Professional Documents
Culture Documents
Vetted by Prepared by
Marno Anisa
Project Manager Site Engineer
3/12/21
Weekly Progress Report 04
Contents
1. Executive Summary
2. HSE Update
• Safety Manhour
• Equipment Report
• Update Initial Work (Temporer)
3. Site Progress
• Weather Report
• Manpower list
• Overall progress
• Site Progress Photos
• Plan Works
4. Documentation
• RFA Drawing
• RFA Material
5. Prevention Covid – 19
3/12/21
Extension Building PT. Clama Indonesia
2
Executive Summary
1. Contract Agreement
• Contract signed
• Start 2 November 2020 – Finish 30 June 2021 (8 Month)
• Production Building : Finish 30 April 2021 (6 Month)
• Running time : 35 Days (06 December 2020)
• Remaining time : 184 Days
2. Work Planning on-Site :
• Piling Indicator : 07 – 09 December 2020 (Star Working)
3/12/21
Extension Building PT. Clama Indonesia
3
HSE Update Safety Manhour
3/12/21
Extension Building PT. Clama Indonesia
4
HSE Update Equipment Report
No. Equipment Name QTY Specification Date of Testing Expiry of Certificate Certificate No. STATUS
3/12/21
Extension Building PT. Clama Indonesia
5
HSE Update Initial Work (Temporer)
6 1 2 3 5
Legend :
1. Site Manager Room & GA Room (2 Level)
2. ISA Office & Engineering Room (2 Level)
3. Meeting Room
4. Security
5. Wearhouse & Project Manager Room (2 Level)
6. Toilet
7. Rebar stockyard
3/12/21
Extension Building PT. Clama Indonesia
6
Site Progress Weather Report
No. Day Date Work Hours 00.00 01.00 02.00 03.00 04.00 05.00 06.00 07.00 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 18.00 19.00 20.00 21.00 22.00 23.00 00.00
Sunny
Cloudy
Rainy
Thunderstorm
3/12/21
Extension Building PT. Clama Indonesia
7
Site Progress Manpower List
3/12/21
Extension Building PT. Clama Indonesia
8
Site Progress Overall Progress
Schedule
Day Week Percentage
1 Total 219 35 100%
Used 35 5 4.42%
Remaining 184 30 95.58%
Composite Progress
Until next week This week Until this week
2 Plan 5.27% 1.05% 4.28%
Actual 1.28% 4.42%
Deviation (Dev) 0.23% 0.14%
3/12/21
Extension Building PT. Clama Indonesia
9
Site Progress Site Progress Photo
Compaction
3/12/21
Extention Building PT. Clama Indonesia
10
Site Progress Site Progress Photo
4 4
Piling machine
Excavator
Tandem Roller
Rebar
3/12/21
Extension Building PT. Clama Indonesia
12
Site Progress Plan Works
PERIODE MINGGU 30 Nove mbe r - 06 Dec ember 2020
LAS T WEEK NEXT WEEK
30 November - 06 De cembe r 2020 07 - 13 Des ember 2020
NO ITEM NOTE
30 1 2 3 4 5 6 7 8 9 10 11 12 13
M T W T F S S M T W T F S S
1 Demolis h Toilet as - 7 - 8
2 Compac tion
3 S urvey rafter exis ting
4 Ins tal cle an water pipe
5 Drain S TP exis iting
6 Indikator P ile (14 nos )
7
8
9
10
11
3/12/21
Extension Building PT. Clama Indonesia
13
Documentation RFA - Drawing
REVISION STATUS
No. CODE TITLE SENT TO STATUS Revise Submit Replay Date NOTE
