Professional Documents
Culture Documents
CONTRACTOR TO COMPLETE
PR2ME-K000-MGT-TMP-006_0
24-AUGUST-2022
Project : No Document K017-T12-0002
Batu Hijau Process Expansion
Project Date 25/05/2023
Title : Revision 00
K-017 Temporary Jetty Page 1 of 47
Title: Revision 00
Temporary Jetty Page 2 dari 47
Table of Contents
1. INTRODUCTION ............................................................................................................................................................................................ 4
1.1 General ...................................................................................................................................................................................... 4
1.2 Scope ......................................................................................................................................................................................... 4
1.3 Reference.................................................................................................................................................................................. 4
1.4 Responsibility ........................................................................................................................................................................... 4
2. BARGE AND LCT SELECTION .....................................................................................................................................................................5
2.1 Barge..........................................................................................................................................................................................5
2.2 LCT 2000 DWT ..........................................................................................................................................................................6
2.3 Cargo.......................................................................................................................................................................................... 7
3. JETTY COORDINATE & PLAN.....................................................................................................................................................................9
3.1 Jetty Coordinate......................................................................................................................................................................9
3.2 Jetty Coordinate against the Sea Plane Path ...................................................................................................................11
4. DETAIL ENGINEERING DESIGN OF TEMPORARY JETTY.........................................................................................................................12
4.1 Jetty Elevation ....................................................................................................................................................................... 13
4.2 Bollard Design ........................................................................................................................................................................ 15
4.3 Lighting Plan .......................................................................................................................................................................... 20
4.4 Roll of Operation for Heavy Cargo Simulation .................................................................................................................21
4.5 Dump Truck and Trailer In/Out Simulation .................................................................................................................... 23
4.6 Dump Truck Ground Bearing Pressure ............................................................................................................................24
4.7 Formula of Settlement Calculation ....................................................................................................................................24
4.8 Settlement Calculation ........................................................................................................................................................ 26
4.9 Calculation Result Based on Finite Elements Method With Software Plaxis As Device ......................................... 29
5. EQUIPMENTS AND MATERIALS .............................................................................................................................................................. 32
5.1 2 units of Excavator ............................................................................................................................................................. 32
5.2 1 unit of Dozer D85R ............................................................................................................................................................ 32
5.3 1 unit of Vibro Roller 10 Ton ................................................................................................................................................ 33
5.4 Geotextile Woven .................................................................................................................................................................. 33
5.5 Sand Filling Material............................................................................................................................................................. 34
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 3 dari 47
6. MANPOWER .............................................................................................................................................................................................. 35
7. MOBILIZATION AND DEMOBILIZATION .................................................................................................................................................. 35
8.1 Mobilization of Manpower ................................................................................................................................................... 35
8.2 Mobilization of Equipment ................................................................................................................................................... 36
8. CONSTRUCTION METHOD STATEMENT ................................................................................................................................................. 38
9. SCHEDULE ................................................................................................................................................................................................ 40
10. ENVIRONMENTAL IMPACT .......................................................................................................................................................................41
11. CONCLUSSION...........................................................................................................................................................................................41
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 4 dari 47
1. INTRODUCTION
1.1 General
This general procedure was prepared for PT. Amman Mineral Nusa Tenggara Roll On/Roll Off operation and also
intended to build temporary jetty for unloading 350 Tons MP Column + LP Column from 270 feet barge or LCT
2000 DWT using Multi-Axle Trailer to quay.
Other civil engineering calculation will be provided once this procedure is approved
1.2 Scope
This procedure covers PT. Amman Mineral Nusa Tenggara intended to build the temporary jetty for landing and
beaching the 270 feet barge and LCT 2000 DWT.
1.3 Reference
- UU No. 17 tahun 2008 tentang Pelayaran.
- Peraturan Pemerintah RI Nomor 27 Tahun 2012 tentang Izin Lingkungan.
- Peraturan Pemerintah RI Nomor 81 tahun 2003 tentang kenavigasian
- Peraturan Pemerintah RI Nomor 69 tahun 2001 tentang Kepelabuhanan
- Undang Undang No. 1 Tahun 1970 tentang Keselamatan
- Permanekertrans RI No. 1 Tahun 1980 tentang Keselamatan Konstruksi Sipil
- Permenaker RI No. 5 Tahun 1995 tentang Pesawat Angkat dan Angkut
- Permenaker RI No. 5 Tahun 1996 tentang K3L
1.4 Responsibility
The Project Manager is responsible for the approval of this document.
