CIRCULATION LIST
Date
No Discipline Initial Title/Comment Sign
Target Remark
1. Project Manager AZ 08Ͳ12Ͳ21 Approval
5. Project Engineer LS
The above document(s) have been reviewed and incorporate in the referenced document(s)/drawing(s) as appropriate
APPROVED
REVIEWED / COMMENTED
Resubmit corrected document for Approval
NOT APPROVED
Krishna H.
(...........................) (Dedy Parsaoran Sianturi) (Akhmad Zamroni)
Revision : 1
SIMENGGARIS BLOCK
Date : 16/11/2021
Revision : 1
SIMENGGARIS BLOCK
Date : 16/11/2021
COMMENT SHEET
Incorporated
Rev Section Page Comment (Y/N) Description
Revision : 1
SIMENGGARIS BLOCK
Date : 16/11/2021
TABLE OF CONTENTS
1. INTRODUCTION .......................................................................................................................... 5
2. SYMBOL AND ABBREVIATIONS: ............................................................................................. 6
2.1 DEFINITIONS AND ABBREVIATION .......................................................................................... 6
2.2 REFERENCES.............................................................................................................................. 6
3. SCOPE .......................................................................................................................................... 7
4. MANPOWER.................................................................................................................................. 7
4.1 Manpower....................................................................................................................................... 7
4.2 Responsibilities............................................................................................................................... 7
5. TOOLS ........................................................................................................................................... 8
6. SURVEY PROCEDURE................................................................................................................. 8
7. HEALTH, SAFETY, AND ENVIRONMENT ................................................................................. 10
8. REGULATION PERMITS............................................................................................................. 10
8.1 Regulatory Permit......................................................................................................................... 10
8.2 Working Permit ............................................................................................................................. 10
Revision : 1
SIMENGGARIS BLOCK
Date : 16/11/2021
1. INTRODUCTION
JOB Pertamina - Medco E&P Simenggaris, hereafter known as COMPANY, is the
operator of South Sembakung Field located at Simenggaris Block, North Kalimantan.
TheSouth Sembakung Field has a South Sembakung Gas Plant was designed to
produce 30MMSCFD gas for 20 years. Currently, there are 4 (Four) wells which have been
drilled; namely SSB-2 as production well and three development wells namely SSB-4,
SSB 5 and SSB-7,which are currently under temporary suspension.
Based on the Gas Sales and Purchase Agreement (PJBG) to PT. PLN 8 MMSCFD
and PT. Kayan LNG 22 MMSCFD, the addition of 3 (Three) development wells will be
required,namely SSB-8, and SSB-10.
COMPANY has initiated the new Project to accommodate produced gas from the new
wells. The project will consist of installation of : New wellsite facilities and its flowlines,
LLP production manifold and LLP production separator, new condensate handling
system (Heater, tanks, pumps, custody meter and export line), new (Future)
compressor package during wells pressure depletion and other repair and
modifications required.
Revision : 1
SIMENGGARIS BLOCK
Date : 16/11/2021
Definitions Description
COMPANY JOB Pertamina – Medco E&P Simenggaris
BUYER The party which purchases product from COMPANY
FEED The party that carries out all or part of the Front-End
CONSULTANT Engineering Design
The party that carries out all or part of the detail engineering,
CONTRACTOR
procurement, construction, installation and commissioning
VENDOR/ Party which supplies equipment/materials or services
SUPPLIER specified and ordered by CONTRACTOR (or COMPANY)
Party which manufactures equipment/materials specified and
MANUFACTURER
ordered by CONTRACTOR (or COMPANY)
Abbreviations Description
BM Benchmark
CPY Company
CTR Contractor
ERP Emergency Response Plan
FJC Field Joint Coating
HSE Health Safety and Environment
JSA Job Safety Analysis
NDT Non-Destructive Test
PPE Personal Protection Equipment
PTW Permit to Work
QC Quality Control
RA Risk Assessment
ROW Right of Way
WPS Welding Procedure Specification
2.2 REFERENCES
x Contract Document – Exhibit B – Scope of Works.