status Date Target Actual
1 PC/PI-CI/001 Pilecap & Tie Beam Layout ISA R0 03-Des-20
2 PC/PI-CI/002 Pilecap & Tie Beam Layout partial 1 ISA R0 03-Des-20
3 PC/PI-CI/003 Pilecap & Tie Beam Layout partial 2 ISA R0 03-Des-20
4 PC/PI-CI/004 Table Tie Beam ISA R0 03-Des-20
5 PC/PI-CI/005 Details & Section Tie Beam ISA R0 03-Des-20
6 PC/PI-CI/006 Details & Section Tie Beam #1 ISA R0 03-Des-20
7 PC/PI-CI/007 Details & Section Tie Beam #2 ISA R0 03-Des-20
8 PC/PI-CI/008 Details & Section Tie Beam #3 ISA R0 03-Des-20
9 PC/PI-CI/009 Details & Section Tie Beam #4 ISA R0 03-Des-20
10 PC/PI-CI/010 Details & Section Tie Beam #5 ISA R0 03-Des-20
11 PC/PI-CI/011 Details & Section Tie Beam #6 ISA R0 03-Des-20
12 PC/PI-CI/012 Details & Section Tie Beam #7 ISA R0 03-Des-20
13 FP/PI-CI/001 Floor Plan Layout ISA R0 03-Des-20
14 FP/PI-CI/002 Floor Plan Layout Partial 01 ISA R0 03-Des-20
15 FP/PI-CI/003 Floor Plan Layout Partial 02 ISA R0 03-Des-20
16 FP/PI-CI/004 Column Pedestal Layout ISA R0 03-Des-20
17 FP/PI-CI/005 Details & Sections #1 Floor Plan ISA R0 03-Des-20
18 FP/PI-CI/006 Details & Sections #2 Floor Plan ISA R0 03-Des-20
19 FP/PI-CI/007 Details & Sections #3 Floor Plan ISA R0 03-Des-20
20 FP/PI-CI/008 Details & Sections #4 Floor Plan ISA R0 03-Des-20
21 ED-01 Column Anchor & Base Plate Plan ISA R0 03-Des-20
22 ED-01A Column Anchor & Base Plate Detail ISA R0 03-Des-20
23 ED-01B Anchor & Base Plate Detail ISA R0 03-Des-20
24 ED-02 Beam Layout EL. ± 4.220 ; ± 8.050 ISA R0 03-Des-20
25 ED-03 Roof Framing Plan ISA R0 03-Des-20
26 ED-04 Roof Purlin Plan ISA R0 03-Des-20
27 ED-05 Portal Frame ISA R0 03-Des-20
28 ED-06 Portal Frame (2) ISA R0 03-Des-20
29 ED-07 Portal Frame (3) ISA R0 03-Des-20
30 ED-08 Portal Frame (4) ISA R0 03-Des-20
31 ED-09 Portal Frame (4) ISA R0 03-Des-20
32 ED-10A Built up Profile ISA R0 03-Des-20
33 ED-11 Detail Connections (1) ISA R0 03-Des-20
34 ED-12 Detail Connections (2) ISA R0 03-Des-20
35 ED-13 Detail Connections (3) ISA R0 03-Des-20
36 ED-14 Detail Connections (4) ISA R0 03-Des-20
37 ED-15 Detail Connections (5) ISA R0 03-Des-20
38 ED-16 Detail Connections (6) ISA R0 03-Des-20
39 ED-17 Section & Detail Canopy ISA R0 03-Des-20
3/12/21
Extention Building PT. Clama Indonesia
14
Documentation RFA - Material
TENDER DOCUMENT APPROVAL PROCURMENT
No. MATERIAL DATE RESULT Delivery NOTE
MERK SPECIFICATION MERK SPECIFICATION PO On Site
Submit Approved A AC R Time
A. STRUCTURE
3 Joint Sealant BASF MasterSeal NP 474 BASF Masterflow 810 24-Nov-20 05-Des-20 V
B. ARCHITECTURE
1 Rolling door Super Teknik Steel plate 1,2 mm Super Teknik Steel plate 1,2 mm 01-Des-20 05-Des-20 V
Jof Metal High Segment 100mm High Segment 100mm
finished powder coating finished powder coating
motor ex. Shinsei Seiki motor ex. Shinsei Seiki