The HSE Manager is responsible for the monitoring, verification and issue of this document and of its subsequent
revisions.
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 5 dari 47
2.1 Barge
Title: Revision 00
Temporary Jetty Page 6 dari 47
Title: Revision 00
Temporary Jetty Page 7 dari 47
2.3 Cargo
Gas Turbine – LNG Power Plant
Temporary Jetty will be used for roro operation for cargo weight 350 tons and with trailer configuration 24
axlelines with axle Load is 7.9 tons and Ground Bearing Pressure is 3.5 ton/m2
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 8 dari 47
Temporary Jetty will be used for roro operation for cargo weight 350 tons and with trailer configuration 48 axlelines
with axle Load is 5.9 tons and Ground Bearing Pressure is 2.6 ton/m2
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 9 dari 47
The Jetty coordinate is from 8°53'51.58"S, 116°44'54.70"E and 8°53'52.21"S 116°44'53.86"E to 8°53'58.45"S,
116°44'59.54"E and 8°53'58.69"S, 116°44'59.22"E
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 10 dari 47
Title: Revision 00
Temporary Jetty Page 11 dari 47
Title: Revision 00
Temporary Jetty Page 12 dari 47
Title: Revision 00
Temporary Jetty Page 13 dari 47
Title: Revision 00
Temporary Jetty Page 14 dari 47
Title: Revision 00
Temporary Jetty Page 15 dari 47
Title: Revision 00
Temporary Jetty Page 16 dari 47
WIND FORCE = F Wind = SHIP BODY AREA ABOVE WATER X P wind X 1.3
= (2 x ( H-T)) x P )
= 23012.275 Kg
= 23.012275 TON
P Wind = 41 Kg/m²
CURRENT FORCE = F Current = AREA OF THE SHIP BODY IN THE WATER X P current
= (( P X L) + (2 X ( P X T ))
= 1609.25 Kg
V = Current Speed
= 0.2 m/s
P Current = ϒ x V²
2xg
= 2.089704383 Kg/m²
ϒ = Weight of Sea Water
= 1025 Kg/m²
F Current = 2208.042559 Kg
= 2.208042559 TON
SHIP MOORING FORCE (BOLLARD TENSILE FORCE) = F Wind + F Current
F bollard = 25.22031756 TON
Title: Revision 00
Temporary Jetty Page 17 dari 47
Title: Revision 00
Temporary Jetty Page 18 dari 47
WIND FORCE = F Wind = SHIP BODY AREA ABOVE WATER X P wind X 1.3
= (2 x ( H-T)) x P )
= 26362.31858 Kg
= 26.36231858 TON
P Wind = 41 Kg/m²
CURRENT FORCE = F Current = AREA OF THE SHIP BODY IN THE WATER X P current
= (( P X L) + (2 X ( P X T ))
= 2287.3395 Kg
V = Current Speed
= 0.2 m/s
P Current = ϒ x V²
2xg
= 2.089704383 Kg/m²
ϒ = massa jenis air laut
= 1025 Kg/m²
F Current = 2890.022303 Kg
= 2.890022303 TON
Title: Revision 00
Temporary Jetty Page 19 dari 47
Title: Revision 00
Temporary Jetty Page 20 dari 47
Title: Revision 00
Temporary Jetty Page 21 dari 47
Title: Revision 00
Temporary Jetty Page 22 dari 47
Title: Revision 00
Temporary Jetty Page 23 dari 47
Title: Revision 00
Temporary Jetty Page 24 dari 47
Description:
Cc : Compression Index
Cs : Swelling Index
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 25 dari 47
Description:
Influence graph
Description:
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 26 dari 47
Title: Revision 00
Temporary Jetty Page 27 dari 47
From the analysis by analytical method, the jetty is able to carry a load of 6,85 T/m2 at surface level
Variation of Tv with U
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 28 dari 47
Title: Revision 00
Temporary Jetty Page 29 dari 47
4.9 Calculation Result Based on Finite Elements Method With Software Plaxis As Device
Title: Revision 00
Temporary Jetty Page 30 dari 47
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 31 dari 47
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 32 dari 47
Title: Revision 00
Temporary Jetty Page 33 dari 47
Title: Revision 00
Temporary Jetty Page 34 dari 47
Sand filling comes from the beach and sedimentation in the area below will be dredged to a depth of 1 meter
Title: Revision 00
Temporary Jetty Page 35 dari 47
2. Gravel
Gravel will be prepared from around West Nusa Tenggara
6. MANPOWER
• 1 Person Project Manager
• 2 Person Supervisor
• 4 Person Operator
• 12 Person Labor
• Speedboat from Kayangan Port to Poto Tano Port = 20,5 km (1,5 hours)
Title: Revision 00
Temporary Jetty Page 36 dari 47
Northern Route
Southern Route
Title: Revision 00
Temporary Jetty Page 37 dari 47
• Trucking from Jamuna Jetty to Jago 10 Laydown or designated Parking Area by AMNT (1 day)
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 38 dari 47
The construction of temporary jetty will include the following two main items:
The jetty structure will be supported with jumbo sandbag on the front and side before being dumped with quarry course.