x Peraturan Menteri Energi Dan Sumber Daya Mineral Republik Indonesia Tentang
Keselamatan Instalasi Dan Peralatan Pada Kegiatan Usaha Minyak Dan Gas Bumi No. 38
Tahun 2017.
x Gas Transmission And Distribution Piping System : ASME B31.8 Thn. 2014.
x Sistem Penyaluran dan Distribusi Pipa Gas : SNI 3474 Tahun 2009.
x Specification for Line Pipe : API 5L 2012
Revision : 1
SIMENGGARIS BLOCK
Date : 16/11/2021
3. SCOPE
This scope of work establishes the procedures to be used in establishing of site survey prior to the
engineering phase, new pipelines and new facilities for the Design, Detail Engineering, Procurement &
Construction.
4. MANPOWER
4.1 Manpower
x Site Manager : 1 person
x Supervisor Survey : 1 person
x Work Permit Coordinator : 1 person
x Surveyor : 1 person
x Helper : 2 persons
x Drafter : 1 person
x Safety Officer : 1 person
4.2 Responsibilities
9 Site manager
Site Manager responsible for all activity at the site. He will make sure to get the work permit
to start the job, and supervise the work topographical survey accordance with the procedure.
He also ensure that tool box meeting are held every day before starting work. And
communicate with the Cpy about work procedure, administration procedure, report system,
and technical problem that occur.
9 Supervisor Survey
Survey supervisors are responsible for survey activity according to approved procedure. He
is also responsible for ensuring the topographical survey work is carried out in accordance
with the available work permit.
Revision : 1
SIMENGGARIS BLOCK
Date : 16/11/2021
9 Surveyor
The surveyor is responsible for ensuring that the survey reference point is in accordance
with the total geodetic system and making it as bench mark. And also make measurement
points if needed.
9 Safety Officer
The Safety Officer is responsible for supervising the work at site in accordance with the HSE
plan.
5. TOOLS
Equipment/ Tools Qty Remarks Last Calibration
6. SURVEY PROCEDURE
- All benchmark (Both existing and new installed) in the survey area will be measured and made
connected to the reference point.
- Network map survey will be made as loop or close route.
- Survey method for this control point survey will be carried out by Geodetic
- GPS or Traversing and Leveling survey.
- GPS survey will be performed if the location is available to used. Dual frequency Geodetic
GPS will be used by static Method.
- Traversing survey will be carried out by using Total Station or Combination of T-2 Theodolite and
EDM (Electronic Distance Measurement). Horizontal angle will be observed by a double series of
Theodolite reading. Whenever discrepancies between mean value and its series of reading more
than 5”, the next double series will be carried out. Vertical angle will be observed by face left and
face right reading into consideration the error of collimating line. Slope distance will be observed at
least 3 times display. Horizontal distance will be obtained from forward and backward slope
distance and it’s respective to vertical angle. Section accuracy of network scheme will be: Angle
close error = 10 √ n (sec.) and linear Error = 1/10000 or better; (n = number of point observation.)
- Leveling survey will be carried out by using Automatic Level. Double stand leveling will be
introduced where fully optical means will be read off during the first stand while for the second
stand will be 3 mm. All of data reading will be recorded to the field note for further processing.
Minimum of line or sight will be 5 m while the farthest not exceed than 60 m. To maintain the
accuracy, total backward and forward distance will be balanced and also the staff will be supported
by foot-staff.
- All field data will be carefully recorded for further processing and description or each control point
will be taken for documentation and completed with clear sketches how to reach.
Revision : 1
SIMENGGARIS BLOCK
Date : 16/11/2021
Illustration - 1
Illustration - 2
Illustration - 3
Revision : 1
SIMENGGARIS BLOCK
Date : 16/11/2021
x Emergency Respond
All workers must follow the ERP when an emergency situation occurs. Workers must gather at the
Muster Point (MP) and follow further safety procedures.
8. REGULATION PERMITS
8.1 Regulatory Permit
Prior to the start of Topographical Survey activity, the Supervisor shall ensure that the site has been
permitted to work by COMPANY, local authorities and/ Or local land owner to avoid any problems
during the performance of the work.