2 Steel door Super Teknik Steel door 55mm thk Super Teknik Steel door 55mm thk 01-Des-20 05-Des-20 V
Jof Metal frame steel plate 2mm frame steel plate 2mm
Steel plate 0.8 mm thk Steel plate 0.8 mm thk
with polyurethane with polyurethane
1 Roof BlueScope Lysaght spandek optima BlueScope Lysaght spandek optima 30-Nov-20 05-Des-20 V
HI-TEN 0.45 TCT HI-TEN 0.45 TCT
Colorbond Colorbond
2 Cladding BlueScope Lysaght spandek optima BlueScope Lysaght spandek optima 30-Nov-20 05-Des-20 V
HI-TEN 0.45 TCT HI-TEN 0.40 TCT
Colorbond Colorbond
B. MEP
1 STP Bio-Tech Cap. 5m3/day 25-Nov-20 03-Des-20 V
3/12/21
Extention Building PT. Clama Indonesia
15
Prevention Covid - 19
Desinfektan
3/12/21
Extension Building PT. Clama Indonesia
16
MEP SECTION – NEW CLEAN WATER INSTALLATION
3/12/21
Expansion Building PT. Clama Indonesia
17
MEP SECTION – STP AS 7 – 8 DEMOLISH
a) STP Discharge
b) STP Excavation
3/12/21
Expansion Building PT. Clama Indonesia
18
MEP SECTION – STP AS 7 – 8 DEMOLISH
3/12/21
Expansion Building PT. Clama Indonesia
19
Documentation RFA – Material - MEP
REVISION STATUS
1 001/AM/R0/PI-CI-MEP/XI/2020 STP - 5M3 BIO TECH ISA B R0 26/11/2020 01/12/2020 05/12/2020
2 004/AM/R0/PI-CI-MEP/XI/2020 COMPRESSED AIR PIPE AIR NET ISA R0 26/11/2020 01/12/2020
3 005/AM/R0/PI-CI-MEP/XI/2020 PVC AW RUCIKA ISA B R0 26/11/2020 01/12/2020 05/12/2020
4 002/AM/R0/PI-CI-MEP/XI/2020 STP - 1M3 BIO TECH ISA R0 30/11/2020 07/12/2020
5 008A/AM/R0/PI-CI-MEP/XI/2020 NYY 2 X (4 X 1C X 185mm) + NYA 95mm KABEL METAL ISA R0 04/12/2020 11/12/2020
6 008B/AM/R0/PI-CI-MEP/XI/2020 NYY 4 x 120mm + NYA 50mm KABEL METAL ISA R0 04/12/2020 11/12/2020
7 008C/AM/R0/PI-CI-MEP/XI/2020 NYY 4 x 16mm + NYA16 mm KABEL METAL ISA R0 04/12/2020 11/12/2020
8 008D/AM/R0/PI-CI-MEP/XI/2020 NYY 4 x 6mm + NYA 6mm KABEL METAL ISA R0 04/12/2020 11/12/2020
9 008E/AM/R0/PI-CI-MEP/XI/2020 NYFGBY 4 x 6mm + NYA 6mm KABEL METAL ISA R0 04/12/2020 11/12/2020
10 008F/AM/R0/PI-CI-MEP/XI/2020 NYFGBY 5 x 4mm KABEL METAL ISA R0 04/12/2020 11/12/2020
11 008G/AM/R0/PI-CI-MEP/XI/2020 NYFGBY 3 x 4mm KABEL METAL ISA R0 04/12/2020 11/12/2020
12 009A/AM/R0/PI-CI-MEP/XI/2020 NYM 3 X 2,5mm KABEL METAL ISA R0 04/12/2020 11/12/2020
13 009B/AM/R0/PI-CI-MEP/XI/2020 NYY 4 X 2,5mm + NYA 2,5mm KABEL METAL ISA R0 04/12/2020 11/12/2020
14 009C/AM/R0/PI-CI-MEP/XI/2020 NYY 4 x 4mm + NYA 4mm KABEL METAL ISA R0 04/12/2020 11/12/2020
15 011/AM/R0/PI-CI-MEP/XI/2020 HIGH IMPACT PVC CONDUIT & ACCESSORIES LEGRAND ISA R0 04/12/2020 11/12/2020
3/12/21
Extention Building PT. Clama Indonesia
20
MEP SECTION – THIS WEEK SCHEDULE
3/12/21
Expansion Building PT. Clama Indonesia
21
MEP SECTION – VRF SCHEDULE TENDER DRAWING
3/12/21
Expansion Building PT. Clama Indonesia
22
MEP SECTION – VRF SCHEDULE FOR CONSTRUCTION
DRAWING
3/12/21
Expansion Building PT. Clama Indonesia
23
Thank you
3/12/21
Extention Building PT. Clama Indonesia
24