SMELTING – GRESIK
NEW SULPHURIC ACID PLANT 1,350 TPD
PROJECT SCHEDULE
Vendor Document No: 4EXP-V-500-127-03-002
PO NO. : 4EXP-R-500-127-03
FOR APPROVAL
KNH
PT FEROS DWITAMA
PT. SMELTING – GRESIK
NEW SULPHURIC ACID PLANT 1,350 TPD
Vendor Doc No: 4EXP-V-500-127-03-002
PROJECT SCHEDULE
Rev. No: [2] Page 2 of 4
CONTENTS
1. GENERAL ............................................................................................................................. 4
2. REFERENCE ........................................................................................................................ 4
3. DEFINITION .......................................................................................................................... 4
4. ATTACHMENT ...................................................................................................................... 4
1. Projet Schedule .................................................................................................... 4
PT. SMELTING – GRESIK
NEW SULPHURIC ACID PLANT 1,350 TPD
Vendor Doc No: 4EXP-V-500-127-03-002
PROJECT SCHEDULE
Rev. No: [2] Page 3 of 4
Revision History
1. GENERAL
Project Schedule are the schedule form process of purchase until finished for Equipment of Fire
Fighting New Sulphuric Acid Plant 1,350 TPD Project.
2. REFERENCE
3. DEFINITION
4. ATTACHMENT
1. Project Schedule
PT Feros Dwitama
Fire Fighting System (New Sulphuric Acid Plant Project)
3 Process of Purchase Order Fire Fghting System by Principal 3 days Tue 26/04/22 Thu 28/04/22
4 Preparation & Approval for Key Document Engineering 14 days Fri 29/04/22 Wed 18/05/22
6 - Fabrication of Fire Hydrant (Local, Indonesia) 30 days Thu 19/05/22 Wed 29/06/22
7 - Fabrication of Fire Hose Cabinet (Local, Indonesia) 30 days Thu 19/05/22 Wed 29/06/22
8 - Fabrication of Fire Extinguisher (Local, Indoensia) 30 days Thu 19/05/22 Wed 29/06/22
9 - Fabrication of Fire Extinguisher Box (Local, Indoensia) 30 days Thu 19/05/22 Wed 29/06/22
10 - Fabrication of Fire Hose (Tipsa, Spain) 80 days Thu 19/05/22 Wed 07/09/22
11 - Fabrication of Hand Nozzle (Tipsa, Spain) 80 days Thu 19/05/22 Wed 07/09/22
12 Delivery from Manufacturing to Workshop PT Feros Jakarta 20 days Mon 12/09/22 Fri 07/10/22
15 Delivery from Jakarta to Site (Gresik) 5 days Tue 18/10/22 Mon 24/10/22