This is also to optimize quality and minimize the potential environment impacts and risk inherent in marine working like
tendering the barge to the jetty, or against the sea wave.
Typically the construction of the temporary jetty would be staged from foreshore using excavator, operators, and labor
plus supervision. Dozer will be required to leveling the ground and maybe compactor can be used.
Bollard installation will use long arm excavator and embedded to the sea bed up to 3 meter in order to get bollard
strength more than 9 Tons against tensile force. Distance of the bollard will be based on the mooring arrangement.
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 39 dari 47
Working area on the foreshore will be limited for the dump truck traffic and as necessary will be kept to be limited to the
safe working minimum to undertake the construction activities. Vehicles access to the jetty will be strictly controlled and
working areas and access track will be clearly remarked and fenced as appropriate with line and sign.
Fuel will be required for the diesel power of our supported equipment and to minimize the number of fuel deliveries, we
will use our fuel drum to support our operation.
The jetty construction contractor will be required to demonstrate that detailed working practices and construction
methods are appropriate to ensure that sufficient measures will be in place to prevent construction materials and
equipment from entering the Project area.
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 40 dari 47
9. SCHEDULE
The planning implementation schedule is 4 months with details below:
SCHEDULE
WEIGHT ( 1ST MONTH 2nd MONTH 3rd MONTH 4th MONTH
NO SCOPE OF WORK VOLUME UNIT
%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 PERMIT 1 LS 2% 0.02
2 PREPARATION 1 LS 1% 0.01
3 MOBILIZATION 1 LS 9% 0.05 0.05
4 BOWLANK MEASUREMENT AND INSTALLATION 1 LS 3% 0.02 0.02
5 JUMBO BAG FILLING 1 LS 5% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 JUMBO BAG INSTALLATION 1 LS 34% 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
7 GEOTEXTILE INSTALLATION 1 LS 6% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8 LANDFILL 1 LS 15% 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
9 COMPACTION 1 LS 16% 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
10 INSTALATION BOULDER 1 LS 6% 0.02 0.02 0.02 0.02
TOTAL 100%
PROGRESS PER WEEK 100% 9.9 6.6 3.5 4.8 6.1 6.1 6.1 6.1 6.1 6.1 6.1 6.1 7.7 7.7 7.7 3.0
PLANING
CUMULATIVE 9.9 16.6 20.1 24.8 31.0 37.1 43.2 49.3 55.5 61.6 67.7 73.8 81.6 89.3 97.0 100.0
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 41 dari 47
11. CONCLUSION
- The settlement that will occur at quay depth of 5.5 m is 1,761 m with 5,13 years of Long Term Settlement. As this
is Temporary Jetty that usage for short period of usage then the Long Term Settlement can be not calculated.
We only use Immediate Settlement as from the analysis using the finite element method (Plaxis), Total Extreme
Immediate Settlement is 25,15 x 10-3 m = 2,515 cm
- Jetty will be passed by cargo weighing 350 tons and distributed to 24 axles. Axle Load is 7,9 tons per axle line
with Ground Bearing Pressure is 3,5 ton/m2. Based on Jetty capacity calculation, the jetty is able to carry a
load of 6,85 T/m2. So, 3,5 ton/m2 < 6,85 ton/m2 (Ok)
- There are 6 points of mooring, each point of Boulders construct using 6 Pcs of Reinforce Concrete Block with
weight @2,4 tons. Total self weight of each set of Boulders is 6 x 2,4 tons = 14,4 tons. Boulder force maximum
is 4,75 tons for LCT 2000 DWT, 4,75 tons < 14,4 tons (Ok) and 5,5 tons for Barge 270 feet, 5,5
tons < 14,4 tons (Ok)
- Installation of Temporary Jetty include processing of permit will takes 4 months and demolished of Temporary
Jetty can be done for 2 months.
