
As shown above in fig.5 the Super Cast Rearguard R water stop shall be installed between:
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-031513N-MET-DoR-001
Project Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Method statement for the fixing of the non swell type Rev. Date NA
waterstop in the sub structure concrete works Pages 10 of 12
Retaining walls shall have waterbar as shown above in figure. Supercast Rearguard R, 250mm wide shall be used in raft at
construction joints and in-fill strips. Note that in the water tank wall shown above waterbar is fixed at the top of the wall to be
cast into the basement slab.
The same shall be the case for the retaining wall if the external ground level is above the joint or there is a green
landscaped area above.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-031513N-MET-DoR-001
Project Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Method statement for the fixing of the non swell type Rev. Date NA
waterstop in the sub structure concrete works Pages 11 of 12
In retaining walls above Supercast Rearguard R shall also be used. Note that there is no water bar on top of the retaining
wall shown above.
8.6.Expansion Joints
The expansion bars shall begin at the retaining wall above the raft. However, the water bar must be embedded in the raft.
Before the cast of the raft concrete, retaining wall expansion joint locations shall be marked out by the surveyor and in these
locations Supercast Rearguard S shall be fixed to the raft shutter.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.
TEC-031513N-MET-DoR-001
Project Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Method statement for the fixing of the non swell type Rev. Date NA
waterstop in the sub structure concrete works Pages 12 of 12
The expansion joint shall continue in to the Ground Floor slab where it shall be treated (details of which shall follow in a
separate submittal). In areas of the ground floor expansion joint no water bar shall be used. The expansion joint at this
location shall only be treated by joint sealer as per waterproofing subcontractor’s proposal (to be submitted soon).