- Design of Temporary Jetty is using maximum for suitable LCT and Tug Barge. LCT is 2000 DWT and Barge is
maximum 270 feet. Operation for Loading/Discharging can be done in High – Low Tide with Ro-Ro (Roll On-Roll
Off) Method.
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 42 dari 47
APPENDIX
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 43 dari 47
Existing Condition:
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 44 dari 47
Title: Revision 00
Temporary Jetty Page 45 dari 47
During construction:
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 46 dari 47
Previous project: 250 tons load through the jetty using multiaxle trailer
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 47 dari 47
CONTRACTOR TO COMPLETE
PR2ME-K000-MGT-TMP-006_0
24-AUGUST-2022
Project : No Document K017-T12-0003
Batu Hijau Process Expansion
Project Date 25/05/2023
Title : Revision 0
K-017 Temporary Jetty Page 1 of 14
Table of Contents
1. Introduction ........................................................................................................................................................................................................... 3
2. Purpose and Scope .............................................................................................................................................................................................. 3
3. Document Control ................................................................................................................................................................................................ 3
4. Reference Documents......................................................................................................................................................................................... 3
4.1 Drawings (Design Drawing, Boulder Drawing, and Layout) .............................................................................................................4
5. Definitions, Terms and Abbreviations ..............................................................................................................................................................7
6. Responsibility .........................................................................................................................................................................................................7
7. Materials, Equipment and manpower ...............................................................................................................................................................7
7.1 Materials.......................................................................................................................................................................................................7
7.2 Equipment.................................................................................................................................................................................................... 8
7.3 Personel/Workforces .............................................................................................................................................................................. 8
8. Methodology / Procedure .................................................................................................................................................................................. 8
8.1 Installation Piling Fender Using Spiral Steel Pipe ............................................................................................................................. 8
8.2 Installation Jumbo Bag ........................................................................................................................................................................... 13
9. Daily Inspection ...................................................................................................................................................................................................13
10. Quality Control .....................................................................................................................................................................................................13
11. Health, Safety and Environmental ................................................................................................................................................................... 13
11.1 General Policy ...........................................................................................................................................................................................13
11.2 Health, Safety and Environmental Hazards ....................................................................................................................................... 13
11.3 Protective and Safety Equipment......................................................................................................................................................... 14
11.4 Emergency Procedures .......................................................................................................................................................................... 14
Project: No Document K017-T12-0003
Jago Beaching Jetty Date 25/05/2023
Title: Revision 0
Temporary Jetty Page 3 dari 14
1. INTRODUCTION
A temporary Jetty shall be built at the project/mining area to facilitate berthing of barges for loading/unloading materials
and equipment. This extension work aims for the ship berthing method which previously could only be used with the Ro-Ro
method, with the addition of this work later the temporary jetty can be used for the long side method.
3. DOCUMENT CONTROL
• The document governing the preparation, registration, approval, distribution and amendment/revision of this method
statement will be according to requirement.
• The requirements for document numbering are addressed in the project specific document control procedure.
• This method statement is a controlled document, and will be distributed as such to those detailed on the Internal parties
maintained by the Document Controller, while external distribution will be via the Secretary.
4. REFERENCE DOCUMENTS
The following documents define the requirements to be employed to demonstrate compliance of the works defined in this
method Statement :
Project: No Document K017-T12-0003
Jago Beaching Jetty Date 25/05/2023
Title: Revision 0
Temporary Jetty Page 4 dari 14
The Jetty coordinate is from 8°53'51.58"S, 116°44'54.70"E and 8°53'52.21"S 116°44'53.86"E to 8°53'58.45"S, 116°44'59.54"E and
8°53'58.69"S, 116°44'59.22"E
6. RESPONSIBILITY
- The Project Manager is responsible for appoint site supervisory personnel to organize, coordinate, and oversee the
execution of the work detailed in this method statement.
- The Site Manager is responsible for the organization and coordination of the entire work detailed in this method
statement.
- The Marine work section engineer is responsible for the execution of the works detailed in this method statement. He
will be responsible for instructing the Foremen / Supervisor about the requirements of the contract, including all
restrictions, safety regulations, scope of work and time schedule. In addition, he will be responsible for related logistic
matters and all matters related to HSE and the quality of the works.
- The Supervisor/Foreman is responsible for the day-to-day implementation and supervision of the works detailed in this
method statement.
- Assigned HSE staff is responsible to assist the construction team to develop safe methods of working and to monitor
implementation of the controls as required.
8. METHODOLOGY / PROCEDURE
8.1 Installation Piling Fender Using Spiral Steel Pipe
- Before starting the erection process, first determine the coordinate points to be designated.
- After the erection point is ready, it must then prepare a mount location that is considered hard and must be able to
support the weight of the crane.
- Preparing supporting equipment in the form of 2 sets of welding travo, generator set, 1 set of cutting torch, iron
cutting grinders placed on special racks made of iron frames and roofed.
- After the crane and supporting equipment have been in the planned position, then the crane first lifts the leader pole
that has previously been kited.
- For the leader pole assembly stage, the leader pole consists of a connection connection that has been assembled by
the manufacturer, which is 4.5 m long.
- Then the pieces of the leader pole are connected until they reach a height of 22 m
- The leader cut splicing usesbolts that have been assembled by the manufacturer.
- Next, set the hook on the pole leader which functions to lift the hammer
- Then connect the sling crane link to the leader pole to lift the hammer, and attach the hammer to the leader pole.
Project: No Document K017-T12-0003
Jago Beaching Jetty Date 25/05/2023
Title: Revision 0
Temporary Jetty Page 9 dari 14
- After the erection tool is ready, then the right sling takes the piles that have been mobilized with the help of excavators
and dump trucks from the stokpile to the erection site.
- The piles that have been tapered will be taken first, andinserted into the bottom of the leader's pile holder which
functions to position the pile at the point of erection and the leader's pile.
- After the pile enters the bottom mount hole of the leader pole, then the hammer cap in the n positionto the top pile.
- After the hammer cap has been in the planned position, the hammer beating is carried out to the level that has been
planned for the cessation of the first pile erection, which is 1 – 1.5 m above the water level.
- After the cessation of erection, the pile head is cut if it is considered damaged caused by a hammer blow, the cutting
is carried out aimed at obtaining a good pile level and circle so as to facilitate the process of smashing.
- After cutting the first pile head, then the sling crane takes the second pile and the same process is carried out as the
first stage, which is to insert the pile into the leader mount hole and position the hammer cap into the upper pile ti.
- After that, position the second pile over the first pile and a welding process is carried out to connect the two piles.
- Before the process of cutting the pile head and welding, it is carried out first andthe manufacture of working
scaffolding made of iron frame using elbow iron with scaffolding legs from iron pipes with scaffolding floors using iron
/ plate grating. This scaffolding serves for the place of footing when the welder performs the work of cuttingpiles and
the process of welding pile joints.
- After the joint welding process has been completed, the erection process is carried out to a predetermined level.
- This process is carried out repeatedly at each point of the pile.
- After the erection is complete, the installation of the bracing / pile stiffener is then carried out.
- Bracing or pile stiffeners have been cut to a predetermined size.
- Then next the bracing / stiffening of the piles that have been cut, is positioned in the position between the two pile
points with the help of an excavator or crane.
- After the bracing/stiffening of the pile has been in the desired position, it is further encapsulatedand welded.
- The installation process of bracing / stiffening piles is carried out according to the existing drawings.
- After the erection process is complete, the process of disassembling the pile tool is then carried out
- The dismantling of the stake begins with lowering the leader's mast to the ground.
- After that, remove the hammer hook so that the hammer and leader separate.
- Then the leader pole pole is separated back into pieces of 4.5 m long leader pole pieces by removing the locking bolts.
- After being removed, the leader pole and hammer piece are lifted onto the truck to be demobilized along with the crane
and other equipment.
Project: No Document K017-T12-0003
Jago Beaching Jetty Date 25/05/2023
Title: Revision 0
Temporary Jetty Page 10 dari 14
- Fix lifting tackles to the lifting eyes of the temporary jetty and be ready for hoisting, approved lifting plan shall be on
board prior to commence the operation.
- Hoist the jumbo bag by using excavator under supervision of lifting supervisor and banks men. Workers will control
the movement of the load using guide ropes by following instructions of the lifting supervisor.
- Place the jumbo bag in position and verify lines and levels. Detach lifting tackles if it satisfactory or adjust it otherwise.
- Fill quarry run material inside the jumbo bag by using excavator. The material will be transported to the site by dump
trucks. The material will be filled up to the required level and graded as per profile. The wearing surface (top surface)
of the access to the jetty will be smoothed by laying a 100 mm thick layer of fine material at its top.
- Place rock armor at front of the temporary jetty using the excavator.
9. DAILY INSPECTION
Necessary Daily inspection for temporary jetty activities will be obtained prior to commencement of the work.
a. Form
b. Checklist
• Tripping hazards
• Manual handling/ handling of hazardous materials
• Slip, trips and falls
• Traffic accident
• Trapping injuries
• Hand injuries
• Defective plant and equipment
• Falling materials Lifting operation
Project: No Document K017-T12-0003
Jago Beaching Jetty Date 25/05/2023
Title: Revision 0
Temporary Jetty Page 14 dari 14
All personnel will be handed out these items during their site induction.
• Helmets
• Safety glasses
• Safety shoes
• Work gloves
• High visibility vests or Life Jackets
Title: Revision 00
Temporary Jetty Demolition Page 1 of 20
METHOD STATEMENT
TEMPORARY JETTY DEMOLITION
Title: Revision 00
Temporary Jetty Demolition Page 2 of 20
TABLE OF CONTENTS
1. INTRODUCTION ..................................................................................................................................... 3
2. PURPOSE AND SCOPE ....................................................................................................................... 3
3. DOCUMENT CONTROL ....................................................................................................................... 4
4. REFERENCE DOCUMENTS ................................................................................................................ 4
4.1 Drawings Temporary Jetty Location .................................................................................... 4
4.2 Temporary Jetty Design ............................................................................................................ 5
5. DEFINITIONS, TERMS AND ABBREVIATIONS ........................................................................ 11
6. RESPONSIBILITY................................................................................................................................. 12
7. EQUIPMENT AND MANPOWER .................................................................................................. 12
7.1 Equipment ..................................................................................................................................... 12
7.2 Personel/Workforces ............................................................................................................ 12
8. METHODOLOGY AND PROCEDURE ........................................................................................... 13
8.1 Removing Fender....................................................................................................................... 13
8.2 Removing Lamppost ................................................................................................................ 14
8.3 Removing Temporary Jetty Platform ................................................................................ 14
8.4 Cleaning and Demob ................................................................................................................ 16
9. DAILY INSPECTION............................................................................................................................ 17
10. QUALITY CONTROL ........................................................................................................................... 17
11. HEALTH, SAFETY, AND ENVIRONMENTAL ............................................................................. 17
11.1 General Policy ........................................................................................................................... 17
11.2 Health, Safety, and Environmental Hazards ................................................................ 17
11.3 Protective and Safety Equipment ..................................................................................... 18
11.4 Emergency Procedures ....................................................................................................... 18
Project: No Document LMU/TJD-001/XII/2022
Jago Temporary Jetty Date 23/12/2022
Title: Revision 00
Temporary Jetty Demolition Page 3 of 20
1. INTRODUCTION
A temporary jetty has been constructed at the project/mining site to facilitate the berthing
of barges for the loading/unloading of materials and Equipment. The main elements of the
temporary wharf consist of the access causeway and structures/sandbags, which must
be installed at the sea end and the side of the causeway. Because it is only temporary after
the project is completed, the temporary Jetty will be removed and returned to its pre-
development condition.
Title: Revision 00
Temporary Jetty Demolition Page 4 of 20
3. DOCUMENT CONTROL
• The document governing the preparation, registration, approval, distribution and
amendment/revision of this method statement will be according to requirements.
• The requirements for document numbering are addressed in the project-specific
document control procedure.
• This method statement is a controlled document and will be distributed to those
detailed on the Internal parties maintained by the Document Controller, while
external distribution will be via the Secretary.
4. REFERENCE DOCUMENTS
The following documents define the requirements to be employed to demonstrate
compliance with the works defined in this method Statement:
Title: Revision 00
Temporary Jetty Demolition Page 5 of 20
Title: Revision 00
Temporary Jetty Demolition Page 6 of 20
The front view of the sandbag arrangement on the Quayside of the Temporary Jetty can be
seen as follows,
Title: Revision 00
Temporary Jetty Demolition Page 7 of 20
Title: Revision 00
Temporary Jetty Demolition Page 8 of 20
Title: Revision 00
Temporary Jetty Demolition Page 9 of 20
The fender pole uses a pile structure to the seabed, as shown below,
Title: Revision 00
Temporary Jetty Demolition Page 10 of 20
Title: Revision 00
Temporary Jetty Demolition Page 11 of 20
• Tidal is fluctuations in sea level as a function of time due to the gravitational pull
of objects in the sky, especially the sun and moon, on the mass of seawater on
earth.
The following is the condition of the tides in the jetty area:
- LWS Lowest Water Sea (+0.64 m)
- HWL Highest Water Level (+3.2 m)
- MSL Mean Sea Level (+2.56 m)
Project: No Document LMU/TJD-001/XII/2022
Jago Temporary Jetty Date 23/12/2022
Title: Revision 00
Temporary Jetty Demolition Page 12 of 20
6. RESPONSIBILITY
7.2 Personel/Workforces
• Project Manager : 1 Person
• Site Manager : 1 Person
• Engineer : 1 Person
• Supervisor : 2 Person
Project: No Document LMU/TJD-001/XII/2022
Jago Temporary Jetty Date 23/12/2022
Title: Revision 00
Temporary Jetty Demolition Page 13 of 20
• Labour : 10 Person
• The operator of Heavy Equipment : 2 Person
Title: Revision 00
Temporary Jetty Demolition Page 14 of 20
Title: Revision 00
Temporary Jetty Demolition Page 15 of 20
Title: Revision 00
Temporary Jetty Demolition Page 16 of 20
Title: Revision 00
Temporary Jetty Demolition Page 17 of 20
9. DAILY INSPECTION
Daily inspections for the demolition of the temporary Jetty activities will be obtained before
the commencement of the work.
1. Form
2. Checklist
Title: Revision 00
Temporary Jetty Demolition Page 18 of 20
• Dust Generation
• Sediment re-suspension
• Waste Generation
• Marine safety
Controls will be implemented to minimize these hazards as set out in the HSE risk
assessment.
Title: Revision 00
Temporary Jetty Demolition Page 19 of 20
c. Responsibilities
HSE, Supervisor, Operational, and all Personnel
Oversees the implementation of pre-job safety meetings with all personnel involved
in the mobilization process and ensures that all trucks and cranes have been
inspected before use, as well as work permits and JSA. Supervise all equipment
loading and unloading activities to ensure the operation is carried out safely. If the
supervisor feels that the procedure is not safe, the supervisor must STOP all
activities and discuss them with the entire crew.
d. Communication
The communication process during the mobilization process will be carried out
using a cellular telephone and HT Radio
The communication process refers to the list of telephone numbers when an
emergency is attached.
Project: No Document LMU/TJD-001/XII/2022
Jago Temporary Jetty Date 23/12/2022
Title: Revision 00
Temporary Jetty Demolition Page 20 of 20
CALCULATION OF STEEL PIPE FENDER
Section Properties
Diameter Of Steel Pile
OD = 40,64 cm
ID = 38,24 cm
Thick
T = 1,2 cm
Pile area
A = 148,7 cm2
Modulus Inertia
I = 28900 cm4
Steel Grade 3
fy = 310 MPa = 2400 kg/cm2
Modulus of Elasticity (E)
Es = 200000 MPa = 2000000 kg/cm2
Safety Factor (SF)
SF = 1
Pile Analysis
The calculation of fender steel piles is carried out by the FEM (Finite Element Methode)
using the SAP2000 auxiliary program. The criteria used are as follows:
• Site class
From the soil data it is known that the majority of the soil is soft. So based on SNI
1726:2019 obtained Site class = SE (soft soil).
• Acceleration of bedrock at the apex ground level (PGA), short period (SS), and acceleration
of bedrock at a period of 1 second (S1) in the rsa.ciptakarya.pu.go.id as follows,
PGA = 0,4842 g
SS = 1,0706 g
S1 = 0,4215 g
Then-liberator on the structure as shown in Figure 2.
• Deflection Analysis
Deflection in the fender structure must not exceed the h/200 clearance deflection in
accordance with SNI 03-1729-2002 . The deflection values of the fender structure as
shown in Table 1.
Mast Data,
OD = 40,64 cm E = 2000000 MPa
t = 1,2 cm EA = 29740000 kn
w = 117 kg/m EI = 578000 kN.m2
A = 148,7 cm2 W = 0,920899 kN/m
I = 28900 cm4
The results of the analysis of the Plaxis auxiliary program are in the form of soil stress and
deformation of the structure. The total decrease occurred by 52.11 mm. Meanwhile, the SF
obtained was 2,131. As for the deformation and stress of the soil that occurs as shown in
Figure 4, Figure 5, Figure 6 and
P= IxAxH
1000 x K
Alloy : Aluminium
Consumption Rate : 2400 Ahr/ Kg
Life Span : 3 years 26280 hours
Utilization Factor : 0.9
Alloy : Aluminium
Consumption Rate : 2400 Ahr/ Kg
Life Span : 3 years 26280 hours
Utilization Factor : 0.9
Reference spec
https://www.asmarines.com/Jual-Aluminium-Anode
D T
28.000
22.500
17.000
6.433
33.500
16.756
T T 18 T T 22 T T 28
4.275
9.045
21.950
3.500 11.500
3.000
2.000 2.000
R2
8.0
00
-6.0
R2
-5.0
2.50
0
20.732 -4.0
R1
7.0
00
5 1
0
7.62
9
22.8
2 1
50
2.00
3.00
-3.0
0
0
-2.0
28
28.7
13.7
28
00
10.0 8.00
0
1. Existing plan W E
2. Additional purpose
Meters
1. Dimension are in millimeter
10 0 10 20
1:203.298
-7.0
-6.0
OAD C A T
21.619
18.227
14.852
33.500
6.433
23.791
13.500
3.500 11.500
3.000
2.000 2.000
O D EA I P ESS E
8 1 2 0
7
-6.0
R2
1.6
-5.0
91
20.732 -4.0
R1
8
.22
7
R1
2B
4 .85
RO
INE
ENGOM 2B
W
CREACE
SP
2
E
STOR
DN
RN
STEAR
GE
UP
0
7.62
22.8
0 0
0
50
5
0
W
CREACE
2
2B
5
SP
2.00
DN
1
2B
3
3.00
-3.0
1
UP
LEY INE
GAL ENGOM
0
RO
RN
STEAR
0
GE
-2.0
28
28.7
13.7
28
00
10.0 8.00
0
1. Existing plan W E
2. Additional purpose
Meters
1. Dimension are in millimeter
10 0 10 20
1:203.298
-7.0
-6.0
4.50
8.00
-8.0
-7.0
0
53.8
N:9016445.99
E:472355.74
-6.0
-5.0
N:9016428.54
20.732 -4.0 E:472363.26
7.00
00
2B
32.0
INE
ENG M 2B
W
CRE CE
ROO SPA
2
78.1
RE
STO
DN
RN
STE R
GEA
UP
N:9016425.63
E:472396.90
22.8
0
7.62
0
12.5
W 2.009
CRE CE 2B
50
SPA
0
DN
13.5
2B
N:9016433.31 UP
GAL
L EY INE
ENG M
ROO
E:472326.35 RN
STE R
GEA -3.0
-2.0
-1.0 17
11.0
19.0
00
N:9016415.86 0
E:472333.88
28
28.7
N:9016393.71
E:472313.73
13.7
8 2
. 0 0 0
10
N
1. Trailer 40ft swept simulation
UOY 2.
3.
Existing plan
Additional purpose W E
1:465.223
1 9 5 1
2
10
790
-8.0
-7.0 N:9016445.99
E:472355.74
-6.0
-5.0
23.9
N:9016428.54
20.732 -4.0 E:472363.26
43
N:9016425.63
E:472396.90
22.8
0
7.62
50
N:9016433.31
E:472326.35 -3.0
-2.0
-1.0 17
11.0
19.0
00
N:9016415.86 0
E:472333.88
28
28.7
N:9016393.71
E:472313.73
13.7
28
00
10.0
2. Existing plan
W E
3. Additional purpose
-7.0 0
8.00 1:465.223
-6.0 -5.0
-4.0 -3.0 -2.0
4.50
8.00
-8.0
0
53.8
-7.0 N:9016445.99
E:472355.74
-6.0
-5.0
N:9016428.54
20.732 -4.0 E:472363.26
19.5
7.00
6
2B
INE
ENG M W
CRE CE
1
2B
ROO SPA
2
78.1
RE
STO
DN
RN
STE R
GEA
UP
N:9016425.63
E:472396.90
22.8
0
7.62
0
12.5
W
CRE CE
50
2B
SPA
0
DN
13.5
2B
N:9016433.31 UP
GAL
LEY INE
ENG M
ROO
E:472326.35 RN
STE R
GEA -3.0
-2.0
-1.0 17
11.0
19.0
00
N:9016415.86 0
E:472333.88
28
28.7
N:9016393.71
E:472313.73
13.7
28
00
10.0
2. Existing plan
W E
3. Additional purpose
-7.0 0
8.00
1:465.223
-6.0
STEEL PLATE BORDES (t = 6 MM)
STEEL PLATE BORDES (t = 6 MM)
STEEL PIPE ∅12 (t=10mm)
A A
+0.00 +0.00
TOP VIEW
(SECTION B-B
ERWIN 2023 05
B tu Hij u Process Exp nsion Project
ERWIN 2023 05
PILE FENDER DESIGN A - TEMPORARY JETTY
M.EDIANSYAH 2023 05
A3